1117 results found for 'Dogger Bank'

1117 results found for 'Dogger Bank'
Order results by

A list of search results

  • 7 April 2021
    Contracts & Tenders, Wind Farm Update

    Spanish manufacturer of rolled rings euskalforging has won a contract to deliver flanges for the 1.2 GW Dogger Bank A offshore wind farm. Under the contract, euskalforging will roll, heat treat, machine, and deliver flanges for all the 95 monopile foundations and transition pieces of the Dogger Bank A. According to the company, this will […]

  • 14 March 2023
    Wind Farm Update

    Several subsea operations are scheduled to soon commence at the sites of the first two phases of the Dogger Bank Wind Farm, currently under construction off the North East coast of England. Later this month, NKT will begin nearshore intervention works in support of the installation of the Dogger Bank B export cable in the […]

  • 23 May 2022
    Wind Farm Update

    The offshore substation topside for Dogger Bank A, the first of the three 1.2 GW phases of the UK’s Dogger Bank Wind Farm, has been completed at Aibel’s yard in Thailand and is now on its way to Haugesund, Norway, where it will undergo further work. The topside is expected to arrive at the yard […]

  • 9 May 2022
    Ports & Logistics, Wind Farm Update

    Smulders has loaded out and sent off the first four of the 95 transition pieces for the first phase of Dogger Bank Wind Farm from its yard in Hoboken, Belgium. The first batch of transition pieces was loaded out on 19 and 20 April and shipped to Sif’s Maasvlakte 2 terminal in Rotterdam, the Netherlands, […]

  • 5 May 2016
    Operations & Maintenance, Technology, Vessels, Wind Farm Update

    Forewind has used its latest operations and maintenance trip to the meteorological masts on Dogger Bank to trial new technology and methodology. The trip enabled aerial inspection and survey contractor Cyberhawk to utilise a new advanced camera technology to inspect the overall status of the met masts and condition of bolts along with the structure of the lattice […]

  • 26 September 2023
    Fixed-Bottom, Green Hydrogen, Planning & Permitting, Power-to-X, Project Updates, Wind Farm Update

    Dogger Bank D, the potential fourth phase of the Dogger Bank Wind Farm, whose first three phases totalling 3.6 GW are currently being built, is planned to have a generation capacity of around 2 GW. If built, the fourth phase would bring the total installed capacity of the UK project – already the world’s largest […]

  • 15 August 2022
    Vessels, Wind Farm Update

    Six of the 95 monopile foundations have been installed at Dogger Bank A, the first of the three 1.2 GW phases that comprise Dogger Bank Wind Farm, the world’s largest offshore wind farm under construction. DEME’s installation vessel Innovation installed the first turbine foundation at the site located around 131 kilometres off the east coast […]

  • 9 July 2021
    Grid Connection, Wind Farm Update

    Delivery of onshore cables for Dogger Bank Wind Farm has started, according to Jones Bros Civil Engineering UK, the company responsible for installing the cables for the first two phases of the offshore wind project. The first drum with the cables has already arrived and Jones Bros are set to commence installation this month. In […]

  • 22 September 2020
    Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farm, a 50:50 joint venture between SSE Renewables and Equinor, has signed a contract with GE Renewable Energy for 190 wind turbines for the Dogger Bank A & B offshore wind project. Dogger Bank A & B will be the world’s first offshore wind farm to use GE’s Haliade-X 13 MW turbines, […]

  • 9 October 2023
    Contracts & Tenders, Jobs & Recruitment, Supply Chain

    High voltage engineering company, Ventus Energy, has secured a contract to supply highly skilled authorised persons (SAPs) for 24/7 support at the 3.6 GW Dogger Bank offshore wind farm in the UK. Awarded to the organisation’s North Shields base in the north-east of England, which is in direct sight of the wind farm’s operational base, […]

  • 19 January 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    DEME Offshore has awarded Greece’s Hellenic Cables with the contract to supply inter-array cables for the third and final phase of the 3.6 GW Dogger bank offshore wind farm – the Dogger Bank C. With this contract, Hellenic Cables has become the sole supplier of inter-array cables for the world’s largest offshore wind farm under […]

  • 27 August 2021
    Operations & Maintenance, Wind Farm Update

    Ryder Geotechnical has completed site-specific assessment (SSA) at the turbine locations of the first two phases of the Dogger Bank offshore wind project. Ryder completed a geotechnical zonation assessment to classify the 190 turbine locations in terms of geotechnical risk to the upcoming jack-up operations at Dogger Bank A and B. According to the company, […]

  • 16 December 2022
    Contracts & Tenders, Wind Farm Update

    UK green energy supplier Octopus Energy Group has signed a Power Purchase Agreement (PPA) with Shell Energy Europe to receive energy generated by the Dogger Bank offshore wind farm. Shell Energy Europe, which has signed agreements to offtake 20 per cent of the energy produced by Dogger Bank, will supply Octopus Energy with up to […]

  • 26 November 2020
    Business & Finance, Wind Farm Update

    Equinor and SSE have reached financial close on the first two phases of the Dogger Bank wind farm project, representing in aggregate the largest offshore wind project financing to date globally. The 3.6 GW Dogger Bank offshore wind project is divided into three 1.2 GW phases, Dogger Bank A, Dogger Bank B, and Dogger Bank C. The […]

  • 27 January 2021
    Contracts & Tenders, Wind Farm Update

    K2 Management has been awarded a four-year contract for construction monitoring on the first two phases of the 3.6 MW Dogger Bank offshore wind farm, Dogger Bank A and Dogger Bank B. The construction monitoring for the project began in late 2020 and will run until Dogger Bank A & B start commercial operation. The […]

  • 10 October 2023
    Vessels

    Last week, North Star took delivery of another hybrid service operations vessel (SOV) leaving the shores of Aberdeen, with the Grampian Derwent setting sail for the 3.6 GW Dogger Bank offshore wind farm in the UK. After completing the final commissioning testing by the technical and rescue teams at North Star, the vessel set sail […]

  • 10 August 2017
    Business & Finance, Wind Farm Update

    Statoil has signed a swap agreement with innogy and SSE for equity interests in the Dogger Bank offshore wind development project.

  • 28 March 2014
    Wind Farm Update

    Forewind submitted its development consent order application for the 2.4 GW Dogger Bank Teesside A&B offshore wind energy proposal to the Planning Inspectorate today. The single application for the development of two offshore wind farms, each with an installed capacity of up to 1.2 gigawatts (GW), was submitted after almost four years of offshore and […]

  • 22 July 2020
    Contracts & Tenders

    Saipem revealed on 22 July that it won three contracts for offshore wind farms in Europe – Dogger Bank A and B, Seagreen, and Saint Brieuc – valued at more than EUR 90 million in total. With the Equinor-SSE Renewables join venture Dogger Bank Offshore Wind Farms, Saipem inked a deal for the transportation and […]

  • 11 September 2023
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first two wind turbines have been installed at Dogger Bank A, the first of the three phases of the UK’s 3.6 GW Dogger Bank Wind Farm, the world’s biggest offshore wind farm under construction. According to a Notice of Operations from the project, the first wind turbine was installed on the 29th of August […]

  • 18 February 2022
    Contracts & Tenders

    UK-based engineering and construction company J. Murphy & Sons (Murphy) has been awarded a multi-million-pound contract for onshore civil works on the export cables for both the 1.4 GW Sofia offshore wind farm and 1.2 GW Dogger Bank C. Although the two large-scale offshore wind farms are being built by different developers, RWE (the owner of […]

  • 24 August 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    North Star Renewables has secured a loan of GBP 96 million (approximately EUR 112 million) from Allianz Global Investors (AllianzGI) to build the three Service Operations Vessels (SOVs) that will serve the Dogger Bank offshore wind farm.  The vessel owner said the loan added to its own balance sheet and equity commitments from its 100 per cent shareholder, […]

  • 12 August 2024
    Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    A multibeam echosounder (MBES) geophysical survey of the Dogger Bank D offshore wind site, using several uncrewed surface vessels (USVs), is scheduled to start on 13 August. According to information in the project’s Notice to Mariners, XOCEAN will deploy multiple USVs to survey the wind turbine array site and the export cable route. The USVs will […]

  • 2 June 2023
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Correll Group, Cable Installation & Power Services Division has been contracted by DEME Offshore to complete the inter-array cable termination & testing on wind turbines and the offshore substation platform on the first phase of the Dogger Bank offshore wind farm in the UK. The 3.6 GW Dogger Bank Wind Farm is being built in […]

  • 14 October 2020
    Contracts & Tenders

    Waves Group has secured a contract to provide marine warranty surveyor services for the Dogger Bank offshore wind project in the UK. Waves Group is providing the services for Dogger Bank A, which involves the installation of foundations, infield cables, turbines, export cables and one offshore substation and the foundation for Dogger Bank B.  Operations […]

  • 3 February 2022
    Wind Farm Update

    The Netherlands-based foundation manufacturer Sif Group has completed the first several monopiles for the world’s largest offshore wind farm under construction – the 3.6 GW Dogger Bank in the UK. Sif manufactured the monopiles at its factory on Maasvlakte 2 in the Port of Rotterdam. The monopiles produced will be installed on the 1.2 GW […]