Search results for: Kriegers Flak

328 results

A list of search results

  • 31 January 2013
    Authorities, Contracts & Tenders, Wind Farm Update

    The Danish Energy Agency (DEA) has published details of the tender process and the provisional timetable for the planned 1,500 MW of offshore wind power to be set up by 2020. Since March 2012, it has been evident that Denmark should have two large offshore wind farms and several coastal offshore wind turbines to meet […]

  • 3 December 2019
    Wind Farm Update

    Danish rubber manufacturer RG Rom Gummi A/S has won a contract to carry out the vulcanization of neoprene on boat landing stubs for the Vattenfall’s Kriegers Flak offshore wind project. The 605MW Kriegers Flak will comprise 72 Siemens Gamesa 8MW turbines installed some 15-40 kilometres off the Danish coast. The turbines will be installed on […]

  • 7 January 2016
    Grid Connection, Wind Farm Update

    Energinet.dk is looking for an EPCI contractor for two gravity-based substructures for substations at Kriegers Flak offshore wind farm in the Baltic Sea. The scope of work includes detailed engineering, procurement, construction and offshore installation based on the basic design and general specifications of two gravity-based substructures (GBS) for KFA and KFBE offshore substations. The substructures will be used as foundations […]

  • 4 April 2018
    Grid Connection, Wind Farm Update

    Energinet has resumed onshore cable installation works for the Kriegers Flak offshore wind farm after the winter break, and is now ready to start with the final stage of cable excavation on land.

  • 23 February 2018
    Grid Connection, Wind Farm Update

    The foundation for the second Kriegers Flak offshore substation was installed on 22 February, a few days after Jan de Nul installed the first one.

  • 23 April 2021
    Authorities, Wind Farm Update

    Vattenfall has been granted a Natura 2000 permit for the Kriegers Flak offshore wind farm in Sweden by the Administrative Board of Skåne County, off whose coast the developer aims to build the 640 MW project. Parts of the Kriegers Flak site in the Baltic Sea have been classified as a Natura 2000 area and, […]

  • 12 May 2020
    Wind Farm Update

    The first three transition pieces for the Kriegers Flak offshore wind farm have been loaded onto a barge and are ready for installation, Bladt Industries said. The remaining 69 transition pieces will follow during the year. The last transition piece is scheduled to leave Bladt’s facility in Aalborg in the third quarter of 2020, Bladt […]

  • 23 November 2017
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Hollandia Offshore and Croonwolter&dros have moved the Kriegers Flak B (KFB) offshore substation topside from Hollandia Offshore’s production hall in Krimpen aan den IJssel and into the yard.  

  • 21 December 2018
    Contracts & Tenders, Vessels

    Vattenfall has contracted Van Oord for the transport and installation of the foundations for the Kriegers Flak offshore wind farm.

  • 17 March 2016
    Business & Finance, Grid Connection, Wind Farm Update

    Denmark’s Energinet.dk has selected the Copenhagen-headquartered ISC Consulting Engineers A/S as designers of two offshore substations for the planned 600MW Kriegers Flak offshore wind farm. The design contract comprises fully detailed design and follow-up of a 200MW offshore substation – named Kriegers Flak A (KFA) and a 400MW offshore substation – named Kriegers Flak B (KFB). KFB will […]

  • 18 September 2019
    Contracts & Tenders, Wind Farm Update

    Vattenfall has invited companies to pre-qualify for boulder clearance work on the 605MW Kriegers Flak offshore wind farm in the Danish Baltic Sea. The clearance of boulders would be carried out on the seabed at 72 wind turbine locations. The clearance is to be carried out with a vessel with a grab, and possibly by […]

  • 23 August 2017
    Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    An export cable for the 600MW Kriegers Flak offshore wind farm made a successful landfall at Rødvig, Denmark, Energinet reports.

  • 29 October 2015
    Wind Farm Update

    The Danish Energy Agency (DEA) has prequalified a total of seven companies and consortia to participate in the tender of Denmark’s largest offshore wind farm, the 600MW Kriegers Flak in the Baltic Sea. Of the eight applications, the DEA received before the deadline October 1, the Agency has prequalified seven companies and consortia to bid […]

  • 6 September 2021
    Wind Farm Update

    His Royal Highness the Crown Prince of Denmark, together with Danish Minister for Industry, Business and Financial Affairs, Simon Kollerup, has inaugurated Vattenfall’s 604 MW Kriegers Flak offshore wind farm. With 72 Siemens Gamesa 8.4 MW wind turbines and a capacity corresponding to the annual energy consumption of approximately 600,000 Danish households, Kriegers Flak is Denmark’s […]

  • 7 July 2020
    Grid Connection

    Kriegers Flak Combined Grid Solution (CGS) has transmitted the first power between Denmark and Germany. The high-voltage cable system connects the Danish region of Zealand with the German state of Mecklenburg-Western Pomerania via the 605 MW Kriegers Flak and 288 MW Baltic 2 offshore wind farms. It is the world’s first offshore interconnector using the national […]

  • 26 October 2017
    Contracts & Tenders

    Vattenfall is reconsidering building a 420MW offshore wind farm in the Swedish part of Kriegers Flak in the Baltic Sea as a result of recent cost reductions in offshore wind, the company told Offshore WIND.

  • 14 December 2017
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Vattenfall has chosen Klintholm Harbour in Denmark as its base for the servicing and maintenance of the 605MW Kriegers Flak offshore wind farm.

  • 23 May 2019
    Wind Farm Update

    Rostock-based EEW Special Pipe Constructions GmbH has started manufacturing the monopiles for Vattenfall’s 605MW Kriegers Flak offshore wind farm. The first pipe for the Danish offshore wind farm was made in the Rostock production site this May. By September 2019, all 72 monopiles will have been produced and coated, according to the company. In spring […]

  • 8 March 2018
    Technology, Wind Farm Update

    Greek Assodivers Underwater Contractors have taken delivery of two MERMAC winches from MacArtney to be used on the Kriegers Flak offshore wind project in the Danish Baltic Sea.

  • 25 September 2017
    Contracts & Tenders, Wind Farm Update

    Vattenfall has invited tenders for the installation of foundations for three projects in Denmark: Danish Kriegers Flak in the Baltic Sea, and Vesterhav Nord and Vesterhav Syd in the North Sea.

  • 12 October 2015
    Environment, R&D

    Birds and seals have got GPS transmitters on them, and the birds are monitored with radar in preparation for the establishment of Kriegers Flak offshore wind farm. It is a requirement for large construction projects such as ports, bridges and wind farms, that they must not affect the nature significantly. This requirement is particularly important […]

  • 14 November 2016
    Business & Finance, Grid Connection, Wind Farm Update

    Energinet.dk and 50Hertz Transmission GmbH have awarded Iemants and Jan De Nul Group with a contract to construct, install, ballast and protect gravity based foundations (GBFs) for two offshore substations. The two offshore substations will serve Vattenfall’s 600MW Kriegers Flak offshore wind farm in the Danish part of the Baltic Sea, and will also serve as an interconnector between […]

  • 7 June 2021
    Wind Farm Update

    The final of the 72 Siemens Gamesa 8.4 MW wind turbines was installed at Kriegers Flak, Denmark’s largest offshore wind farm, on Saturday, 5 June. The next steps will be to finalise testing and certification of the 604 MW wind farm so that it can be inaugurated after the summer, Vattenfall, the wind farm’s owner […]

  • 29 January 2016
    Grid Connection

    The Danish Energy Agency (DEA), Energinet.dk, and Kriegers Flak tenderers will hold a meeting on 2 February.  They will discuss grid connection, platforms and technical issues regarding the 600MW offshore wind farm in the Baltic Sea. The DEA has prequalified seven companies and consortia to participate in the tender for the project. The decision of the winner is expected […]

  • 7 April 2016
    Business & Finance

    DEME Concessions Wind and Siemens Financial Services have joined Kriegers Flak ApS, a project company set up by EnBW for participating in Kriegers Flak tender procedure.  The project company submitted an indicative offer for the construction of the Danish offshore wind farm on 5 April – as was stipulated by the Danish government in the tender procedure. This […]

  • 17 January 2018
    Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

    A barge loaded with two gravity-based foundations (GBFs) for the high voltage station of the 605MW Kriegers Flak offshore wind farm has arrived in Koge, Denmark, Blue Water Shipping (BWS), the port agents for the project, told Offshore WIND.