172 results found for 'Empire Wind 1'

172 results found for 'Empire Wind 1'
Order results by

A list of search results

  • 5 January 2024
    Contracts & Tenders, Project Updates, Supply Chain, Wind Farm Update

    Great Lakes Dredge & Dock (GLDD), together with its consortium partner Van Oord, has been informed by Empire Offshore Wind, a joint venture between BP and Equinor, of the termination of the rock installation contract for the Empire Wind 2 offshore wind project which was set to commence in 2026. In 2022, the GLDD-Van Oord […]

  • 18 July 2024
    Authorities, Planning & Permitting

    The New York State Energy Research and Development Authority (NYSERDA) has launched the state’s fifth offshore wind solicitation, with proposals due by 9 September. The offshore wind solicitation includes provisions such as inflation indexing, labor provisions, stakeholder engagement requirements, and disadvantaged community commitments, according to NYSERDA. A webinar will be held on 22 July to […]

  • 22 October 2021
    Business & Finance, Grid Connection

    Nexans is set to open the first U.S. high-voltage subsea cable facility in Charleston, South Carolina, on 9 November. The transformed subsea cable plant will support the expanding US offshore wind market, Nexans said. The company plans to create more than 200 new jobs for the industry by the end of the year. To remind, […]

  • 1 August 2023
    Business & Finance, Business development, Wind Farm Update

    BP and Equinor are in the process of renegotiating the power purchase agreements (PPAs) for their joint offshore wind projects in the USA, according to Reuters. The partners do not plan on developing the projects off the US East Coast unless they meet the ”return thresholds of 6% to 8%”, Reuters quoted bp’s CEO Bernard […]

  • 14 August 2024
    Authorities, Business & Finance, Contracts & Tenders, Fixed-Bottom, Planning & Permitting

    Equinor and Virginia Electric and Power Co, a subsidiary of Dominion Energy, have provisionally won lease areas in the Central Atlantic offshore wind auction in the US, each securing one site. The auction, which yielded almost USD 93 million (around EUR 84 million), saw a total of six companies participating. Equinor is provisionally awarded the […]

  • 10 February 2022
    R&D, Technology

    Danish wind turbine manufacturer Vestas has installed the mould for the 115.5-metre turbine blades to be installed on the V236-15 MW prototype offshore wind turbine later this year. The mould was installed at the company’s blades factory in Nakskov, Denmark. Vestas plans to install the prototype turbine at the Østerild National test centre for large […]

  • 13 October 2022
    Contracts & Tenders, Vessels

    The first steel has been cut for the offshore wind installation vessel (WIV) ordered by Maersk Supply Service at the Sembcorp Marine shipyard in Singapore. In March, the Denmark-based Maersk Supply Service ordered a wind turbine installation vessel and won its first contract with Equinor and BP to install wind turbines at the Empire Wind 1 and […]

  • 24 January 2023
    R&D, Technology

    The Offshore Wind Innovation Hub, led by Equinor and BP, has opened for business and announced its first call for applications to help accelerate the development phase of offshore wind in New York. The Accelerator Program is looking for start-ups that provide innovative technology and solutions related to the development of offshore wind in New […]

  • 30 March 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    French power cable manufacturer Nexans has signed a preferred supplier agreement with Empire Offshore Wind LLC to connect the Empire Wind offshore projects to the New York State’s onshore grid. The turnkey projects cover the full design and manufacturing, as well as the laying and protection of over 300 kilometres of export cables that will […]

  • 1 September 2023
    Authorities, Business & Finance, Wind Farm Update

    This summer, the developers of the Sunrise Wind (Ørsted and Eversource) and Empire Wind 1 & 2 and Beacon Wind projects (Equinor and BP) filed petitions with the New York State Public Service Commission (PSC), seeking price adjustments to their contracts with the New York State Energy Research and Development Authority (NYSERDA). In response to […]

  • 15 February 2022
    Contracts & Tenders, Wind Farm Update

    Empire Offshore Wind has awarded the engineering consulting group, COWI, with a contract to deliver a turnkey design for the wind turbine foundations for the Empire Wind 1 and 2 projects off the coast of Long Island, New York. This is COWI’s largest offshore wind engineering contract in the US to date, the company said. […]

  • 10 June 2022
    Contribution, R&D, Technology

    Equinor and BP have launched an Offshore Wind Innovation Hub in New York that they say will facilitate partnerships with start-ups that bring new technological solutions to the growing US offshore wind industry. The initiative is being led by Equinor on behalf of its 50/50 joint venture with BP and is a result of a […]

  • 4 May 2022
    Contracts & Tenders, Wind Farm Update

    Equinor and BP have selected a consortium between Van Oord and Great Lakes Dredge & Dock (GLDD) for subsea rock installation works for their Empire Wind 1 and Empire Wind 2 offshore wind farms in New York. The consortium plans to start operations at the offshore wind farm sites in the mid-2020s, with Van Oord […]

  • 17 May 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dutch offshore wind foundation manufacturer, Sif, has started the production of monopile foundations for the third phase of the Dogger Bank Wind Farm in the UK, the world’s biggest offshore wind farm under construction. According to a trading update Sif issued on 17 May, the company — which is delivering foundations for all three phases […]

  • 8 February 2023
    Contracts & Tenders

    Equinor and BP have selected Skanska USA as the construction manager for the port upgrade of New York’s South Brooklyn Marine Terminal (SBMT). Port upgrades to redevelop SBMT were part of the Empire Wind 2 and Beacon Wind 1 project proposals Equinor and BP submitted in the 2021 offshore wind power solicitation in the State of New […]

  • 4 April 2022
    Vessels

    Kongsberg Maritime (KM) has won two contracts, one with Integrated Wind Solutions (IWS) to supply two Commissioning Service Operation Vessels (CSOVs) with integrated equipment solution, and the other with Sembcorp Marine to supply the Wind Turbine Installation Vessel (WTIV) with comprehensive technology package. Under the contract with IWS, KM will supply CSOVs with an integrated […]

  • 24 June 2024
    Authorities, Fixed-Bottom, Planning & Permitting

    The US Bureau of Ocean Energy Management (BOEM) has approved Sunrise Wind’s construction and operations plan (COP), marking the final approval needed for the federal agency to move the 942 MW offshore wind project toward the start of offshore construction. Sunrise Wind, New York’s largest offshore wind project, is being developed by Ørsted and Eversource […]

  • 23 August 2022
    Technology

    Vestas has completed the prototype nacelle for the V236-15.0 MW™ offshore wind turbine at its factory in Lindø, Denmark. The new design is now ready for testing, the wind turbine manufacturer said via social media. The turbine will undergo mechanical testing, as well as strict control of its vital controlling software, and the test programme […]

  • 23 May 2024
    Supply Chain, Vessels

    The keel for the first Jones Act-compliant subsea rock installation vessel (SRIV) for the US offshore wind industry, Acadia, was laid on 2 May at the Philly Shipyard in Philadelphia, Pennsylvania. The vessel was ordered by Great Lakes Dredge & Dock Corporation (GLDD) in 2021 and the first steel for the SRIV was cut in […]

  • 29 March 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    The recently announced wind turbine installation vessel (WTIV) for which Singapore’s Sembcorp Marine won a shipbuilding contract is now confirmed to have been ordered by Maersk, whose subsidiary Maersk Supply Service has just revealed that it signed a firm contract with a joint venture between Equinor and BP for the installation of the Empire 1 […]

  • 17 January 2022
    Authorities, Contracts & Tenders, Wind Farm Update

    Equinor and BP have finalised the Purchase and Sale Agreements (PSAs) with the New York State Energy Research and Development Authority (NYSERDA) for their Empire Wind 2 and Beacon Wind 1 projects, after being selected in the state’s offshore wind power solicitation in January 2021. The finalisation of the agreements was announced at an event […]

  • 10 July 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted and Eversource have finalized the transaction for Eversource’s share in the Sunrise Wind offshore wind project, initially announced in January. Ørsted has acquired its former partner’s stake for USD 78 million (approximately EUR 72 million) less than the originally agreed price earlier this year. In the agreement signed in January, the two companies agreed […]

  • 24 March 2021
    Ports & Logistics

    Carver Companies (P&M Brick), the owner of the Port of Coeymans deep water inland marine terminal, has filed an application with the New York State Department of Environmental Conservation for an environmental permit for the upgrade of the port infrastructure to support offshore wind projects. The Port of Coeymans Offshore Wind Infrastructure (POWI) Project proposes […]

  • 3 April 2023
    Business development, Technology

    Last week, three months after it was installed at the National Test Center for large wind turbines in Østerild, Denmark, Vestas’s V236-15.0 MW prototype wind turbine reached its nominal power rating of 15 MW. The company’s new flagship wind turbine produced its first electricity shortly after being installed in December 2022 and has started operating at […]

  • 30 December 2022
    R&D

    Vestas’ V236-15.0 MW prototype wind turbine has produced its first kWh after being fully assembled at the Østerild National test centre for large wind turbines in Western Jutland, Denmark. The wind turbine prototype will now undergo an extensive test and verification programme to ensure reliability before full-type certification and serial production begins. The prototype development […]

  • 22 December 2022
    R&D, Technology

    The full blade set for the Vestas V236-15.0 MW™ prototype offshore wind turbine has arrived to Østerild National Test Centre in Denmark where they will be installed. The blade set arrived at the port of Hanstholm on Sunday, 18 December, and was then transported to Østerild National Test Centre. The 115.5-metre blades for the prototype […]