59 results found for 'Fryslân'

59 results found for 'Fryslân'
Order results by

A list of search results

  • 15 April 2020
    Grid Connection, Wind Farm Update

    The transformer station of the Windpark Fryslân nearshore wind project has started taking shape at Breezanddijk in the Netherlands. According to the project developer, work is being done on the 382.7 MW wind farm despite the coronavirus situation. Located south of the Afsluitdijk and some six kilometers off the Frisian coast, Windpark Fryslân will comprise 89 4.3MW […]

  • 18 July 2019
    Contracts & Tenders, Wind Farm Update

    Dutch energy company Eneco has signed an agreement with Windpark Fryslân to purchase all the power generated at the Fryslân nearshore wind farm in the Netherlands for a period of 15 years. The Fryslân wind farm will produce 1,500 GWh of energy annually. To use the power as locally as possible, companies and organizations in the […]

  • 10 January 2020
    Ports & Logistics, Wind Farm Update

    Siemens Gamesa has selected TMA Logistics to provide the storage and transshipment of wind turbines for the Windpark Fryslân nearshore wind farm project at its terminal in the Port of Amsterdam. Located in the IJsselmeer and some six kilometres off the Frisian coast, the 382.7MW Windpark Fryslân will comprise 89 Siemens Gamesa 4.3MW wind turbines […]

  • 3 August 2018
    Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    Windpark Fryslân B.V. has selected the consortium of Siemens Gamesa Renewable Energy and Van Oord as the preferred contractor for the construction of the Fryslân nearshore wind farm in the Netherlands.

  • 17 January 2020
    Contracts & Tenders

    Bijlsma Constructies has won a contract to deliver 89 internal platforms for the Windpark Fryslân nearshore wind farm project in the Netherlands. The Dutch company will start production in March and is expected to complete all the platforms in July. Windpark Fryslân is being built by Zuiderzeewind, a consortium of Van Oord and Siemens Gamesa […]

  • 10 December 2019
    Jobs & Recruitment, Wind Farm Update

    Ventolines has selected Marine Coordination Services to supply a range of support personnel for the construction phase of the 382.7MW Windpark Fryslân offshore wind farm in the Netherlands. The arrangement will include the supply of QA, QC inspectors, auditors, and client representatives. “We are glad to be able to offer our support to Windpark Fryslân,” […]

  • 2 October 2019
    Wind Farm Update

    Windpark Fryslân has achieved the financial close for the 382.7 MW Windpark Fryslân nearshore wind farm in the IJsselmeer, the Netherlands. Ten banks and the province of Fryslân are jointly financing Windpark Fryslân, which is being built south of the Afsluitdijk, six kilometers off the Frisian coast. The nearshore wind farm is being built by […]

  • 24 May 2021
    Grid Connection, Wind Farm Update

    The installation of inter-array cables has been completed at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake in the Netherlands. The inter-array cables will undergo tests in the coming days, Windpark Fryslân said. The cables connect the wind farm’s 89 Siemens Gamesa 4.3 MW wind turbines with the wind farm’s own transformer station […]

  • 20 December 2019
    Contracts & Tenders, Wind Farm Update

    Van Oord has selected Tekmar Energy’s Cable Protection System (CPS) TekLink® Mechanical Latch for the Windpark Fryslân nearshore wind farm in the Netherlands. The 382.7MW Windpark Fryslân comprises 89 Siemens Gamesa 4.3MW wind turbines to be installed in the IJsselmeer some six kilometers off the Frisian coast. Tekmar Energy is providing 167 cable protection systems […]

  • 4 January 2021
    Wind Farm Update

    Van Oord has started installing inter-array cables at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake, the Netherlands. The installation work started in December, as planned, a spokesperson for Windpark Fryslân said. The inter-array cables will first come to shore at the wind farm’s own transformer station at Breezanddijk on the artificial island […]

  • 7 September 2020
    Wind Farm Update

    Van Oord has installed the first of the 89 monopiles at the Windpark Fryslân in the IJsselmeer Lake, the Netherlands. The remaining 88 foundations are expected to be installed by January 2021, Windpark Fryslân said. Unique Installation Approach – Sarens Soccer Pitch The 382.7 MW Windpark Fryslân is being built in the Frisian part of the IJsselmeer […]

  • 13 July 2020
    Wind Farm Update

    Zuiderzeewind, a consortium of Van Oord and Siemens Gamesa Renewable Energy, plans to finish building the artificial island near Kornwerderzand, the Netherlands, in September. The island, which will first serve as the construction stage for the Windpark Fryslân nearshore project and after that as a nature reserve and a bird sanctuary, is located next to […]

  • 20 January 2020
    Vessels, Wind Farm Update

    Van Oord’s crane vessel Werkendam has arrived at the IJsselmeer to start working on the Windpark Fryslân nearshore wind farm project. The vessel will be involved in the construction of an artificial island off the Frisian coast, Windpark Fryslân said. With a land area of 2ha and a submerged, shallow water area of 25ha, the […]

  • 30 October 2020
    Contracts & Tenders, Grid Connection

    Visser & Smit Hanab has secured a contract by Van Oord to perform inter-array cable termination and testing work at the Windpark Fryslân nearshore wind farm in the Netherlands. The routing, termination and testing activities will commence as soon as the cable installation starts. Visser & Smit Hanab is also in charge of installing the […]

  • 24 March 2021
    Wind Farm Update

    The first of the 89 Siemens Gamesa 4.3 MW wind turbines has been installed at Windpark Fryslân, the world’s largest wind farm in inland fresh waters. Located in the IJsselmeer Lake and some six kilometres off the Frisian coast, the Netherlands, the 382.7 MW Windpark Fryslân wind farm is being constructed by the Zuiderzeewind consortium […]

  • 8 December 2021
    Wind Farm Update

    The 382.7 MW Windpark Fryslân, the largest wind farm built in a body of fresh water, has been fully commissioned. Located in the IJsselmeer Lake in the Netherlands, Windpark Fryslân comprises 89 Siemens Gamesa 4.3 MW wind turbines which have been fully tested and in operation since November. Data at the project’s website shows that the […]

  • 23 December 2020
    Wind Farm Update

    Van Oord has installed all of the 89 foundations at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake, the Netherlands. Van Oord installed the first monopile at the site in the Frisian part of the IJsselmeer near Breezanddijk in September. Due to the shallows in the IJsselmeer and the width of the locks, […]

  • 30 January 2020
    Contracts & Tenders

    Van Oord has awarded Vos Prodect Innovations with a contract to deliver cable hang-off systems for the Windpark Fryslân nearshore wind project in the Netherlands.

  • 26 February 2021
    Environment, Wind Farm Update

    The installation of Siemens Gamesa turbines at the Windpark Fryslân nearshore wind farm in the Netherlands is set to commence at the beginning of March. The 382.7 MW Windpark Fryslân will comprise 89 Siemens Gamesa 4.3 MW turbines located in the IJsselmeer Lake. According to the project developer, all preparations are almost ready, Van Oord installed the final […]

  • 11 July 2018
    Authorities, Wind Farm Update

    The Council of State dismissed eight objections filed against the final permits for Windpark Fryslân and thus cleared the way for the construction of the project in the Frisian part of the IJsselmeer near Breezanddijk in the Netherlands.

  • 25 July 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Dutch contractor Visser & Smit Hanab, part of Volker-Wessels, has won a contract to install power cables that will link the Fryslân offshore wind farm in the IJsselmeer to the Dutch grid.

  • 25 May 2021
    Wind Farm Update

    Turbine installation at the Windpark Fryslân will last longer than initially expected, the developer of the nearshore wind farm in the IJsselmeer Lake in the Netherlands said. The installation of the wind farm’s 89 Siemens Gamesa 4.3 MW started this spring and was initially expected to be completed by the beginning of Summer 2021. The […]

  • 2 November 2020
    Wind Farm Update

    Aarsleff BIZ has delivered the last 17 Concrete Work Platforms (CWPs) built in Poland for the Windpark Fryslân nearshore project in the Netherlands. In total, Aarsleff BIZ, a Per Aarsleff company, built and delivered 89 CWPs for the 382.7 MW wind farm at its factory in Swinoujscie. The CWPs, each weighing 76 tonnes, will be […]

  • 1 September 2020
    Ports & Logistics, Wind Farm Update

    The first shipment of wind turbine blades for the Windpark Fryslân project has been unloaded at the TMA Terminal in the Port of Amsterdam, TMA Logistics said. Located in the IJsselmeer Lake and some six kilometres off the Frisian coast, the 382.7MW Windpark Fryslân will comprise 89 Siemens Gamesa 4.3 MW wind turbines. Siemens Gamesa selected TMA […]

  • 12 April 2021
    Wind Farm Update

    The first wind turbine at Windpark Fryslân has begun producing electricity, according to a project update published on social media on 12 April. The first of the total of 89 Siemens Gamesa 4.3 MW wind turbines was installed at the project site at the end of the last month. Located in the IJsselmeer Lake in […]

  • 21 September 2020
    Wind Farm Update

    Aarsleff BIZ, a Per Aarsleff company, has loaded out the first batch of concrete work platforms (CWPs) for the Windpark Fryslân nearshore wind farm in the Netherlands at its factory in Swinoujscie, Poland. The CWPs, each weighing 76 tonnes, will be mounted on the project’s monopiles, which are currently being installed at the project site in the […]