  • 12 January 2024
    Business development, Environment, Fixed-Bottom, R&D, Research & Development

    Ørsted and Van Oord, through their Ocean Health initiative, will install innovative droppable oyster structures at the 752 MW Borssele 1&2 offshore wind farm in the Netherlands to introduce European flat oysters and improve biodiversity in the wind farm. The new installation method will allow affordable and manual deployment of oyster broodstock, according to Ørsted. […]

  • 10 October 2023
    Contracts & Tenders, Operations & Maintenance, Supply Chain

    UK-based Specialist Marine Consultants (SMC) has been awarded two contracts by Ørsted to continue delivering structural inspections above water (SIAW) across the company’s offshore wind portfolio. The SIAW contracts, which will run until 2026, will see SMC continue to deliver inspection and maintenance works of external, internal, and confined space areas of the foundation, transition […]

  • 30 November 2023
    Business & Finance, Business development, Collaboration, Environment, Fixed-Bottom, Floating Wind, Grid Connection, Industry, Operations & Maintenance, Outlook & Strategy, Planning & Permitting, Ports & Logistics, Power-to-X, Project Updates, Supply Chain, Transition

    The offshore wind industry, now the linchpin between several offshore energy industries, is calling for both innovation and accelerating deployment, while also making sure one does not impede the progress of the other.  

  • 7 September 2023
    Business & Finance, Collaboration, Outlook & Strategy

    Offshore wind developer, Deep Wind Offshore, has secured Octopus Energy as a new investor to accelerate international expansion and strengthen Norwegian projects, according to the company. Octopus Energy will join the ownership side of the company, Deep Wind Offshore said, together with the existing industrial owners Knutsen OAS, Haugaland Kraft, and SKL. Deep Wind Offshore […]

  • 10 April 2020
    Wind Farm Update

    DEME has installed half of the 94 monopile foundations at the Borssele 1+2 offshore wind farm site.

  • 27 November 2020
    Wind Farm Update

    Ørsted’s first offshore wind farm in the Netherlands, Borssele 1 & 2, has been fully commissioned. Located 22 kilometres off the coast of the province of Zeeland, the 752 MW project has now become the largest offshore wind farm in the Netherlands and the second largest operating offshore wind farm in the world, providing enough […]

  • 13 February 2020
    Vessels, Wind Farm Update

    DEME Offshore’s jack-up Innovation has installed 18 out of 94 monopile foundations on the 752MW Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation is loading the monopiles and the transition pieces at Sif’s facility on Maasvlakte 2 in Rotterdam and installing them at the site some 22 kilometres off the coast of […]

  • 2 November 2018
    Contracts & Tenders, Jobs & Recruitment, Wind Farm Update

    Ørsted has selected ERSG to supply temporary specialist staff for the Borssele 1+2 offshore wind project in the Dutch North Sea.

  • 2 September 2020
    Wind Farm Update

    DEME Offshore has completed the installation of the 94 Siemens Gamesa 8 MW turbines at the Borssele 1 & 2 offshore wind farm in the Netherlands. DEME’s jack-up tandem Sea Installer and Sea Challenger were in charge of the installation at the site located 22km off the coast of the province of Zeeland. The first turbine was […]

  • 13 January 2020
    Wind Farm Update

    DEME Group has installed the first foundations at Ørsted’s Borssele 1&2 offshore wind project in the Netherlands. DEME’s jack-up vessel Innovation loaded the first set of monopiles at Sif’s facility on Maasvlakte 2 earlier this month and transported them to the wind farm. “The first monopile installed was also the heaviest and tallest on the wind farm, […]

  • 6 August 2020
    Business & Finance, Wind Farm Update

    The European Investment Bank (EIB) has approved a EUR 500 million financing for the Borssele 1 & 2 offshore wind project in the Netherlands. At the beginning of the year, Ørsted applied for a loan with the EIB which will finance the construction and the operation of the 752 MW wind farm. The estimated value […]

  • 4 June 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has completed the installation of the 94 monopile foundations at the Borssele 1 & 2 offshore wind project. The installation, which began in mid-January in the Dutch North Sea, was completed on time despite the COVID-19 crisis, DEME said. Sif provided 47 monopiles for the project and EEW SPC, the parent […]

  • 7 November 2018
    Business & Finance, Contracts & Tenders, Grid Connection

    Nexans will provide up to 190km of inter-array cable rated at a maximum operating capacity of 72.5kV for the 752MW Borssele 1 and 2 offshore wind project in the Netherlands as part of the recently-announced contract.

  • 30 January 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has installed 13 of the 94 monopile foundations on the 752MW Borssele 1&2 offshore wind farm in the Dutch North Sea, Ørsted said. Innovation is loading the monopiles and transition pieces at Sif’s Maasvlakte 2 facility before transporting and installing them at the site located some 22 kilometres off the […]

  • 29 April 2020
    Wind Farm Update

    Ørsted’s Borssele 1 & 2 offshore wind farm has delivered first power to the Dutch grid. According to the Danish company, the first Siemens Gamesa 8 MW turbine began producing electricity on 28 April. “This is a big milestone for Borssele 1 & 2. Ørsted is doing its utmost to allow the construction of the […]

  • 14 May 2020
    Wind Farm Update

    Ørsted has provided an update on the ongoing offshore construction work at the 752 MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, saying that all activities are going according to plans. So far, DEME’s installation vessel Innovation has installed 73 out of the 94 monopile foundations at the site some […]

  • 9 February 2021
    Wind Farm Update

    Manor Renewable Energy (MRE) has completed its work to provide temporary power during the turbine commissioning phase at the Borssele 1 & 2 offshore wind farm in the Netherlands. MRE supplied modular temporary power packages, consisting of a 116 kVA generator, custom-built fuel tank and bespoke lifting frames. Manor Venture, Manor Initiative and Manor Enterprise […]

  • 12 November 2021
    Business & Finance, Wind Farm Update

    Ørsted has signed a EUR 175 million, 8-year loan agreement with the Nordic Investment Bank (NIB) for co-financing its investment in the Borssele 1 & 2 offshore wind farm in the Netherlands. Together with the loan agreement closed with the European Investment Bank (EIB) on 6 September, the intended long-term financing of Ørsted’s investment in […]

  • 24 October 2018
    Business & Finance, Contracts & Tenders, Jobs & Recruitment, Wind Farm Update

    UK-based EEW OSB has secured a contract to provide 35 transition pieces for Ørsted’s Borssele 1 + 2 offshore wind farm in the Dutch North Sea.

  • 27 September 2019
    Contracts & Tenders, Grid Connection

    Dutch energy network company Alliander and Ørsted have signed an agreement through which Alliander will purchase green certificates from the Borssele 1+2 offshore wind farm. The agreement takes effect in 2021 and has a duration of fifteen years. Alliander aims to have a climate-neutral business operation by 2023. The annual CO2-emissions of the company are mainly […]

  • 1 June 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has arrived at the Borssele 1+2 offshore wind farm in the Dutch North Sea with the final monopiles. Innovation picked up the monopiles last night at Sif Rotterdam, a spokesperson from DEME Offshore said. Sif was in charge of providing 47 monopiles for the project, with EEW SPC, the parent […]

  • 13 April 2020
    Wind Farm Update

    The first Siemens Gamesa 8 MW turbine has been installed on the 752 MW Borssele 1+2 offshore wind farm in the Dutch North Sea. The team working on DEME’s jack-up Sea Challenger installed the wind farm’s first turbine over the weekend, Ørsted said. In total, the wind farm will comprise 94 of the Siemens Gamesa […]

  • 21 July 2020
    Wind Farm Update

    Ørsted has shared an update on construction activities at the site of the 752 MW Borssele 1&2 wind farm in the Dutch North Sea. DEME’s jack-up tandem of Sea Installer and Sea Challenger has now installed two-thirds of the wind farm’s 94 Siemens Gamesa 8 MW wind turbines. The inter-array cables have been laid and […]

  • 1 May 2020
    Operations & Maintenance

    NHV Group has started carrying out its helicopter services for the Borssele 1 & 2 offshore wind farm in the Netherlands. The flights depart from NHV’s recently installed base in Arnemuiden, Midden-Zeeland, to the project site located 23km from Westkapelle. The company stated it had taken delivery of a new H145 aircraft for the Midden-Zeeland […]

  • 17 March 2020
    Wind Farm Update

    30 monopile foundations and 14 inter-array cables have so far been installed on the 752MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, Ørsted said. Located some 23 kilometres off the coast of Zeeland, Borssele 1 + 2 will comprise 94 Siemens Gamesa 8MW wind turbines scheduled to be operational by […]

  • 9 January 2020
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has loaded the first set of monopiles to be installed on the Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation loaded the first set of monopiles at Sif’s facility on Maasvlakte 2 in the Port of Rotterdam. DEME is in charge of transporting and installing the 94 monopile […]