252 results found for 'Arkona offshore wind farm'

252 results found for 'Arkona offshore wind farm'
Order results by

A list of search results

  • 15 October 2025
    Fixed-Bottom, Operations & Maintenance, Technology

    RWE said on 15 October it had completed more than 80 successful cargo drone flights to offshore wind turbines in Germany, marking what it described as a milestone for the offshore wind industry. The company said the tests demonstrated the technical feasibility of using drones to deliver tools and spare parts directly to wind turbines […]

  • 25 September 2025
    Business & Finance, Contracts & Tenders, Grid Connection, Offshore Platforms, Supply Chain

    RWE has awarded Semco Maritime with a framework agreement for the maintenance of German offshore substations. The agreement, commencing in September 2025, will continue through 2027 and includes a two-year extension option. Semco Maritime’s scope of work includes scheduled and unscheduled maintenance above water and troubleshooting services of the auxiliary equipment at RWE’s offshore substations […]

  • 21 July 2025
    Vessels

    The keel for Bibby Marine’s hybrid methanol battery-powered commissioning service operation vessel (eCSOV), which will serve the offshore wind industry, has been laid at the Armon Shipyard in Vigo, Spain. When announcing the vessel construction in early 2024, Bibby Marine said this would be “the world’s first truly zero-emission” eCSOV. The vessel, designed in collaboration […]

  • 15 May 2025
    Operations & Maintenance

    German transmission system operator (TSO) 50Hertz has unveiled its plans to build a new operating site in Rostock on the Baltic Sea to support its offshore operations. The 90-million facility is scheduled to be completed in 2028. The investment costs for the new location amount to around EUR 90 million, with Germany’s federal state of […]

  • 5 March 2025
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Supply Chain

    EchoBolt has signed a contract with RWE Renewables to provide bolt integrity services for the Amrumbank West and Arkona offshore wind farms in Germany. The scope of work under the contract will include advanced ultrasonic inspection techniques to assess the integrity of critical bolted connections on the wind turbines. By enabling an informed, condition-monitoring approach, […]

  • 20 September 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    French energy company Engie has signed a 4 year power-purchase agreement with OWP Arkona, a joint venture of E.ON and Equinor.

  • 23 July 2018
    Grid Connection

    Manor Renewable Energy (MRE) Ltd will provide the full temporary power package of generators, personnel and vessels for E.ON during the turbine installation of the Arkona offshore wind farm.

  • 24 September 2018
    Grid Connection, Operations & Maintenance, Wind Farm Update

    The 385MW Arkona offshore wind farm in the German part of the Baltic Sea has supplied the first electricity to the German electricity grid.

  • 5 July 2018
    Wind Farm Update

    The first of the total of 60 wind turbines has been installed at the Arkona offshore wind farm, located off the coast of Rügen in the German Baltic Sea.

  • 25 April 2016
    Business & Finance, Vessels, Wind Farm Update

    A2SEA has won the contract to install sixty six-megawatt Siemens wind turbines at the 385MW Arkona offshore wind farm in the German part of the Baltic Sea. A2SEA will start turbine installation works in the summer of 2018. The company will use the offshore installation vessel Sea Challenger for the job. ”We are very proud to be […]

  • 27 February 2018
    Grid Connection, Wind Farm Update

    STX France has transported the offshore substation jacket foundation for the Arkona offshore wind farm to a quay in the Saint-Nazaire Port, from where it will be placed on a barge and transported to the wind farm site in the German Baltic Sea.

  • 1 May 2016
    Authorities, Business & Finance, Environment, Grid Connection, Operations & Maintenance, Wind Farm Update

    Siemens, SPR Sign Europe’s Largest Wind Turbine Contract ScottishPower Renewables (SPR) has concluded a major East Anglia ONE deal with Siemens, worth up to one-third of the overall £ 2.5 billion (€ 3.2 billion) project investment. Under the agreement, Siemens will supply 102 wind turbines and service them for an initial period of five years. […]

  • 23 February 2018
    Vessels

    Following the installation of all 60 transition pieces at the Arkona offshore wind farm in mid-January, Jumbo posted a video showing the works that were completed ahead of schedule at the offshore wind farm site in Germany. 

  • 3 August 2017
    Grid Connection, Wind Farm Update

    STX France AS has lowered the third and final block of the offshore substation topside, being constructed for the Arkona offshore wind farm, onto a transportation barge in the drydock of the company’s yard in St. Nazaire.

  • 4 December 2017
    Vessels, Wind Farm Update

    Jumbo’s Heavy Lift Crane Vessel (HLCV) Fairplayer is now installing transition pieces (TPs) at the Arkona offshore wind farm. The vessel was outfitted with an SMST gangway shortly before the works started in early November, according to SMST.

  • 25 April 2016
    Grid Connection, Wind Farm Update

    VBMS has been awarded a contract by E.ON for the installation of 65 inter array cables for the Arkona offshore wind farm. The total scope of work for VBMS will consist of route engineering, surveying, a pre-lay grapnel run, trenching, termination and testing of the 65 cables. Survey activities are scheduled to start this year, and […]

  • 25 April 2016
    Business & Finance, Wind Farm Update

    Germany’s E.ON and Norwegian energy company Statoil have teamed up on a EUR 1.2 billion project to build the 385MW Arkona offshore wind farm in the German waters of the Baltic Sea. Statoil will have a 50-percent stake and will be involved in the project from the start. E.ON, the holder of the remaining 50% stake, will have […]

  • 5 June 2017
    Vessels, Wind Farm Update

    Emden-based EMS Maritime Offshore GmbH (EMO) has won a contract to support maritime coordination during the construction phase of the 385MW Arkona offshore wind farm in the Baltic Sea.

  • 23 February 2018
    Ports & Logistics

    The Mukran Port is upgrading two berths with new heavy load slabs to be used in the construction of the Arkona offshore wind farm.

  • 19 April 2018
    Ports & Logistics, Wind Farm Update

    The port service provider Mukran Port Terminals (MPT) has handled the first six wind turbine tower segments delivered for the 385MW Arkona offshore wind farm at the Mukran Port in Sassnitz, Germany.

  • 9 November 2017
    Wind Farm Update

    The installation of monopiles at the Arkona offshore wind farm site has been completed ahead of schedule with the last of the total of 60 monopiles now in place, allowing for an early start of the installation of the transition pieces.

  • 9 April 2018
    Operations & Maintenance, Vessels, Wind Farm Update

    Vroon’s subsea-support walk-to-work (W2W) vessel VOS Stone has commenced operations at the 385MW Arkona offshore wind farm in the German Baltic Sea.

  • 18 October 2017
    Vessels

    Landfall Marine Contractors has posted a photo of their Neptune Mariner during the delivery of one of the monopiles for the 385MW Arkona offshore wind farm in the German Baltic Sea, where they are being installed by Van Oord’s heavy lift installation vessel Svanen.

  • 13 June 2016
    Wind Farm Update

    E.ON has awarded DNV GL with a project certification contract for the new Arkona offshore wind farm, which covers inspection phases from manufacturing, transport, installation, to the commissioning of the wind farm. Having worked on the project since 2014, DNV GL was initially appointed by E.ON for the full design assessment of the wind farm’s […]

  • 9 July 2018
    Vessels

    Acta Marine’s first 24-passenger capacity crew transfer vessel (CTV) Offshore Wielingen is currently working at the Arkona offshore wind farm, which marks its first mobilization.

  • 30 May 2017
    Vessels, Wind Farm Update

    Danish marine contractor Peter Madsen Rederi A/S (PMR) has completed the removal of boulders at the 385MW Arkona offshore wind farm in the German Baltic.