Search results for: Arcadis Ost 1

1860 results

A list of search results

  • 5 December 2023
    Project Updates, Wind Farm Update

    The Arcadis Ost 1 offshore wind farm is now supplying its full capacity to the German electricity transmission grid, according to the transmission system operator (TSO) 50Hertz. 50Hertz built the submarine and onshore cable connection to the Lubmin substation and worked with the wind farm operator Parkwind to construct the offshore platform. Parkwind’s 257 MW […]

  • 17 November 2023
    Project Updates, Wind Farm Update

    Parkwind and its partners have installed the final towers and wind turbines at the 257 MW Arcadis Ost offshore wind farm in the German Baltic Sea. The final three turbines of Parkwind’s 27-turbine Arcadis Ost 1 offshore wind farm were installed during the stormy autumn in less than eight days at the project site in […]

  • 26 January 2024
    Fixed-Bottom, Infrastructure, Operations & Maintenance, Ports & Logistics, Project Updates, Wind Farm Update

    Work on the construction of a service base that will serve the Baltic Power offshore wind farm, a joint project between ORLEN Group and Northland Power, has begun in Łeba, Poland. The service base in Łeba will be ready in 2025, one year before the Baltic Power offshore wind farm becomes operational. The service base […]

  • 21 December 2023
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has taken the final investment decision (FID) on what the company says is the world’s single largest offshore wind farm, the 2.9 GW Hornsea 3, which is expected to be completed around the end of 2027. In July 2022, Ørsted was awarded a contract for difference (CfD) for Hornsea 3 at an inflation-indexed strike price of […]

  • 19 March 2024
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The installation of Siemens Gamesa’s 14 MW wind turbines at the Moray West offshore wind farm site in Scotland is scheduled to start in April. The vessel chartered to install the turbines, Cadeler’s Wind Orca, has just arrived in Esbjerg, Denmark, to mobilise for the project after completing a crane upgrade in the Netherlands. In […]

  • 16 May 2024
    Authorities, Business development, Floating Wind, Foundations, Manufacturing, Supply Chain

    Principle Power’s WindFloat, PelaStar, Technip Energies’ INO15, Stiesdal’s Tetra Triple-One, and Esteyco’s WHEEL floating wind platforms are the winners of the second phase of the FLoating Offshore Wind ReadINess (FLOWIN) Prize in the United States, set up to support technologies that can facilitate mass production and deployment of floating wind turbines. Each of the five […]

  • 11 December 2023
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Work on the installation of the two offshore substations (OSS) at the Moray West offshore wind farm site has started, with Boskalis’s DP installation vessel Bokalift 1 currently moored in the Port of Nigg with the components for the first OSS on board. The Moray West project team notified about the commencement of the OSS […]

  • 17 April 2024
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Vessels, Wind Farm Update

    Saipem, using its vessel Saipem 7000, has completed the installation of the offshore substation (OSS) at Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK, which is set to become the world’s largest offshore wind farm once in operation. Saipem 7000 arrived this month at the Dogger Bank […]

  • 3 April 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US Bureau of Ocean Energy Management (BOEM) has issued a Record of Decision (ROD) for Avangrid’s New England Wind offshore wind project and is expected to approve its Construction and Operations Plan this Summer, which would clear the two-phased development for construction. The first offshore wind farm could enter the construction stage in 2025. […]

  • 3 May 2024
    Authorities, Business & Finance, Business development, Fixed-Bottom, Floating Wind, Planning & Permitting, Research & Development

    Irish Minister for the Environment, Climate and Communications, Eamon Ryan, has launched the Future Framework for Offshore Renewable Energy, which provides a roadmap for Ireland to deliver 37 GW of offshore wind by 2050. The framework sets out the pathway Ireland will take to deliver 20 GW of offshore wind by 2040 and at least 37 […]

  • 22 December 2023
    Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Shortly after changing the preferred wind turbine supplier, the three projects in the Norfolk Offshore Wind Zone in the UK have now also changed hands as RWE will acquire Vattenfall’s 4.2 GW Norfolk portfolio for GBP 963 million (approximately EUR 1.1 billion). The new owner says it will also resume the development of the Norfolk Boreas […]

  • 3 January 2024
    Project Updates, Wind Farm Update

    The Estonian Ministry of Climate has approved the report on the environmental impact assessment (EIA) of the North-Western Estonian offshore wind farm being developed by Enefit Green. The North-Western Estonian offshore wind farm is planned to have a capacity of 1 GW and can accommodate up to 60 wind turbines. The wind farm’s annual electricity […]

  • 1 May 2024
    Business & Finance, Business development, R&D, Research & Development, Supply Chain, Technology

    The Offshore Wind Growth Partnership (OWGP) has launched a GBP 1 million Innovation Grant funding competition aimed at boosting the local offshore wind supply chain. Innovation Grants between GBP 25,000 and GBP 200,000 are available for projects that focus on future cables, electrical systems, next-generation installation, and operations and maintenance technologies. The scope of the […]

  • 27 May 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    RWE has made the investment decision for its Nordseecluster, involving offshore wind projects with a total capacity of 1.6 GW to be built in the German North Sea. The Nordseecluster is being implemented in two phases, Nordseecluster A and Nordseecluster B, each comprising two offshore wind farms. Nordseecluster A has a total capacity of 660 […]

  • 23 May 2024
    Supply Chain, Vessels

    The keel for the first Jones Act-compliant subsea rock installation vessel (SRIV) for the US offshore wind industry, Acadia, was laid on 2 May at the Philly Shipyard in Philadelphia, Pennsylvania. The vessel was ordered by Great Lakes Dredge & Dock Corporation (GLDD) in 2021 and the first steel for the SRIV was cut in […]

  • 3 May 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Dominion Energy has issued a statement in response to claims that the Coastal Virginia Offshore Wind (CVOW) project was delayed saying the project was on schedule and that the installation vessel Orion would start construction between 6 and 8 May. “On April 29, anti-wind groups filed a petition in the United States District Court for the District of Columbia seeking […]

  • 13 June 2024
    Supply Chain, Wind Turbines

    Danish wind turbine manufacturer Vestas has signed a conditional agreement for the supply of turbines for an offshore wind power project in two phases in Northern Europe. The capacity of the project is above Vestas’ current disclosure threshold of 1 GW. If and when the agreement translates into firm and unconditional orders, Vestas said it […]

  • 2 January 2024
    Fixed-Bottom, Floating Wind, Market Outlooks, Supply Chain, Wind Turbines

    The biggest wind turbines also make for some of the biggest news on offshoreWIND.biz. In 2023, wind turbine OEMs continued making headlines with their models in development and on the path to commercialisation, and by announcing brand new wind turbine generators (WTGs) that further raise the bar in generation capacity and size. Here, we are […]

  • 15 January 2024
    Authorities, Contracts & Tenders, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Lithuania’s National Energy Regulatory Council (NERC) has opened the country’s second offshore wind tender which, same as the first one, is looking for a developer of a 700 MW offshore wind farm. Interested developers now have until 15 April to register and submit their documents and offers, which will then be undergoing evaluation until 27 […]

  • 10 April 2024
    Business & Finance, Floating Wind, Planning & Permitting, Project Updates, Wind Farm Update

    The joint venture company behind the 1 GW Gwynt Glas floating wind project is set to change ownership structure as EDF Renewables UK, which owns Gwynt Glas together with DP Energy, is entering into a partnership with Irish renewable energy developer ESB and UK-headquartered offshore wind investor Reventus Power. DP Energy will remain a development […]

  • 14 March 2024
    Business & Finance, Fixed-Bottom

    RWE has reported an adjusted EBITDA of nearly EUR 1.7 billion in its offshore wind segment for 2023, compared to EUR 1.4 billion for the previous fiscal year. The increase in earnings is due to the commissioning of new capacity and better wind conditions, according to the company. Electricity generation from renewable energy at RWE rose by […]

  • 22 April 2024
    Business & Finance, Collaboration, Fixed-Bottom, Outlook & Strategy, Project Updates, Wind Farm Update

    US utility Eversource Energy has finalized definitive documents regarding its previously announced agreement to sell its 50 per cent ownership stake in the 924 MW Sunrise Wind offshore wind project to Ørsted. Eversource will remain contracted, under a separate construction management agreement, to lead the onshore construction of the Sunrise Wind project following the closing. […]

  • 2 February 2024
    Business & Finance, Contracts & Tenders, Floating Wind, Foundations, Supply Chain

    Denmark-headquartered Copenhagen Infrastructure Partners (CIP) has signed a memorandum of understanding (MoU) with HSG Sungdong for the floating wind structures for its 1.5 GW Haewoori offshore wind project in South Korea. Under the non-binding MoU, the two companies plan to establish a partnership to explore opportunities to optimise the fabrication of floating foundations to reduce […]

  • 15 January 2024
    Authorities, Contracts & Tenders, Fixed-Bottom, Planning & Permitting

    The Danish Energy Agency (DEA) is doing one last check with the market before launching the offshore wind tenders for at least 6 GW of capacity that would be installed by 2030 across several sites, starting with the first auction this Spring. On 12 January, the DEA published revised draft tender documents for a follow-up […]

  • 15 December 2023
    Equipment, Supply Chain, Wind Turbines

    Siemens Gamesa has manufactured the first 108-metre-long wind turbine blades at its factory in Hull for the 880 MW Moray West offshore wind farm in Scotland. The team from Ocean Winds and Gareth Davies MP, Exchequer Secretary to the UK Treasury were present to see the first blades produced in Hull. In total, 180 blades […]

  • 7 May 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Wind turbine installation at the Yunlin offshore wind farm site in Taiwan has resumed with two wind turbines already installed in this year’s campaign and 36 of the project’s total 80 Siemens Gamesa 8 MW units in place so far. The wind turbines are being installed by the vessel Seajacks Zaratan. “Following weeks of hard […]