904 results found for 'Arcadis Ost 1'

904 results found for 'Arcadis Ost 1'
Order results by

A list of search results

  • 8 July 2024
    Contracts & Tenders, Foundations, Supply Chain

    Ramboll has been selected as the foundation designer for the Gennaker offshore wind project in the German Baltic Sea, owned by Skyborn Renewables. Under the contract, Ramboll will be responsible for developing the basic and detailed design of 63 monopile foundations supporting Siemens Gamesa’s SG 14-236 DD wind turbines. In addition, the company’s role extends […]

  • 5 December 2023
    Project Updates, Wind Farm Update

    The Arcadis Ost 1 offshore wind farm is now supplying its full capacity to the German electricity transmission grid, according to the transmission system operator (TSO) 50Hertz. 50Hertz built the submarine and onshore cable connection to the Lubmin substation and worked with the wind farm operator Parkwind to construct the offshore platform. Parkwind’s 257 MW […]

  • 3 April 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US Bureau of Ocean Energy Management (BOEM) has issued a Record of Decision (ROD) for Avangrid’s New England Wind offshore wind project and is expected to approve its Construction and Operations Plan this Summer, which would clear the two-phased development for construction. The first offshore wind farm could enter the construction stage in 2025. […]

  • 13 June 2024
    Supply Chain, Wind Turbines

    Danish wind turbine manufacturer Vestas has signed a conditional agreement for the supply of turbines for an offshore wind power project in two phases in Northern Europe. The capacity of the project is above Vestas’ current disclosure threshold of 1 GW. If and when the agreement translates into firm and unconditional orders, Vestas said it […]

  • 22 July 2024
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain

    Estonia-based renewable energy developer Enefit Green is currently running a competitive tender for a meteorological and oceanographic (metocean) campaign at the company’s Liivi offshore wind site in the Estonian part of the Gulf of Riga. The tender, first issued in mid-July with a submission deadline date set to 1 August, has now been prolonged until […]

  • 27 June 2024
    Authorities, Business & Finance, Contracts & Tenders, Industry, Planning & Permitting

    European wind energy industry organisation, WindEurope, has warned that the negative bidding approach will lead to the bid costs falling onto the supply chain and/or electricity consumers after Germany and the Netherlands closed their latest offshore wind tenders, securing nearly EUR 4 billion in total through winning bids. “The negative bidding amounts are a straight […]

  • 10 April 2024
    Business & Finance, Floating Wind, Planning & Permitting, Project Updates, Wind Farm Update

    The joint venture company behind the 1 GW Gwynt Glas floating wind project is set to change ownership structure as EDF Renewables UK, which owns Gwynt Glas together with DP Energy, is entering into a partnership with Irish renewable energy developer ESB and UK-headquartered offshore wind investor Reventus Power. DP Energy will remain a development […]

  • 20 June 2024
    Authorities, Business & Finance, Business development, Planning & Permitting, Research & Development

    India’s Union Cabinet has approved the viability gap funding (VGF) scheme for offshore wind energy projects totalling Rs. 7453 crores (approximately EUR 833 million). This includes about EUR 765 million for the installation and commissioning of 1 GW of offshore wind projects – 500 MW each off the coast of Gujarat and Tamil Nadu – […]

  • 1 May 2024
    Business & Finance, Business development, R&D, Research & Development, Supply Chain, Technology

    The Offshore Wind Growth Partnership (OWGP) has launched a GBP 1 million Innovation Grant funding competition aimed at boosting the local offshore wind supply chain. Innovation Grants between GBP 25,000 and GBP 200,000 are available for projects that focus on future cables, electrical systems, next-generation installation, and operations and maintenance technologies. The scope of the […]

  • 8 July 2024
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain

    Enefit Green, a renewable energy developer based in Estonia, has issued a call for tenders for geotechnical surveys at the project site of its Liivi offshore wind farm, located ten kilometres off the island of Kihnu in the Estonian part of the Gulf of Riga. The call was published on 8 July with the deadline […]

  • 5 June 2024
    Authorities, Business & Finance, Contracts & Tenders, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The State of New York and the developers of Empire Wind 1 and Sunrise Wind projects, Equinor and Ørsted, have signed Offshore Wind Renewable Energy Certificate (OREC) Purchase and Sale Agreements for the two projects the developers re-bid in the state’s fourth offshore wind solicitation and were awarded capacity. Empire Wind 1 and Sunrise Wind […]

  • 16 May 2024
    Authorities, Business development, Floating Wind, Foundations, Manufacturing, Supply Chain

    Principle Power’s WindFloat, PelaStar, Technip Energies’ INO15, Stiesdal’s Tetra Triple-One, and Esteyco’s WHEEL floating wind platforms are the winners of the second phase of the FLoating Offshore Wind ReadINess (FLOWIN) Prize in the United States, set up to support technologies that can facilitate mass production and deployment of floating wind turbines. Each of the five […]

  • 5 July 2024
    Business development, Equipment, Fixed-Bottom, Foundations, Innovation, Supply Chain, Technology

    A consortium comprising some of the world’s leading offshore wind developers and Tier 1 suppliers have initiated a joint industry project that aims to commercialise a new foundation connection technology developed by the Netherlands-based company C1 Connections. “With the increasing size of wind turbines, the traditional L-flange design has reached a point where in cases […]

  • 3 May 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Dominion Energy has issued a statement in response to claims that the Coastal Virginia Offshore Wind (CVOW) project was delayed saying the project was on schedule and that the installation vessel Orion would start construction between 6 and 8 May. “On April 29, anti-wind groups filed a petition in the United States District Court for the District of Columbia seeking […]

  • 22 April 2024
    Business & Finance, Collaboration, Fixed-Bottom, Outlook & Strategy, Project Updates, Wind Farm Update

    US utility Eversource Energy has finalized definitive documents regarding its previously announced agreement to sell its 50 per cent ownership stake in the 924 MW Sunrise Wind offshore wind project to Ørsted. Eversource will remain contracted, under a separate construction management agreement, to lead the onshore construction of the Sunrise Wind project following the closing. […]

  • 24 June 2024
    Authorities, Planning & Permitting

    Germany’s Federal Network Agency has awarded 2.5 GW of offshore wind across two areas in its latest auction that saw two bidders collectively pay EUR 3 billion for the opportunity to develop in the North Sea. EnBW has secured the 1 GW N-12.3 area in the German North Sea. The company won the site at […]

  • 11 July 2024
    Authorities, Planning & Permitting

    Attentive Energy and Atlantic Shores Offshore Wind have submitted a proposal to the New Jersey Board of Public Utilities (NJBPU) in the state’s fourth offshore wind solicitation. The NJBPU announced on 30 April the opening of the state’s fourth solicitation for 1.2 GW to 4 GW of offshore wind generation capacity. The application window remained […]

  • 23 May 2024
    Supply Chain, Vessels

    The keel for the first Jones Act-compliant subsea rock installation vessel (SRIV) for the US offshore wind industry, Acadia, was laid on 2 May at the Philly Shipyard in Philadelphia, Pennsylvania. The vessel was ordered by Great Lakes Dredge & Dock Corporation (GLDD) in 2021 and the first steel for the SRIV was cut in […]

  • 17 May 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain, Wind Turbines

    Vestas has signed a conditional agreement for the supply of wind turbines for a large-scale offshore wind project in Europe. The company did not disclose the name of the client or the project. In an update on 17 May, the Danish wind turbine manufacturer said that the offshore wind project was located in Northern Europe […]

  • 3 May 2024
    Authorities, Business & Finance, Business development, Fixed-Bottom, Floating Wind, Planning & Permitting, Research & Development

    Irish Minister for the Environment, Climate and Communications, Eamon Ryan, has launched the Future Framework for Offshore Renewable Energy, which provides a roadmap for Ireland to deliver 37 GW of offshore wind by 2050. The framework sets out the pathway Ireland will take to deliver 20 GW of offshore wind by 2040 and at least 37 […]

  • 13 May 2024
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates

    Maryland Governor Wes Moore signed a new offshore wind bill on 9 May, under which the State will create a schedule for offshore wind solicitations until 2031 and revise previous solicitations. The latter will allow the State to re-allocate the support awarded to Ørsted’s Skipjack project, from whose power purchase agreement the developer withdrew, to […]

  • 27 June 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Iberdrola has taken the final investment decision (FID) for its Windanker offshore wind farm in Germany, which has now advanced to the delivery phase. Windanker is the third offshore wind project for Iberdrola in the German Baltic Sea. The company already operates the 350 MW Wikinger and is developing the 467 MW Baltic Eagle project. […]

  • 6 February 2024
    Business development, Contracts & Tenders, Fixed-Bottom, Research & Development, Supply Chain

    The Dutch company, Ventolines, has won a public tender to consult the team behind the Estonian-Latvian cross-border offshore wind project, ELWIND, in executing the next practical steps in de-risking the offshore areas. By winning the tender and signing the agreement, Ventolines took the position of technical consultant for the 1 GW ELWIND offshore wind project. […]

  • 19 April 2024
    Business & Finance, Business development, Fixed-Bottom, Floating Wind, Industry, Infrastructure, Jobs & Recruitment, Outlook & Strategy, Ports & Logistics, R&D, Supply Chain, Transition

    RenewableUK, the Offshore Wind Industry Council, The Crown Estate and Crown Estate Scotland have published an Industrial Growth Plan, setting out how to triple offshore wind manufacturing capacity over the next ten years in the UK. The UK offshore wind industry already employs 32,000 people and each new large offshore wind farm adds GBP 2-3 […]

  • 9 July 2024
    Authorities, Floating Wind, Grid Connection, Onshore Infrastructure, Planning & Permitting

    Buchan Offshore Wind, a consortium comprising BayWa r.e., Elicio, and BW Ideol, has initiated the scoping process for its onshore grid infrastructure by submitting the Onshore Scoping Report to Aberdeenshire Council. The Onshore Scoping Report contains details of the planned onshore elements and its approach to the Environmental Impact Assessment (EIA), with stakeholders now invited […]

  • 17 April 2024
    Equipment, Fixed-Bottom, Supply Chain, Vessels

    As construction work has started on Taiwan’s 1 GW Hai Long offshore wind farm with the vessel Green Jade installing the first jacket foundation pin piles, TWD and Seatools each revealed their contracts for the provision of pre-piling and piling equipment and services with the vessel owner, CSBC-DEME Wind Engineering (CDWE). The Hai Long joint […]