EEW OSB Completes Hornsea Project One Work

EEW Offshore Structures (Britain) Ltd. (EEW OSB) has completed the work scope for Ørsted’s Hornsea Project One offshore wind project.

EEW OSB was tasked with manufacturing 86 out of 174 transition pieces (TPs) for the project. EEW Special Pipe Constructions GmbH (EEW SPC), EEW OSB’s parent company, is manufacturing the 174 monopiles for the wind farm.

The remaining TPs are being delivered by Bladt Industries (68), and Steelwind Nordenham with Wilton Engineering (20).

By early November 2018, 104 of the wind farm’s foundations were already in place.

Located 120km off the Yorkshire Coast in the UK, the 1.2GW Hornsea Project One will comprise 174 Siemens 7MW wind turbines, three offshore substations, and a reactive compensation substation (RCS).

Once fully operational in 2020, it will be the largest offshore wind farm in the world.

Related news

List of related news articles

Posted: 2 months ago

SENER Joins Scottish Floating Wind Project

Engineering and technology group SENER has announced its involvement in the 50MW Kincardine floating...

Categories:
  • Wind Farm Update
Posted: 2 months ago
Posted: 2 months ago

Hornsea One Nears Turbine Installation

Windhoist Limited has pre-assembled the first Siemens Gamesa turbines destined for the Hornsea Proje...

Categories:
  • Wind Farm Update
Posted: 2 months ago
Posted: 3 months ago

Ørsted Seeks Hornsea Two UXO Inspection and Clearance Permit

Ørsted’s subsidiary Optimus Wind Limited has applied to the UK Marine Management Organisation ...

Categories:
  • Wind Farm Update
Posted: 3 months ago
Posted: 2 months ago

JECS Offshore Completes Rampion Duty

UK-based JECS Offshore Scaffolding Ltd has just completed its contract to supply scaffolding access ...

Categories:
  • Wind Farm Update
Posted: 2 months ago