Horns Rev 3 TP Countdown Starts

The first transition piece will be installed on the Horns Rev 3 wind farm mid-July, Vattenfall, the owner and developer of the 406.7MW project in the Danish North Sea, said.

The remaining 48 transition pieces are scheduled to be installed by September, Vattenfall said. The units are manufactured by Bladt Industries in Denmark and by Smulders in Belgium.

SAL Heavy Lift is in charge of delivering the transition pieces to the Port of Esbjerg.

The transition pieces will support 49 MHI Vestas 8.3MW wind turbines scheduled for commissioning in 2020.

Horns Rev 3 wind farm is being developed north-west of Blåvands Huk on the Danish west coast.

Related news

List of related news articles

Posted: 5 months ago

Energinet Seeks Heli Services Provider

Danish transmission system operator Energinet has issued a tender searching for a provider of offsho...

Categories:
  • Business & Finance
Posted: 5 months ago
Posted: 5 months ago

Boskalis Appoints New CFO from Within

Royal Boskalis Westminster N.V. has nominated Carlo van Noort to be appointed as Chief Financial Off...

Categories:
  • Business & Finance
Posted: 5 months ago
Posted: 5 months ago

Northwester 2 Reaches Financial Close

Northwester 2 has reached the official close of financial agreements with all key stakeholders and b...

Categories:
  • Business & Finance
Posted: 5 months ago
Posted: 5 months ago

DEME Group to See CEO Switch in 2019

DEME Group has selected Luc Vandenbulcke to succeed Alain Bernard as CEO, effective from 1 January 2...

Categories:
  • Business & Finance
Posted: 5 months ago