Triton Knoll Seeks Seabed Preparation Clearance

Triton Knoll Offshore Windfarm Ltd has applied to the UK’s Marine Management Organisation for a marine licence to undertake boulder clearance and seabed preparation works within the Triton Knoll offshore wind farm array zone.

Source: innogy

The developer proposes to undertake boulder clearance and seabed preparation to relocate boulders and obstructions from the areas within which foundations and inter-array cables will be installed.

It is anticipated that the boulder clearance works for foundation installation will be undertaken in the third quarter of 2019 and be undertaken for a continuous 60-day campaign.

The seabed preparation works and boulder clearance for the installation of inter-array cables will also be undertaken in the third quarter of 2019 and be undertaken for a continuous 60-day campaign.

The consultation on the application will close on 25 June.

Triton Knoll, owned and developed by innogy, has a planned installed capacity of 860MW. The project is now progressing towards a financial investment decision later this summer with full onshore construction starting shortly after, and offshore construction starting in late 2019. First energy generation could be as early as mid-Q1 2021, with the project expected to begin commissioning in 2021.