Taiwan Selects Eleven Offshore Wind Projects

Taiwan’s Ministry of Economic Affairs (MOEA) has awarded grid capacity to eleven offshore wind projects under the first process of its kind in Taiwan.

Map showing location of the 11 selected projects (the 708MW Yunlin to be built in two phases); Image: MOEA/ cropped

The Ministry informed on 30 April that it had awarded a total of 3,836MW of grid connection capacity to eleven offshore wind farms proposed by seven developers.

Of this, 738MW will be completed by 2020, with 3,098MW to be set up between 2021 and 2025. For 2020, 500MW were planned to be added, however, an additional 238MW was allocated after a thorough review of the planning sites and applications, resulting in a total capacity of 738MW approved to go online in 2020.

The table of projects released by the Ministry shows twelve projects that were reviewed, of which Ørsted’s Greater Changhua North East site is listed as not getting an approval in this procedure.

In some two years, Taiwan will see the first phase (360MW) of wpd’s Yunlin project (totalling 708MW) and Swancor/Macquarie’s 378MW Formosa 2.

Approved to come online between 2021 and 2025 are wpd’s Yunlin II phase (348MW) and 350MW Taoyuan, Ørsted’s 605.2MW Greater Changhua South East and 294.8MW Greater Changhua South West, Copenhagen Infrastructure Partners’ (CIP) 552MW ChungFang and 48MW Xidao, China Steel Corporation/CIP’s 300MW Chungnan, Taiwan Power Company’s (Taipower) 300MW second phase of Changhua project, and Yushan Energy/Northland Power’s 300MW Hai Long 2 offshore wind farm.

Aside from the FiT contracts awarded through this process, two projects have already been approved to come online in 2019/2020 as demonstration projects preceding further, commercial developments: the 120MW second phase of Formosa 1, developed by a consortium comprising Swancor, Macquarie and Ørsted; and TPC’s (Taipower) 110MW first phase of the Changhua project.

This sets Taiwan on track to adding 4,066MW of offshore wind by 2025.


To remind, at the beginning of 2018, nine developers had qualified for offshore environmental permits in Taiwan, offering 10.5GW of offshore wind capacity in total. They have been competing for 5.5GW of offshore wind contracts: 3.5GW being awarded through the feed-in-tariff (FIT) process – which resulted in 3.8GW awarded now – and the rest to be awarded through a tendering procedure expected to take place in May or early June.

Share this article

Follow Offshore Wind

Events>

<< Dec 2018 >>
MTWTFSS
26 27 28 29 30 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31 1 2 3 4 5 6

Energy Storage 2019

The conference will bring together senior representatives from European energy suppliers, developers…

read more >

5th Asia Offshore Wind Day 2019

The event will bring together senior executives active in the offshore wind industry in Asia…

read more >

11th Annual Wind Operations Dallas 2019 Conference & Exhibition

Wind Operations Dallas (O&M, Asset Management, Storage) will draw together 100 professional speakers…

read more >

Jobs>

Senior Operations & Maintenance Engineer

The Senior O&M Engineer (Structural) sits within the Asset Integrity Management Department team of Offshore O&M, reporting to a Lead O&M Engineer...

apply

O&M Lead Contract Manager

Here at Scottish Power Renewables we’re committed to remaining a UK leader in renewable energy. As well as investing in our technologies, we are committed to investing in the future of extraordinary people like you...

apply

Senior Contract Manager

Here at Scottish Power Renewables we’re committed to remaining a UK leader in renewable energy. As well as investing in our technologies, we are committed to investing in the future of extraordinary people like you...

apply

Vessels>