32 Beatrice Foundations In Place

Seaway Heavy Lifting’s (SHL) vessel Oleg Strashnov installed the 32nd of 86 jacket foundations on the 588MW Beatrice offshore wind farm in Outer Moray Firth, Scotland, on 24 December, a Weekly Notice of Operations shows.

Image source: BOWL

Oleg Strashnov will remain on the site off Scotland until early January, after which another SHL vessel, Stanislav Yudin, will take over the project and install the remaining jackets. The project is expected to be completed by September 2018.

The Beatrice offshore wind farm will comprise 84 Siemens 7MW turbines and two offshore substations, all installed on jacket foundations.

The first turbines are expected to be installed in summer 2018, with the wind farm scheduled for commissioning by the end of 2019.

Beatrice Offshore Windfarm Ltd (BOWL), the owner and developer of the wind farm, is a joint venture partnership between SSE (40%), Copenhagen Infrastructure Partners (35%) and Red Rock Power Ltd. (25%).

Related news

List of related news articles

Posted: 4 months ago

Swedish Offshore Wind Farm Is No More

Offshore wind O&M specialist Ziton has completed the decommissioning of the Utgrunden offshore ...

Categories:
  • Business & Finance
Posted: 4 months ago
Posted: 4 months ago

Half of Hornsea One Foundations Up

GeoSea has installed half of the monopile foundations at the Hornsea Project One offshore wind farm ...

Categories:
  • Wind Farm Update
Posted: 4 months ago
Posted: 4 months ago

Wind of Change Takes to Water (VIDEO)

Turkey’s Cemre Shipyard has shared a video showing the launch of Ørsted’s service operat...

Categories:
  • Operations & Maintenance
Posted: 4 months ago
Posted: 4 months ago

SSC Wind and Robur Combine Forces

SSC Wind and Robur have signed an agreement to join forces with an aim to expand their wind energy s...

Categories:
  • Business & Finance
Posted: 4 months ago