Siem to Connect 84 Beatrice Wind Turbines

Seaway Heavy Lifting has awarded Siem Offshore Contractors (SOC) a contract for the turnkey supply and installation package of the inner array grid cable system for the 588MW Beatrice Offshore Wind Farm.

In addition to the submarine cable installation works, SOC will also provide associated materials and services including the supply of the submarine composite cables, cable protection systems and related accessories as well as post-installation termination, trenching and testing services.

The 84 wind turbines at the Beatrice offshore wind farm will be connected by an inner-array grid of 91 33kV medium voltage alternating current submarine composite cables with a total length of up to 164km.

The offshore works for the inter-array cable system are due to begin in 2017, with the project scheduled to be completed before the end of Q3 2018.

Related news

List of related news articles

Posted: about 1 year ago

SSC Wind and Robur Combine Forces

SSC Wind and Robur have signed an agreement to join forces with an aim to expand their wind energy s...

Categories:
  • Business & Finance
Posted: about 1 year ago
Posted: about 1 year ago

Virginia Affirms Offshore Wind Ambitions

Virginia’s Governor Ralph Northam has released the 2018 Virginia Energy Plan which calls for t...

Categories:
  • Authorities
Posted: about 1 year ago
Posted: about 1 year ago

WindEurope Outlines Floating Wind Potential

The costs of floating offshore wind in Europe could decrease from the current EUR 180-200 per MWh to...

Categories:
Posted: about 1 year ago
Posted: about 1 year ago

Germany Readies New Offshore Wind Call

Germany’s ruling coalition has agreed to issue a special call to tender for additional renewab...

Categories:
  • Authorities
Posted: about 1 year ago