East Anglia One Met Masts Undergoing Repairs

Operations & Maintenance

East Anglia Offshore Wind has started remedial works on the East Anglia One ZE and East Anglia One 1B Met Mast, according to KIS-ORCA.

Image: East Anglia One Wind

The works have been performed from a Crew Transfer vessel since the 5th January, and will consist of the installation of 4 vertical axis wind turbines, one on the mast platform and three on the lattice structure.

Operations will be weather dependent and a notice will be issued on completion of works.

KIS-ORCA has also advised that the navigation aid system (navigation lanterns and foghorn) on an offshore met mast EAZE has failed or is operating at a reduced range.

EAZE navaid system does not feature AIS or Racon; it has lantern and fog signal only.