RXPE has won another multi-million GBP turnkey contract from DONG Energy for equipment to support compliance with the UK Grid Code.

DONG Energy selected RXPE through a competitive tender process. The power electronics specialist will provide two market-leading utility grade STATCOMs for DONG Energy’s Race Bank Offshore Wind Farm located approximately 16.8 miles off Blakeney Point on the North Norfolk coast and 17.4 miles off the Lincolnshire coast at Chapel St Leonards.

The scope of delivery includes design, supply, installation and commissioning of two off 33/220 kV step up transformers and associated switchgear as well as two +120MVAr MAXIVAR™ STATCOM units.

With a potential maximum capacity of up to 580MW, Race Bank Offshore Wind Farm could generate enough electricity to power 400,000 UK homes per year.

In January, DONG awarded a contract for a ±50MVAr STATCOM to RXPE for its Burbo Bank Extension project.

Thomas Karst, Programme Director for Race Bank at DONG Energy, said: “Investing in the UK is a real priority for DONG Energy so we’re very pleased to agree this contract with RXPE for important work being delivered from UK-based offices.”

RXPE will deliver this new project from its engineering and project delivery office based in Altrincham, near Manchester, and a recently opened second office in Newcastle, both in the UK. The original UK office in Altrincham was established in 2013 to support RXPE EPC projects in Europe, Africa and India.