  • 30 June 2014
    Wind Farm Update

    The first set of transition pieces (TPs) for EnBW’s Baltic 2 offshore wind farm has left the port in Rostock on board the installation jack-up platform Goliath on Friday. Two transition pieces per shipment are loaded on the Goliath and then transported in around 12 hours of sailing to their destination in the Baltic 2 […]

  • 1 February 2016

    Specialist Marine Consultants Ltd (SMC) has completed marine coordination work for Siemens on the Baltic 2 offshore wind farm. SMC’s services included coordination of Siemens personnel movements, planning of daily transfers, conducting site inductions, and safety briefings. SMC also covered the event of emergencies and undertook vessel inspections to ensure fitness for purpose and compliance with relevant […]

  • 29 April 2015
    Wind Farm Update

    EnBW’s offshore wind farm Baltic 2 generated the first kilowatt hour of electricity and fed it into the grid last weekend.  EnBW Baltic 2 is currently being built 32 kilometres north of the island of Rügen in the Baltic Sea. At this point, 60 of a total of 80 wind energy turbines have been installed. Now that […]

  • 23 April 2013
    Grid Connection, Wind Farm Update

    The work for the network connection of the second German offshore wind farm in the Baltic Sea, the EnBW Baltic 2, is in progress. The vessel Aura rinsed the first submarine cable section into the Baltic ground, on Saturday, 20 April 2013, for the connection of Baltic 2. A total of sixty kilometers of submarine […]

  • 9 February 2015
    Grid Connection, Wind Farm Update

    50Hertz is in charge of connecting EnBW Baltic 2 to the grid.  The German offshore wind farm, being constructed 32 kilometers north of the Baltic island of Rügen, is four times as large as EnBW Baltic 1. With 80 Siemens SWT-3.6-120 turbines, it can produce six times as much power. The construction of EnBW Baltic 2 began in […]

  • 22 April 2020
    Operations & Maintenance, Ports & Logistics

    The 288 MW EnBW Baltic 2 offshore wind farm in the German Baltic Sea will be serviced from the Danish port of Klintholm on the island of Møn from August 2020, EnBW said. Until now, the company’s service team of up to 25 has travelled from Rostock to a hotel vessel close to the wind […]

  • 27 August 2014
    Wind Farm Update

    In the development of its second offshore wind farm, Energie Baden-Württemberg AG (EnBW) has reached a milestone with the installation of the first wind turbine at its EnBW Baltic 2 offshore wind farm. In Sassnitz harbor, the installation vessel Vidar had taken on board components for a total of six wind turbines. Yesterday afternoon, the […]

  • 20 January 2012

    Minister Harry Glawe met with the company representatives, operators and planners on Thursday at the service station that was built for two wind farms Baltic I and II, in Barhöft (County-West Pomerania Rügen). “Domestic firms can benefit from the construction of Baltic II,“ said Glawe. North of Rügen, Baltic II will be built as the […]

  • 30 July 2014

    Offshore WIND’s photo of the day: Loading of turbine blades for EnBW Baltic 2 wind farm in Sassnitz harbor. The wind turbine blades are being loaded onto HOCHTIEF’s jack-up vessel Vidar. With large deck space and 1,200-ton crane, the vessel can operate in water depths of up to 50 meters. Last month the first transition […]

  • 21 January 2015

    Bladt Industries loaded out the last of 41 jacket foundations for EnBW Baltic 2 offshore wind farm yesterday. After receiving the order, Bladt established a production site at Lindø Industrial Park where they created dedicated production line for serial production of jacket foundations. The first jacket was manufactured in May last year, after which it […]

  • 29 April 2013

    Since the completion of Amrumbank and Humber Gate order for flange foundations (80 + 73 sets), Euskalforging was awarded with 41 flanges for Baltic II last week, and foundations will be supplied by Ambau.  Last year, the company secured a contract to supply 3 connecting flanges for the prototype of NENUPHAR floating foundation, an innovative […]

  • 20 August 2013
    Wind Farm Update

    The construction of the second offshore wind farm of EnBW Energie Baden-Württemberg AG has entered its late stage: the “Goliath” installation platform left Rostock port on August 16 for its destination – EnBW’s Baltic 2 construction area, which is located 32 kilometres north of the Baltic Sea island of Rügen. Installation has started there on […]

  • 16 September 2014
    Business & Finance, Technology, Wind Farm Update

    In the last week of August, the first of a total of 80 wind energy plants of the Baltic 2 offshore wind farm was erected. For INROS LACKNER this also marks an important milestone as the company is involved in the offshore wind project on behalf of EnBW. The wind farm, with a total capacity of 288 […]

  • 17 March 2015
    Business & Finance

    JV Baltic II Foundations (joint venture between Hochtief and GeoSea) and Blue Water Shipping have cooperated on the project of shipping 41 jacket foundations from Lindo to the Baltic II wind farm in the Baltic Sea. During the project period from the summer of 2014 until January 2015, JV Baltic II Foundations was offered office […]

  • 14 January 2015
    Wind Farm Update

    With EnBW Baltic 2 in the Baltic Sea, about 32 kilometers north of Rügen, one of the largest offshore wind farms in Germany is under construction at the moment.  At the same time, EnBW is building a service station on the land of the Kraftwerks Rostock. When the wind farm goes into operation, service deployments will be […]

  • 23 May 2014

    Bladt Industries, an international steel contractor, has erected the first out of 41 Baltic 2 offshore wind farm jackets at its Lindoe construction site. Last year, the company received an order from ARGE Baltic 2 Foundations, a joint venture between HOCHTIEF Offshore Crewing, HOCHTIEF Solutions AG and GeoSea NV, who are responsible for the design, […]

  • 19 August 2014
    Wind Farm Update

    A barge that sank on Wednesday morning (August 13) off Darßer Ort in the Baltic Sea was carrying four working platforms for the EnBW Baltic 2 offshore wind farm, the company confirmed to Offshore WIND.  “We are still examining the impact and we cannot make a statement yet,” EnBW’s spokeswoman said. She added that the platforms will […]

  • 1 June 2022
    Contracts & Tenders, Operations & Maintenance, Ports & Logistics, Vessels

    EnBW has selected Njord Offshore and FRS Windcat Offshore Logistics to provide crew transfer vessels (CTVs) that will operate on the Baltic 1 and the Baltic 2 offshore wind farms in the German Baltic Sea. Njord Offshore will provide two 12-PAX CTVs for each of the wind farms, and FRS Windcat will supply one 18-PAX […]

  • 30 April 2014
    Grid Connection, Wind Farm Update

    The work on the cable connection of the EnBW Baltic 2 offshore wind farm to the grid is progressing at full speed off the Baltic coast of the German Federal State of Mecklenburg-Vorpommern. More than half of the project’s cables are now lying on the seabed. A total of sixty kilometers of submarine cables will […]

  • 25 June 2013

    Since 3 June 2013, AMBAU GmbH has been constructing 41 transition pieces to be used for the jackets at the “EnBW Baltic 2” wind farm on commission from Bladt Industries A/S. In April 2013, Bladt Industries announced that it had received an order to construct the 41 jackets to be installed in water depths of […]

  • 23 November 2011
    Grid Connection

    EnBW has commissioned a consortium consisting of the WeserWind and Alstom to build the substation for Baltic 2 offshore wind farm. Wind farm will consist of 80 Seiemens’ 3,6MW wind turbines located 32 km north of the island Rügen. Alstom will be in charge of electrical construction and Weser Wind in charge of steel construction. […]

  • 11 January 2013
    Business & Finance

    The European Investment Bank (EIB) has granted a loan of € 500 million to the largest offshore wind farm to date in the German Baltic Sea; EnBW Baltic 2. The project is being realised by EnBW Erneuerbare Energien GmbH. The financing contract was signed today in Karlsruhe. The position and scale of EnBW Baltic 2 […]

  • 8 August 2023
    Contracts & Tenders

    Trianel Windkraftwerk Borkum GmbH & Co. KG (TWB) has signed a power purchase agreement (PPA) with Deutsche Bahn for electricity generated at the Trianel Windpark Borkum I offshore wind farm in Germany. Under the agreement, TWB will supply Deutsche Bahn with wind power from the North Sea in the coming year. As part of the […]

  • 5 June 2014
    Wind Farm Update

    Offshore WIND’s photo of the day: Large component for offshore wind farm EnBW Baltic 2 come in the port of Sassnitz. Located 32 kilometres north of the Baltic Sea island of Rügen, this wind farm will consist of 80 wind power plants with a total output of 288 MW. Baltic 2 will produce enough electricity […]

  • 27 March 2013
    Grid Connection

    Ballast Nedam has signed a contract for the installation of foundations at the German EnBW Baltic 2 offshore wind farm with ARGE BALTIC 2 Foundations, a joint venture between HOCHTIEF Solutions AG, GeoSea N.V. and HOCHTIEF Offshore Crewing GmbH. Ballast Nedam will erect the project’s 39 monopile and transition piece foundations and provide the logistics […]

  • 8 October 2013

    A new rescue helicopter was commissioned into service for the Baltic 2 offshore wind project yesterday (October 7) at the airport in Güttin (Vorpommern-Rügen district). The Eurocopter BK 117 helicopter is specially equipped for rescue operations at sea. The network operator 50 Hertz and the wind turbine manufacturer EnBW are covering the hiring costs for […]