712 results found for 'Dudgeon'

712 results found for 'Dudgeon'
Order results by

A list of search results

  • 22 January 2016
    Vessels

    Poland’s Nauta Shiprepair Yard today launched a partly outfitted offshore service vessel (OSV) – Esvagt Njord – destined to operate at the 400 MW Dudgeon offshore wind farm off Norfolk, UK , once completed. Nauta and Havyard Ship Technology of Norway, the designer of the vessel, signed a shipbuilding contract for the 84-meter-long, 17-meter-wide Esvagt Njord back […]

  • 4 April 2014

    Jack-Up Barge Presents New Installation Method Jack-Up Barge, the offshore self-elevating platform supplier, has pioneered a new cost-effective installation method that promises to revolutionise offshore wind turbine construction. Scotland Gives Thumbs Up to Two Offshore Wind Farms Scottish Energy Minister, Fergus Ewing, has announced the formal consent of two adjacent offshore wind farm applications in […]

  • 3 August 2016
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s Oleg Strashnov has installed the last of the 67 foundations for the Dudgeon offshore wind farm, Statoil, the owner, developer and future operator of the wind farm, reports. Oleg Strashnov carried out the inshore loading, transportation and installation of the monopile foundations from a storage site to the installation site. The foundations were manufactured by […]

  • 6 February 2017
    Authorities, Vessels

    The Royal National Lifeboat Institution’s (RNLI) Cromer station received a report from the Coastguard of a wind farm support vessel in distress off the Dudgeon offshore wind farm on Saturday, February 4, at around 5 am local time.

  • 27 June 2018
    Business & Finance, Contracts & Tenders, Operations & Maintenance

    Equinor, formerly known as Statoil, has awarded Reach Subsea with a contract for survey and inspection, maintenance and repair (IMR) works at Dudgeon and Hywind offshore wind farms, which Reach Subsea will execute together with MMT.

  • 25 May 2012
    Grid Connection

    The inquiry into the 28km cabling route from Weybourne to Great Ryburgh began yesterday, EDP 24 informed. Even though the North Norfolk District Council (NNDC) initiated the appeal hearing, due to a lack of money, they will not be opposing the evidence proposed by the Warwick Energy. The company decided to go with the underground […]

  • 9 January 2017
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    Roxtec has secured a contract to deliver its safety seal solutions for the 402MW Dudgeon offshore wind farm project. Roxtec UK managing director Graham O’Hare said the firm will deliver cable transit systems to safeguard workers, structures and equipment on the wind farm’s substation platform. The deal will see a wide range of sealing solutions used […]

  • 9 September 2016
    Business & Finance, Operations & Maintenance, Wind Farm Update

    Norway’s Statkraft is preparing a possible divestment of its shares in the operational Sheringham Shoal offshore wind farm, as well as the Dudgeon and the Dogger Bank projects.  The revised strategy follows the announcement in December 2015 that Statkraft would make no new investments in offshore wind. Preparations for the divestment will be carried out in […]

  • 26 August 2019
    Contracts & Tenders, Operations & Maintenance

    Green Marine has won a three-year contract to deliver operations and maintenance work for Equinor’s Dudgeon offshore wind farm in the UK. Green Marine will provide its Damen-built 2610 Twin Axe vessel Green Storm to assist in the O&M, as well as support from its onshore team. According to Equinor, Green Storm will be working in […]

  • 22 August 2017
    Vessels

    Umoe Rapid has completed its first charter at world’s first floating wind farm, the 30MW Hywind Scotland Pilot Park, and at the 402MW Dudgeon offshore wind farm for Statoil.

  • 15 October 2015
    Wind Farm Update

    VBMS has completed two 1,170-metre long horizontal directional drillings (HDDs) at the landfall for the Dudgeon offshore wind farm. The drillings were done in preparation for the installation of two 42-kilometre long export cables next year. To avoid worsening weather conditions later in the season, the work was carried out three months earlier. Dudgeon Offshore Wind […]

  • 21 October 2022
    Contracts & Tenders, Vessels

    Norway-headquartered Equinor has chartered Seacat Columbia, a new BARTech 30 crew transfer vessel (CTV), from Seacat Services, for operations at its Sheringham Shoal and Dudgeon wind farms offshore Norfolk, England. The charter will cover service at the 317 MW Sheringham Shoal and the 402 MW Dudgeon offshore wind farms, both operated by Equinor from its […]

  • 6 March 2015
    Technology

    SPT Offshore has been awarded the design, fabrication and installation of the suction pile foundation for Statoil Siemens Dudgeon Transformer Substation. This deal will support Sembmarine SLP, main fabricator for this substation, who was initially awarded the contract by Siemens Transmission & Distribution Limited for design, engineering, procurement, project management and construction of the platform’s jacket substructure and […]

  • 22 September 2011
    Grid Connection

    Plans to build an electricity substation in Norfolk have been refused after an appeal against a planning ruling was dismissed. Dudgeon … (bbc) [mappress] Source: bbc, September 22, 2011

  • 25 August 2014
    Business & Finance, Wind Farm Update

    Tekmar Energy has been awarded a multi-million pound project with Statoil and Statkraft on the Dudgeon Offshore Wind Farm for the supply of its patented technology TekLink®. As part of the cable contract VSMC will be procuring the TekLink® Mechanical Latch Cable Protection System which will be installed for the protection of the subsea power […]

  • 9 July 2020
    Wind Farm Update

    Equinor has launched the community consultation period for the Sheringham Shoal and Dudgeon offshore wind extension projects off the North Norfolk coast in the UK. This first phase will run from 9 July to 20 August, and feedback is sought for the location of the onshore substation, the underground onshore cable route and any lessons […]

  • 15 August 2014
    R&D, Training & Education

    Statoil has accepted to support a PhD work of Ole-Erik Vestøl Endrerudat at University of Stavanger with Dr. Nenad Keseric from Statoil Wind Operations being a co-supervisor. The PhD work examines ways to the most cost effective operation and maintenance of offshore wind farms. Statoil wind operation department has recognised the potential of the agent-based model developed […]

  • 21 August 2016

    BREAKING: USA Just Got Its First Offshore Wind Farm “The Block Island Wind Farm is now fully constructed,” Jeff Grybowski, Deepwater Wind’s CEO, informed via social media. Timelapse: Dudgeon OSS Topside Lowered into Place Statoil has shared a timelapse video of a heavy lift vessel Oleg Strashnov installing a 1,700-tonne topside onto a jacket on […]

  • 11 March 2015
    Business & Finance

    Opportunities for Norfolk and Suffolk companies to secure business with developers of the world’s largest wind farm will be spelt out at supply chain events to be announced soon. Jonathan Cole, managing director of Scottish Power Renewables, said the procurement process for the £2bn 714 MW East Anglia One would begin after contracts were signed […]

  • 28 April 2014
    Business & Finance

    News that the Department of Energy and Climate Change (DECC) has awarded an investment contract for the planned Dudgeon Offshore Wind Farm off Norfolk received positive feedback in the East of England Energy Zone (EEEZ). EEEZ inward investment director James Gray said: “Dudgeon is a key project for us, being only 20 miles off Cromer and […]

  • 25 May 2017
    Wind Farm Update

    Mech-Tool Engineering, a Teesside based product manufacturer and supplier of fire, blast and radiant heat protection systems has delivered a contract for Statoil’s GBP 1.5 billion Dudgeon offshore wind farm project.

  • 19 January 2014

    E.ON Starts Building Amrumbank West OWF E.ON has started the construction of Amrumbank West wind farm in the North Sea. The first foundation was installed today 37 kilometers northwest of the island of Helgoland. Three Crewmen Rescued after Their Vessel Caught Fire Three crewmen have been rescued off Lowestoft this afternoon after their vessel caught […]

  • 25 August 2020
    Authorities, Wind Farm Update

    Equinor has signed lease agreements with the Crown Estate for extensions of the Sheringham Shoal and Dudgeon offshore wind farms in the UK. With the lease agreements, Equinor has secured an area of seabed of approximately 196km2 in total. The company has decided to develop the two extension projects jointly to minimise local impacts and […]

  • 11 January 2016

    Italian manufacturer of hydraulic lifting systems, Sormec, has been awarded a contract to supply an offshore telescopic crane for the Dudgeon Offshore Wind Farm’s substation.  In December 2015, representatives of Sembmarine SLP, Statoil and Siemens visited Sormec’s head office to award a kick off meeting for a new offshore telescopic crane M500/3S. The crane will be installed […]

  • 9 September 2016
    Operations & Maintenance, Vessels

    Today’s opening event for the Dudgeon Offshore Wind Farm Operations Centre will also incorporate the naming of the wind farm’s purpose built 84-metre service operations vessel (SOV), Esvagt Njord. The vessel marks a new approach to operations and maintenance with accommodation for up to 40 wind turbine technicians who will live on the ship and […]

  • 30 August 2013
    Wind Farm Update

    The site of the proposed Dudgeon Offshore Wind Farm is 20 miles off the coast of Cromer, and since acquiring the project late last year, Statoil and Statkraft have undertaken a review of the project design and the seabed characteristics of the consented site. As of the result of this review Dudgeon Offshore Wind Limited […]