Search results for: Dudgeon

286 results

A list of search results

  • 5 August 2014
    Environment

    Fugro EMU Ltd is to undertake a benthic ecology survey at the Dudgeon wind farm location. The company will utilize the survey vessel MV Ocean Dawn for the job. The vessel will deploy a benthic grab sampler and drop down video directly to the seabed from the stern of the vessel. In addition, a 2m […]

  • 5 August 2016
    Grid Connection, Wind Farm Update

    The 1,700-ton topside built by Sembmarine SLP for the offshore substation of the 402MW Dudgeon offshore wind farm has sailed out of the port of Lowestoft, UK. The four-deck topside will be installed on a 1,500-tonne steel jacket which was put in place some 32 kilometres off Cromer, Norfolk, at the beginning of June. The jacket structure […]

  • 26 August 2019
    Contracts & Tenders, Operations & Maintenance

    Green Marine has won a three-year contract to deliver operations and maintenance work for Equinor’s Dudgeon offshore wind farm in the UK. Green Marine will provide its Damen-built 2610 Twin Axe vessel Green Storm to assist in the O&M, as well as support from its onshore team. According to Equinor, Green Storm will be working in […]

  • 12 October 2017
    Business & Finance, Wind Farm Update

    The 402MW Dudgeon offshore wind farm entered full operation in October and has started receiving difference payments on generated electricity. 

  • 25 March 2014
    Technology

    Atkins has been awarded an engineering contract for the Dudgeon Offshore Wind Farm. The contract will cover all design and engineering services for the monopile foundations for the 6.0 MW turbines as well as management assistance during fabrication and installation. David Parkin, managing director for Atkins’ Renewables business, said: “This contract win further builds on […]

  • 11 January 2016

    Italian manufacturer of hydraulic lifting systems, Sormec, has been awarded a contract to supply an offshore telescopic crane for the Dudgeon Offshore Wind Farm’s substation.  In December 2015, representatives of Sembmarine SLP, Statoil and Siemens visited Sormec’s head office to award a kick off meeting for a new offshore telescopic crane M500/3S. The crane will be installed […]

  • 21 April 2016
    Vessels, Wind Farm Update

    Statoil has shared a timelapse of the 1,500-tonne jacket for the Dudgeon substation being loaded onto a barge in Lowestoft yesterday. The jacket, built by Sembmarine SLP, will be towed around 100 kilometres to the offshore construction site located some 32 kilometres off the coast of North Norfolk, where nine of sixty-seven turbine foundations have already been installed. […]

  • 9 January 2012

    Dudgeon offshore windfarm worth GBP 1.5bn hopes to clear another obstacle. North Norfolk District Council’s decision on cable route has been delayed as planners waited final wording on the planned substation at Little Dunham, reports EDP24. The onshore cable route runs over 45km in the south westerly direction to the proposed substation site located south […]

  • 18 March 2016
    Vessels

    The crane vessel Oleg Strashnov is preparing for the installation work scheduled to start soon at the Dudgeon offshore wind farm site in the UK. The vessel is currently docked at Verbrugge, Vlissingen, where it has been equipped with an outrigger frame, TP grillage, storage grillage and an “upend cradle”, according to Seaway Heavy Lifting’s social media pages. […]

  • 3 August 2016
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s Oleg Strashnov has installed the last of the 67 foundations for the Dudgeon offshore wind farm, Statoil, the owner, developer and future operator of the wind farm, reports. Oleg Strashnov carried out the inshore loading, transportation and installation of the monopile foundations from a storage site to the installation site. The foundations were manufactured by […]

  • 6 July 2014

    MHI Vestas Invites Suppliers MVOW has now launched a new website which includes a supplier gateway which allows companies to submit their details online to request to become a supplier to MVOW. Sif Group Expands Its Production Capacity, Manufactures Supersize Monopiles In the future, the length and the diameters of the monopiles will continue to […]

  • 24 November 2015
    Grid Connection, Operations & Maintenance, Technology, Wind Farm Update

    Lancashire-based VolkerInfra has been awarded its first contract with Siemens Energy which will see the company work on the Dudgeon Offshore Wind Farm. The company will install extra high voltage cables required to connect the onshore substation to the wind farm which is off the Norfolk coast. VolkerInfra will be responsible for the in-house design, […]

  • 9 September 2016
    Business & Finance, Operations & Maintenance, Wind Farm Update

    Norway’s Statkraft is preparing a possible divestment of its shares in the operational Sheringham Shoal offshore wind farm, as well as the Dudgeon and the Dogger Bank projects.  The revised strategy follows the announcement in December 2015 that Statkraft would make no new investments in offshore wind. Preparations for the divestment will be carried out in […]

  • 21 April 2016
    Wind Farm Update

    Nine foundations have been installed so far at the Dudgeon offshore wind farm, with 58 more to go until all the foundation are in place, expected to be achieved this summer. FoundOcean has connected the nine monopiles with their corresponding transition pieces by using BASF’s MasterFlow 9500 material, under a contract with Seaway Heavy Lifting (SHL), which […]

  • 11 February 2014
    Business & Finance, Grid Connection, Wind Farm Update

    ABB has won an order worth around $55 million to supply a submarine AC (alternating current) power cable system for a new wind farm, located off the coast of Norfolk. The underwater cables will feed the electricity generated by the 400-megawatt (MW) Dudgeon Offshore Wind Farm into the UK national grid. The order was received […]

  • 2 September 2014
    Grid Connection

    JDR, a provider of technology connecting the global offshore energy industry, has won a new contract with VBMS for the Statoil/Statkraft Dudgeon offshore wind farm. Dudgeon, off the UK’s Norfolk coast will utilise over 95 kilometres of JDR’s copper core inter-array cable and a range of cable accessories. The design and manufacture will take place […]

  • 1 September 2016
    Vessels, Wind Farm Update

    Jack-up vessel Sea Challenger arrived and positioned herself at the offshore substation at the 402MW Dudgeon offshore wind farm off Norfolk, UK, on 31 August, A2SEA reports. Statoil hired Sea Challenger to serve as an accommodation platform from September until the end of 2016, with the start of turbine installation phase scheduled for January 2017. Hull […]

  • 9 June 2015

    Dudgeon Offshore Wind Limited has awarded a contract to Granada Material Handling Ltd to design , manufacture, deliver and commission 1 davit crane unit for the  operations and maintenance facility in Great Yarmouth. The Granada ‘Python’ crane unit has been specifically designed for the Dudgeon offshore wind farm and the challenging marine environment in which […]

  • 9 January 2017
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    Roxtec has secured a contract to deliver its safety seal solutions for the 402MW Dudgeon offshore wind farm project. Roxtec UK managing director Graham O’Hare said the firm will deliver cable transit systems to safeguard workers, structures and equipment on the wind farm’s substation platform. The deal will see a wide range of sealing solutions used […]

  • 1 June 2016
    Grid Connection, Technology, Vessels, Wind Farm Update

    A 1,500-tonne steel jacket which will support an offshore substation at the 402MW Dudgeon offshore wind farm has been installed in the seabed some 32 kilometres off Cromer, Norfolk.  The jacket structure, built by Sembmarine SLP Ltd, was sunk into the seabed using suction bucket technology for the first time on an offshore substation in the UK. Four suction buckets, […]

  • 15 August 2014
    R&D, Training & Education

    Statoil has accepted to support a PhD work of Ole-Erik Vestøl Endrerudat at University of Stavanger with Dr. Nenad Keseric from Statoil Wind Operations being a co-supervisor. The PhD work examines ways to the most cost effective operation and maintenance of offshore wind farms. Statoil wind operation department has recognised the potential of the agent-based model developed […]

  • 22 September 2011
    Grid Connection

    Plans to build an electricity substation in Norfolk have been refused after an appeal against a planning ruling was dismissed. Dudgeon … (bbc) [mappress] Source: bbc, September 22, 2011

  • 11 March 2015
    Business & Finance

    Opportunities for Norfolk and Suffolk companies to secure business with developers of the world’s largest wind farm will be spelt out at supply chain events to be announced soon. Jonathan Cole, managing director of Scottish Power Renewables, said the procurement process for the £2bn 714 MW East Anglia One would begin after contracts were signed […]

  • 4 April 2014

    Jack-Up Barge Presents New Installation Method Jack-Up Barge, the offshore self-elevating platform supplier, has pioneered a new cost-effective installation method that promises to revolutionise offshore wind turbine construction. Scotland Gives Thumbs Up to Two Offshore Wind Farms Scottish Energy Minister, Fergus Ewing, has announced the formal consent of two adjacent offshore wind farm applications in […]

  • 27 June 2018
    Business & Finance, Contracts & Tenders, Operations & Maintenance

    Equinor, formerly known as Statoil, has awarded Reach Subsea with a contract for survey and inspection, maintenance and repair (IMR) works at Dudgeon and Hywind offshore wind farms, which Reach Subsea will execute together with MMT.

  • 6 March 2015
    Technology

    SPT Offshore has been awarded the design, fabrication and installation of the suction pile foundation for Statoil Siemens Dudgeon Transformer Substation. This deal will support Sembmarine SLP, main fabricator for this substation, who was initially awarded the contract by Siemens Transmission & Distribution Limited for design, engineering, procurement, project management and construction of the platform’s jacket substructure and […]