Search results for: kriegers flak

328 results

A list of search results

  • 29 October 2015
    Wind Farm Update

    The Danish Energy Agency (DEA) has prequalified a total of seven companies and consortia to participate in the tender of Denmark’s largest offshore wind farm, the 600MW Kriegers Flak in the Baltic Sea. Of the eight applications, the DEA received before the deadline October 1, the Agency has prequalified seven companies and consortia to bid […]

  • 10 October 2017
    Grid Connection

    Energinet.dk and 50Hertz have selected Greece-based Assodivers for cable burial works at the Kriegers Flak Combined Grid Solution (CGS), a project that will interconnect Danish and German grids via Kriegers Flak and Baltic 2 offshore wind farms.

  • 8 October 2018
    Grid Connection

    The commissioning of the Kriegers Flak Combined Grid Solution (CGS) between Germany and Denmark has been delayed until May 2019.

  • 23 November 2017
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Hollandia Offshore and Croonwolter&dros have moved the Kriegers Flak B (KFB) offshore substation topside from Hollandia Offshore’s production hall in Krimpen aan den IJssel and into the yard.  

  • 21 December 2018
    Contracts & Tenders, Vessels

    Vattenfall has contracted Van Oord for the transport and installation of the foundations for the Kriegers Flak offshore wind farm.

  • 6 September 2021
    Wind Farm Update

    His Royal Highness the Crown Prince of Denmark, together with Danish Minister for Industry, Business and Financial Affairs, Simon Kollerup, has inaugurated Vattenfall’s 604 MW Kriegers Flak offshore wind farm. With 72 Siemens Gamesa 8.4 MW wind turbines and a capacity corresponding to the annual energy consumption of approximately 600,000 Danish households, Kriegers Flak is Denmark’s […]

  • 7 July 2020
    Grid Connection

    Kriegers Flak Combined Grid Solution (CGS) has transmitted the first power between Denmark and Germany. The high-voltage cable system connects the Danish region of Zealand with the German state of Mecklenburg-Western Pomerania via the 605 MW Kriegers Flak and 288 MW Baltic 2 offshore wind farms. It is the world’s first offshore interconnector using the national […]

  • 29 June 2017
    Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    Jan De Nul Group has taken delivery of the multipurpose vessel Adhémar de Saint-Venant which as of next week will start working on the Kriegers Flak OSS project in Denmark.

  • 14 December 2017
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Vattenfall has chosen Klintholm Harbour in Denmark as its base for the servicing and maintenance of the 605MW Kriegers Flak offshore wind farm.

  • 23 May 2019
    Wind Farm Update

    Rostock-based EEW Special Pipe Constructions GmbH has started manufacturing the monopiles for Vattenfall’s 605MW Kriegers Flak offshore wind farm. The first pipe for the Danish offshore wind farm was made in the Rostock production site this May. By September 2019, all 72 monopiles will have been produced and coated, according to the company. In spring […]

  • 8 March 2018
    Technology, Wind Farm Update

    Greek Assodivers Underwater Contractors have taken delivery of two MERMAC winches from MacArtney to be used on the Kriegers Flak offshore wind project in the Danish Baltic Sea.

  • 25 September 2017
    Contracts & Tenders, Wind Farm Update

    Vattenfall has invited tenders for the installation of foundations for three projects in Denmark: Danish Kriegers Flak in the Baltic Sea, and Vesterhav Nord and Vesterhav Syd in the North Sea.

  • 12 October 2015
    Environment, R&D

    Birds and seals have got GPS transmitters on them, and the birds are monitored with radar in preparation for the establishment of Kriegers Flak offshore wind farm. It is a requirement for large construction projects such as ports, bridges and wind farms, that they must not affect the nature significantly. This requirement is particularly important […]

  • 2 December 2014
    Authorities, R&D, Wind Farm Update

    The publishing of the dialogue paper on Danish offshore wind farm Kriegers Flak is slightly delayed, the Danish Energy Agency (DEA) notified on its website.  “We expect the paper to be published next week,” the DEA said. In order to ensure that potential tenderers can offer their views on these framework conditions and contribute to making […]

  • 14 November 2016
    Business & Finance, Grid Connection, Wind Farm Update

    Energinet.dk and 50Hertz Transmission GmbH have awarded Iemants and Jan De Nul Group with a contract to construct, install, ballast and protect gravity based foundations (GBFs) for two offshore substations. The two offshore substations will serve Vattenfall’s 600MW Kriegers Flak offshore wind farm in the Danish part of the Baltic Sea, and will also serve as an interconnector between […]

  • 7 June 2021
    Wind Farm Update

    The final of the 72 Siemens Gamesa 8.4 MW wind turbines was installed at Kriegers Flak, Denmark’s largest offshore wind farm, on Saturday, 5 June. The next steps will be to finalise testing and certification of the 604 MW wind farm so that it can be inaugurated after the summer, Vattenfall, the wind farm’s owner […]

  • 29 January 2016
    Grid Connection

    The Danish Energy Agency (DEA), Energinet.dk, and Kriegers Flak tenderers will hold a meeting on 2 February.  They will discuss grid connection, platforms and technical issues regarding the 600MW offshore wind farm in the Baltic Sea. The DEA has prequalified seven companies and consortia to participate in the tender for the project. The decision of the winner is expected […]

  • 26 September 2016
    Authorities, Business & Finance, Wind Farm Update

    The European Investment Bank (EIB) is reviewing a request to provide financing for the 600MW Kriegers Flak offshore wind farm project in the Baltic Sea. The Danish Energy Agency (DEA) is seeking an undisclosed amount from EIB for the wind farm which is expected to be commissioned in 2022. EIB says that the project will further […]

  • 7 April 2016
    Business & Finance

    DEME Concessions Wind and Siemens Financial Services have joined Kriegers Flak ApS, a project company set up by EnBW for participating in Kriegers Flak tender procedure.  The project company submitted an indicative offer for the construction of the Danish offshore wind farm on 5 April – as was stipulated by the Danish government in the tender procedure. This […]

  • 22 December 2016
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    Vattenfall and the Danish minister for Energy, Utilities and Climate, Lars Chr. Lilleholt, have signed the concession agreements for the offshore wind farm Kriegers Flak and the near shore wind farms Vesterhav Nord and Vesterhav Syd. The signatures became possible after the Danish Parliament on 19 December unanimously adopted the legislation that determines the subsidies […]

  • 17 January 2018
    Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

    A barge loaded with two gravity-based foundations (GBFs) for the high voltage station of the 605MW Kriegers Flak offshore wind farm has arrived in Koge, Denmark, Blue Water Shipping (BWS), the port agents for the project, told Offshore WIND.

  • 4 April 2018
    Grid Connection, Wind Farm Update

    Energinet has resumed onshore cable installation works for the Kriegers Flak offshore wind farm after the winter break, and is now ready to start with the final stage of cable excavation on land.

  • 11 December 2017
    Wind Farm Update

    Jan De Nul and Iemants have completed the two gravity-based foundations for Kriegers Flak substations. The steel structures, designed and built by Iemants (Smulders), have been placed on top of their corresponding concrete structures and the foundations are now being prepared to be transported from the port of Ostend in Belgium to Denmark by the end of December. 

  • 18 October 2016
    Business & Finance, Grid Connection, Vessels, Wind Farm Update

    Transmission system operators Energinet.dk and 50Hz Transmission are inviting tenders for an unexploded ordnance (UXO) survey and services along the planned cable routes of the 400MW Kriegers Flak Combined Grid Solution (CGS) interconnector in the Baltic Sea. Kriegers Flak CGS is a joint project between Energinet.dk and 50Hz Transmission to interconnect the Danish and German grid via two offshore […]

  • 23 April 2021
    Authorities, Wind Farm Update

    Vattenfall has been granted a Natura 2000 permit for the Kriegers Flak offshore wind farm in Sweden by the Administrative Board of Skåne County, off whose coast the developer aims to build the 640 MW project. Parts of the Kriegers Flak site in the Baltic Sea have been classified as a Natura 2000 area and, […]

  • 21 March 2017
    Business & Finance, Contracts & Tenders, Grid Connection, Operations & Maintenance, Vessels, Wind Farm Update

    Danish transmission system operator Energinet.dk is looking for a provider of manned crew transfer vessels (CTVs) for the transportation of service crews between the harbors of Klintholm/Rødsand and the Kriegers Flak platforms KFA and KFB in the Baltic Sea.