231 results found for 'Hollandse Kust noord'

231 results found for 'Hollandse Kust noord'
Order results by

A list of search results

  • 7 July 2020
    Grid Connection

    Sea & Land Project Engineering has been appointed to provide the detailed design of the offshore transformer station jacket and foundations for the Hollandse Kust Noord offshore wind farm. The offshore transformer station consists of a 45m jacket weighing 1,930t and 870t piles supporting a topside structure consisting of four decks weighing approximately 4,100t, the […]

  • 5 April 2017
    Authorities, Contracts & Tenders, R&D, Wind Farm Update

    The Netherlands Enterprise Agency (RVO.nl), part of the Dutch Ministry of Economic Affairs, issued a call for tenders for geophysical soil investigations at the Hollandse Kust Noord offshore wind farm zone on 5 April.

  • 5 July 2016
    Authorities, Wind Farm Update

    Hollandse Kust Zuid (South) and Hollandse Kust Noord (North) offshore wind zones, totalling 2.1GW of potential offshore wind capacity, have been selected for the construction of offshore wind farms by the Dutch government in an effort to reach the goal of 16% of renewable energy in the country’s energy mix by 2023. Hollandse Kust Zuid, covering […]

  • 21 September 2020
    Business & Finance

    Eneco has joined the Amsterdam IJmuiden Offshore Ports (AYOP), an association focused on the offshore energy sector which gathers more than 85 companies and organisations active in the North Sea Canal region. According to AYOP’s press release from 21 September, the membership will provide Eneco with “an ideal way to work with regional players” on […]

  • 15 September 2022
    Grid Connection, Wind Farm Update

    Equans has loaded out the topside for the offshore substation of the Hollandse Kust Noord offshore wind farm that is being built in the Dutch sector of the North Sea. The company, which is delivering the platform in partnership with Smulders, loaded out the topside on 12 September on the Scheldt along the quay of […]

  • 3 April 2023
    Grid Connection, Wind Farm Update

    The Dutch-German transmission system operator (TSO), TenneT, has announced that the grid connection for the 759 MW Hollandse Kust Noord offshore wind farm is ready for commissioning. Now the wind farm’s operator, CrossWind, can connect the 69 Siemens Gamesa’s SG 11.0-200 DD 11 MW wind turbines to the offshore substation located some 20 kilometres off the […]

  • 4 April 2018
    Contracts & Tenders, Operations & Maintenance

    Fugro will carry out a site characterization program with its geotechnical drilling vessel Fugro Synergy at the Hollandse Kust (Noord) offshore wind farm zone as part of a further contract with the Netherlands Enterprise Agency (RVO.nl).

  • 20 May 2016
    Authorities, R&D, Technology, Wind Farm Update

    Netherlands Enterprise Agency (RVO) has issued a tender for metocean desk study for Hollandse Kust (noord) and Hollandse Kust (zuid) offshore wind farm zones. The purpose of the assignment will be to provide the metocean conditions to serve as input for the design, installation and maintenance of wind turbines, inter-array cables, substations and their support structures at […]

  • 4 March 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    CrossWind, a consortium of Shell and Eneco, has signed agreements with TenneT for the construction of the offshore grid connection for the Hollandse Kust (noord) wind farm. Located in the Dutch North Sea some some 18.5 kilometres off Egmond aan Zee, the 759 MW Hollandse Kust (noord) and its grid connection are scheduled to be […]

  • 12 November 2021
    Grid Connection, Wind Farm Update

    The jacket foundation for the Hollandse Kust (noord) offshore substation has been installed off the northern coast of the Netherlands, TenneT said. The topside for this 700 MW offshore substation is scheduled to be installed in May 2022, the transmission system operator said. After departing from the port of Vlissingen, the jacket arrived at its […]

  • 10 January 2022
    Contracts & Tenders, Technology, Wind Farm Update

    Energy giant Shell has signed a supply contract with thyssenkrupp Uhde Chlorine Engineers for the Hydrogen Holland I large-scale project in the port of Rotterdam, the Netherlands. Under the contract, thyssenkrupp Uhde Chlorine Engineers will engineer, procure and fabricate a 200 MW electrolysis plant based on their large-scale 20 MW alkaline water electrolysis module. The […]

  • 24 April 2020
    Contracts & Tenders

    TenneT TSO has issued a tender seeking Construction All Risk (CAR) insurance for the Hollandse Kust Noord and West Alpha offshore wind farms. The tender is divided into two lots, for a leading insurer and next insurer. The duration of the contract is four years. The deadline for submitting applications for the tender is 4 June. […]

  • 7 May 2020
    Contracts & Tenders, Wind Farm Update

    Shell and Eneco have jointly submitted a bid in a zero-subsidy round of the tender to develop the Hollandse Kust (noord) offshore wind farm in the Dutch North Sea. The two companies are, through their CrossWind joint venture, competing with several other bidders including Ørsted, to develop a wind farm with a capacity of up […]

  • 1 June 2023
    Grid Connection, Wind Farm Update

    The Hollandse Kust Noord platform has been taken over by the Dutch transmission system operator (TSO) TenneT. After a successful project engineering, procurement, construction, installation, and offshore hook-up, the Hollandse Kust Noord platform take-over is now official by signing off the Taking-Over certificate. In March 2020, TenneT awarded the joint venture Equans-Smulders the contract to […]

  • 22 December 2020
    Contracts & Tenders, Wind Farm Update

    Sif has secured a contract with Van Oord for the fabrication and supply of monopiles for the Hollandse Kust Noord offshore wind project in the Netherlands. Sif will manufacture 70 TP-less monopile foundations and store them at its Maasvlakte2 facility in Rotterdam in 2022-2023. “We are grateful for the confidence Van Oord and CrossWind have […]

  • 22 November 2021
    Grid Connection, Wind Farm Update

    LS Cable & System and Jan De Nul have completed the first lot of submarine power cables for the Hollandse Kust Noord and West Alpha offshore wind projects in the Netherlands.

  • 13 October 2021
    Wind Farm Update

    Fugro is carrying out an unexploded ordnance (UXO) survey campaign at the Hollandse Kust Noord offshore wind project in the Netherlands. The goal of the survey, which began in September, is to identify the locations of UXOs in all inter-array cable routes, corridors, and all turbine locations. The activities are supported by NjordIC, who secured […]

  • 27 May 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    TenneT has selected the consortium of ENGIE Fabricom and Iemants to design, engineer, produce, deliver, transport, and install a 700 MW offshore substation for the Hollandse Kust Noord offshore wind farm. The contract also includes the options for identical work on the Hollandse Kust West Alpha and Hollandse Kust West Beta offshore substations. The Hollandse […]

  • 23 September 2021
    Ports & Logistics, Wind Farm Update

    Buss Terminal in Eemshaven has been selected as the pre-assembly and installation port for the wind turbines that will spin as part of the Dutch Hollandse Kust Noord offshore wind farm. Starting in October 2022, the terminal will be serving as a base port for pre-assembly and installation of rotor blades, nacelles, and towers for […]

  • 20 January 2021
    Contracts & Tenders, Wind Farm Update

    Heerema Fabrication Group (HFG) has secured a contract with Iemants, a subsidiary of Smulders, to construct the offshore transformer jacket for the Hollandse Kust Noord offshore wind project. Construction, which will take place at the HFG Vlissingen yard, is expected to begin this month and be completed in September. According to Heerema, the jacket will […]

  • 10 April 2018
    Authorities, Contracts & Tenders, Wind Farm Update

    Netherlands Enterprise Agency (RVO.nl) has launched a market orientation procedure to determine which contractors are willing and able to carry out a morphodynamic assessment of the Hollandse Kust (noord) wind farm zone.

  • 1 April 2020
    Contracts & Tenders, Wind Farm Update

    The Dutch government is opening the tender to develop the Hollandse Kust (noord) offshore wind farm on Thursday, 2 April. The tender will remain open until 30 April. The Dutch government has expressed confidence that, similarly to the Hollandse Kust (zuid) 1 and 2, and the Hollandse Kust (zuid) 3 and 4, this wind farm […]

  • 13 April 2021
    Contracts & Tenders

    The CrossWind consortium has selected ERSG to provide technical personnel for the Hollandse Kust Noord offshore wind project in the Netherlands. As part of the deal, ERSG will provide quality management and inspection manpower for the 759 MW subsidy-free offshore wind farm. “This is a great achievement for the ERSG team, who put together a […]

  • 3 April 2020
    Contracts & Tenders

    Swedish energy company Vattenfall has decided not to participate in the tender for the Hollandse Kust (noord) offshore wind farm in the Netherlands, citing uncertainty over the COVID-19 pandemic as the reason. ”In light of the current COVID-19 situation, we have carefully evaluated our risk-reward balance against the remainder of our strong pipeline and the […]

  • 14 July 2023
    Contracts & Tenders

    CrossWind has awarded Rosetti Marino an Engineering, Procurement, Construction, and Installation and Commissioning (EPCIC) contract for an offshore green hydrogen production and storage plant, located within CrossWind’s Hollandse Kust Noord offshore wind farm in the Netherlands. Rosetti Marino said that the pilot plant, called the Baseload Power Hub and fully integrated into an offshore wind […]

  • 29 June 2017
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    The Netherlands will allow companies interested in developing the 700MW Hollandse Kust Zuid I and II offshore wind farm zones without government subsidies to submit their bids prior to the subsidy and permit tender planned for this autumn.