Search results for: Dogger Bank Wind Farm

881 results

A list of search results

  • 19 June 2023
    Vessels, Wind Farm Update

    Jan De Nul’s new jack-up vessel Voltaire has arrived in the port of Able Seaton, UK, from where it is set to start installing GE Haliade-X offshore wind turbines on the 3.6 GW Dogger Bank Wind Farm in early July. Jan De Nul took delivery of Voltaire from China’s COSCO Shipping Shipyard at the end […]

  • 13 June 2023
    Infrastructure, Vessels

    A steel-cutting ceremony was held for North Star’s service operation vessel (SOV) NB 945 at Vard Vung Tau in Vietnam. This is the fourth SOV to be delivered from VARD to North Star for operation on the Dogger Bank Wind Farm in the North Sea. In March 2021, North Star won the initial contract for […]

  • 2 June 2023
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Correll Group, Cable Installation & Power Services Division has been contracted by DEME Offshore to complete the inter-array cable termination & testing on wind turbines and the offshore substation platform on the first phase of the Dogger Bank offshore wind farm in the UK. The 3.6 GW Dogger Bank Wind Farm is being built in […]

  • 28 March 2023
    Contracts & Tenders, Wind Farm Update

    GE Renewable Energy has contracted Teesside-based company Eastgate Engineering for mechanical and electrical work for the pre-assembly of the towers and nacelles for the Dogger Bank Wind Farm offshore wind turbines, whose components started arriving at the marshalling port in January. Eastgate Engineering’s contract is expected to support approximately 90 local jobs including Electrical and […]

  • 3 June 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    Dogger Bank Wind Farm has chartered two newbuild Commissioning Service Operation Vessels (CSOV) for the construction and commissioning work on Dogger Bank – the world’s largest offshore wind project. Dogger Bank Wind Farm signed charter agreements for one CSOV each with Edda Wind and Awind AS. Under the terms of the contract, Edda Wind will […]

  • 7 August 2020
    Vessels, Wind Farm Update

    Dogger Bank Wind Farm has signed a contract with Jan De Nul Group for the transport and installation of GE Haliade-X offshore wind turbines at Dogger Bank A and Dogger Bank B. The installation of the 12 MW units at the site some 130 kilometres off the Yorkshire coast will start in 2023. Turbine transport […]

  • 19 May 2022
    Contracts & Tenders, Wind Farm Update

    UK-based Fulkrum has secured a contract to support the QA/QC-quality assurance/quality control activities for the first phase of the 3.6 GW Dogger Bank Wind Farm project offshore England. Under the contract, Fulkrum will provide inspection services during the Dogger Bank A development stage, with a possibility of a contract extension to Dogger Bank B and […]

  • 18 May 2021
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farm and GE Renewable Energy have finalised contracts for the supply of 87 Haliade-X 14 MW turbines and a five-year service and warranty agreement for Dogger Bank C, the third and final phase of what will become the world’s largest offshore wind farm. GE Renewable Energy secured a preferred turbine supplier agreement […]

  • 12 July 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    After winning contracts to install GE Haliade-X 13 MW offshore wind turbines at Dogger Bank A & B last year, Jan De Nul has now signed an agreement with Dogger Bank Wind Farm for the transport and installation of 87 GE Haliade-X 14 MW units at the final phase of the project, Dogger Bank C. […]

  • 17 November 2020
    Contracts & Tenders, Wind Farm Update

    The consortium of Sif Netherlands and Smulders Projects Belgium will manufacture all the monopiles and transition pieces for the Dogger Bank A & B offshore wind farm project. Dogger Bank Wind Farm, a joint venture between SSE Renewables and Equinor, awarded the consortium with the contract to manufacture and deliver 190 monopiles and transition pieces […]

  • 6 October 2022
    Business & Finance, Wind Farm Update

    SSE Renewables and Equinor are looking into building what would be the fourth part of Dogger Bank Wind Farm, the world’s largest offshore wind farm, whose three phases (A, B and C) are currently under construction. Surveys are now underway at an offshore site where the partners want to develop Dogger Bank D, which would […]

  • 14 September 2020
    Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farm has signed the contract with OHT to transport and install foundations for the second phase of the world’s largest wind farm – the 3.6 GW Dogger Bank. Dogger Bank Wind Farm and OHT signed the contract for the 1.2 GW Dogger Bank A phase in July. The new contract covers the […]

  • 18 March 2022
    Contracts & Tenders, Wind Farm Update

    Heerema Marine Contractors will transport and install the Dogger Bank C offshore substation under a contract awarded to the company by the Dogger Bank Wind Farm joint venture partners SSE Renewables, Equinor, and Eni. For the third phase of the 3.6 GW Dogger Bank Wind Farm, Heerema will transport and install the project’s 3,500-tonne jacket […]

  • 22 July 2021
    Contracts & Tenders, Vessels

    Red Rock has been awarded a contract by Vard for equipment supply for the three service operations vessels (SOVs) owned by North Star Renewables that have been chartered for the Dogger Bank Wind Farm in the UK. Red Rock will deliver two 2T 3D Motion Compensated cranes, a 5T 3D Motion Compensated crane, three 2T […]

  • 3 January 2023
    Operations & Maintenance, R&D

    Several unexploded ordnance (UXO) items have been identified within Dogger Bank A & B array areas during a UXO inspection campaign. The UXO items will be addressed during a separate UXO Clearance phase of work estimated to be performed around February 2023. The Dogger Bank A, B, and C UXO inspection campaign started on 8 June 2022 […]

  • 9 May 2022
    Ports & Logistics, Wind Farm Update

    Smulders has loaded out and sent off the first four of the 95 transition pieces for the first phase of Dogger Bank Wind Farm from its yard in Hoboken, Belgium. The first batch of transition pieces was loaded out on 19 and 20 April and shipped to Sif’s Maasvlakte 2 terminal in Rotterdam, the Netherlands, […]

  • 4 May 2021
    Grid Connection, R&D, Technology, Wind Farm Update

    Dogger Bank Wind Farm, the world’s largest offshore wind project, will use what the developers say is ”a revolutionary platform design, unveiling the world’s first unmanned High Voltage Direct Current (HVDC) offshore substation.” When complete in 2026, the 3.6 GW Dogger Bank wind farm will become the biggest in the world, able to produce enough […]

  • 8 June 2023
    Infrastructure, Vessels

    North Star has held a naming ceremony for the Grampian Tyne service operation vessel (SOV) that will be deployed at the 3.6 GW Dogger Bank Wind Farm in the UK. The vessel was named at Equinor’s Port of Tyne base in the North East of England ahead of its early handover to the Dogger Bank […]

  • 11 February 2022
    Business & Finance, Wind Farm Update

    Italian oil and gas major Eni has completed the aquisition of a 20 per cent stake in the 1.2 GW Dogger Bank C offshore wind farm in the UK. Eni bought the stakes from Equinor (ten per cent) and SSE Renewables (ten per cent). Eni is already a partner with SSE Renewables and Equinor on […]

  • 18 April 2023
    Vessels, Wind Farm Update

    The heavy lift vessel Seaway Strashnov has returned to the Dogger Bank A offshore wind farm site to resume the installation of monopile foundations. Meanwhile, the crane vessel Thialf has installed the jacket foundation for the Dogger Bank A offshore substation and will soon move on to the installation of the topside. The foundation installation on […]

  • 9 July 2021
    Grid Connection, Wind Farm Update

    Delivery of onshore cables for Dogger Bank Wind Farm has started, according to Jones Bros Civil Engineering UK, the company responsible for installing the cables for the first two phases of the offshore wind project. The first drum with the cables has already arrived and Jones Bros are set to commence installation this month. In […]

  • 9 June 2021
    Vessels, Wind Farm Update

    The Fugro Synergy survey vessel is currently conducting a geotechnical survey in the Dogger Bank C array area and export cable route, while the vessel Wind of Pride is performing inspection works in the Dogger Bank A array area and the export cable routes for Dogger Bank A & B. According to the latest update […]

  • 6 February 2023
    Wind Farm Update

    SSE Renewables and Equinor, the developers of the Dogger Bank Wind Farm in the UK, are exploring two options for Dogger Bank D, the fourth wind farm the partners are looking to build as part of the development. These include using Dogger Bank D for electricity that would feed into the UK grid and/or for […]

  • 12 May 2023
    Vessels, Wind Farm Update

    Jan De Nul’s new offshore wind installation vessel Voltaire has called Port Esbjerg after arriving from the UAE and before heading to the UK for its first assignment. Voltaire is so far the largest installation vessel to call the Danish port, where it will mobilise for work on Dogger Bank Wind Farm. The jack-up was […]

  • 26 July 2011
    Authorities, Wind Farm Update

    Scarborough Council says years of work to capitalise on an unprecedented period of economic opportunity with the arrival of the world’s largest wind farm is now paying off, with a host of companies focusing “serious inward investment” on the North Yorkshire coast. The announcement comes following top-level talks between Scarborough Council chiefs and Yorkshire and […]

  • 8 September 2020
    Business & Finance, Wind Farm Update

    Dogger Bank Wind Farm and its tier 1 contractors are holding a series of supply chain webinars for the 3.6 GW offshore wind project. The webinars will focus on introducing the Dogger Bank wind farm development and the tier 1 contractors, and will showcase the opportunities the project offers with a particular focus on tier […]