  • 7 August 2020
    Wind Farm Update

    The Borssele III & IV offshore wind farm produced first power early in the morning on 7 August, the Blauwwind consortium informs. “This marks a key milestone in the construction of the project as the first turbine is now generating power and delivering renewable electricity into the Dutch grid”, the developer said. The first of […]

  • 21 July 2017
    Contracts & Tenders, Grid Connection, Technology, Wind Farm Update

    In October, Australian company Gap Explosive Ordnance Detection (EOD) will deliver a new system for detection of unexploded ordnance (UXO) to Boskalis, recently contracted together with Fugro to survey and identify UXO along the cable routes for the planned grid connection between TenneT’s two offshore platforms and its high-voltage substation onshore.

  • 17 September 2017
    Contracts & Tenders

    Three Offshore Wind Projects Secure Contracts for Difference as Strike Prices Go Down The UK government has awarded three offshore wind projects with Contracts for Difference (CfD) in the second round of auctions with strike prices going as low as GBP 57.50/MWh for projects scheduled for commissioning in 2022/23. North Sea Wind Power Hub Consortium […]

  • 3 September 2018
    Environment, R&D

    Van Oord and Eneco, together with the North Sea Foundation and the Natuur & Milieu organization, are launching the Rich North Sea project dedicated to restoring natural underwater features around offshore wind farms.

  • 1 February 2017
    Authorities, Business & Finance, Contracts & Tenders, Environment, Grid Connection, Operations & Maintenance, R&D, Technology, Training & Education, Vessels, Wind Farm Update

    Ex-Statkraft Engineer Develops New Foundation Installation Solution Arild Bolsø, an engineer who worked for Statkraft in Norway and Forewind in the UK, has developed a new technical concept for offshore wind foundation installation. According to Bolsø, the concept would reduce installation time by 30-50%, compared to current methods. Public Consultation for Borssele V Tender Opens […]

  • 24 December 2019
    Business & Finance, Grid Connection

    The European Investment Bank (EIB) has approved funding for the Tennet South-West 380KV West grid project in the Netherlands. EIB will provide around EUR 250 million in funding for the project valued at around EUR 509 million. The TenneT South-West 380KV West comprises the construction of the electricity transmission corridor connecting Borsselle to Rilland, in […]

  • 1 September 2017
    Grid Connection

    Dutch transmission system operator TenneT TSO B.V. and the Schiedam-based HSM Offshore have cut the first steel for the Borssele Alpha offshore transformer station and have signed a contract for the construction of the Borssele Beta platform.

  • 6 March 2020
    Grid Connection

    HSM Offshore B.V. has appointed Rhenus Offshore Logistics B.V. for the commissioning logistics of the Borssele Beta offshore high voltage substation. The 700MW Borssele Beta will connect the Borssele 3 & 4 offshore wind farm to the Dutch grid. Offshore construction on the 731.5MW project started in October 2019, with the commissioning scheduled for 2021. HSM Offshore rolled out […]

  • 14 February 2017
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Dutch transmission systems operator TenneT TSO B.V. has awarded a contract to the Schiedam-based HSM Offshore for the construction of offshore transformer stations required to link up the wind farms to be built offshore at Borssele in the south-west of the Netherlands. The contract concerns the offshore platform for the Borssele Alpha wind farm zone. […]

  • 7 November 2018
    Business & Finance, Contracts & Tenders, Grid Connection

    Nexans will provide up to 190km of inter-array cable rated at a maximum operating capacity of 72.5kV for the 752MW Borssele 1 and 2 offshore wind project in the Netherlands as part of the recently-announced contract.

  • 30 May 2018
    Grid Connection, Wind Farm Update

    Work on the jacket foundation for the 700MW Borssele Alpha offshore transformer station is in full swing at HSM Offshore’s yard in Schiedam, the Netherlands, as this photo shared by Ørsted shows.

  • 30 March 2020
    Grid Connection

    The Borssele Beta offshore substation topside has sailed out from HSM Offshore’s yard in Schiedam to the installation site in the Dutch North Sea, TenneT said. The 700MW offshore grid connection is scheduled to be operational on September 1, the Dutch transmission system operator said. Borssele Beta will connect the 731.5MW Borssele III and IV […]

  • 18 June 2018
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Prysmian Group has been awarded a contract by Van Oord Offshore Wind B.V. to provide a submarine inter–array cable system for Borssele III & IV offshore wind project in the Dutch North Sea.

  • 31 October 2017
    Business & Finance, Contracts & Tenders, Grid Connection

    NKT’s part of the contract for Borssele Beta, won in a consortium with VBMS, is valued at approximately EUR 90 million. As reported earlier, the contract value for VBMS is approximately EUR 70 million.

  • 10 March 2020
    Grid Connection

    HSM Offshore has loaded out the Borssele Beta offshore substation topside at its yard in Schiedam, the Netherlands. The 700MW Borssele Beta high voltage substation will connect the 731.5MW Borssele 3 & 4 wind farm to the Dutch grid. The substation’s jacket foundation, also built by HSM Offshore, was installed at the site off Zeeland in May 2019. The […]

  • 9 April 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Van Oord has awarded Dutch high voltage specialists Visser & Smit Hanab with a contract to perform all array cable terminations and testing work at the Borssele III and IV offshore wind farm in the Dutch North Sea. A total of 77 MHI Vestas V164 9.5 MW wind turbines will be connected to the Borssele […]

  • 7 August 2018
    Grid Connection

    Seaway Heavy Lifting’s vessel Oleg Strashnov has installed the jacket foundation for TenneT’s Borssele Alpha offshore transformer station in the Dutch North Sea.

  • 19 December 2016
    Grid Connection, Technology

    TenneT has provisionally awarded Heijmans and Europoles with a EUR 200 million contract for the design and construction of high-voltage Wintrack pylons and foundations for the Eemshaven-Vierverlaten (Noordwest 380kV) and Borssele-Rilland (Zuidwest 380kV West) grids in the Netherlands.  The Noordwest 380kV project involves replacement of the existing high-voltage connection (220kV) between Eemshaven and Vierverlaten with […]

  • 6 July 2017
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Blauwwind II C.V., a consortium behind the Borssele III and IV offshore wind project, has applied for a loan with the European Investment Bank (EIB) to support the development of the 740MW offshore wind farm in the Dutch part of the North Sea.

  • 2 September 2015
    Grid Connection

    TenneT, the Dutch electricity transmission system operator, has mapped the export cable route for the Borssele offshore wind farm zone. The cable will come ashore at Borssele, less than a kilometre from TenneT’s existing 380 kV substation. “This is the outcome of an intensive process, in which all interests are identified and weighted. The Ministries […]

  • 29 June 2018
    Business & Finance, Wind Farm Update

    The Blauwwind consortium has achieved financial close on the Borssele III & IV offshore wind farms in the Netherlands, moving the project to the construction phase, with the main offshore works due to start in the fourth quarter of 2019. 

  • 20 March 2020
    Grid Connection

    The Borssele Beta offshore substation topside will sail out from HSM Offshore’s yard in Schiedam to the installation site in the Dutch North Sea on 22 March, TenneT said. The 700MW offshore grid connection is scheduled to be operational on September 1. From then on, the 731.5MW Borssele III and IV wind farm that is […]

  • 3 December 2015
    Business & Finance, Grid Connection, Operations & Maintenance, Technology, Wind Farm Update

    TenneT has signed framework agreements for the future supply of Gas Insulated Switchgear (GIS) with Alstom Grid Netherlands, and the supply of power transformers with CG Power Systems Belgium, for the Dutch offshore power grid. This equipment will form the ‘heart’ of five offshore platforms that will transmit the power from five new wind locations to […]

  • 6 April 2016
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    The Netherlands will start the tendering procedure for the Borssele I and II offshore wind farms on 10 April, following the last month’s adoption of the amendment to the Electricity Act 1998 which allowed further development of offshore wind energy projects in the country. The window for submitting bids will remain open until 12 May, the Netherlands Enterprise Agency (RVO.nl) said. RVO.nl also […]

  • 27 November 2017
    Contracts & Tenders, Grid Connection, Technology

    HSM Offshore has contracted Joulz Energy Solutions as subcontractor for TenneT’s 700MW Borssele Beta to be built offshore at Borssele in the south-west of the Netherlands.

  • 9 March 2020
    Business & Finance, Grid Connection

    The European Investment Bank (EIB) has signed a EUR 250 million loan agreement with TenneT for the western section of the Zuidwest 380kV offshore grid project in the Netherlands. The financing will support the construction of a new 380kV transmission line, combined with a 150kV line for part of the route, from the substation at […]