  • 20 February 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Vesterhav Nord (North) offshore wind farm, owned by Vattenfall, started producing power on 16 February, joining its sister park Vesterhav Syd, which began generating electricity in January 2024. Vesterhav Nord is part of Vattenfall’s 344 MW Vesterhav duo, whose 168 MW Vesterhav Syd (South) has been feeding power into the Danish grid since January. The […]

  • 13 November 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 170 MW Vesterhav Syd offshore wind farm, developed by Vattenfall in Denmark, has delivered its first green power. The installation of 20 8.4 Siemens Gamesa wind turbines took place from July to September this year, and Vattenfall’s initial plan was to connect the turbines to the grid immediately after the installation. However, the plan […]

  • 9 January 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Vattenfall has commissioned all wind turbines at the offshore wind farm Vesterhav Syd in Denmark, which is now fully operational and feeding power into the Danish grid. Vesterhav Syd (South) is part of Vattenfall’s 344 MW Vesterhav duo, whose Vesterhav Nord (North) wind farm the company expects to connect to the grid during the first […]

  • 12 March 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 21 wind turbines at Vattenfall’s Vesterhav Nord (North) offshore wind farm have delivered the first power and the 176 MW project is now connected to the Danish electricity grid. However, the blades on a single unit have been temporarily taken down for repairs after sustaining damage during the preparation of the offshore wind farm. […]

  • 19 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 21st and final wind turbine was installed at the Vesterhav Nord wind farm in the Danish North Sea on Wednesday, 18 October, Vattenfall, the owner and developer of the project, said. The milestone completes the wind turbine installation scope at the Vesterhavn Nord, and the 20-turbine Vesterhavn Syd wind farm. Vattenfall expects to be […]

  • 5 June 2023
    Contracts & Tenders, Wind Farm Update

    The Correll Group – Cable Installation & Power Services Division has been awarded a contract by Asso.subsea to deliver the offshore pull-ins and termination & testing of 66 kV export and inter-array cables for the Vesterhav Nord and Syd offshore wind farms in Denmark. The Vesterhav Nord and Syd, being developed by Vattenfall, consist of […]

  • 12 July 2023
    Authorities, Wind Farm Update

    The Danish Energy Agency (DEA) has granted Vattenfall an electricity production permit for the Vesterhav Syd and Nord offshore wind farms. The electricity production licence, which is granted before a wind farm is put into operation, is issued in accordance with Section 29 of the Act on the Promotion of Renewable Energy, said DEA. The […]

  • 2 November 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    Mainprize Offshore has won a contract for the provision of crew transfer vessels (CTVs) during the construction phase of the Vesterhav Nord and Syd offshore wind farms in the Danish North Sea. Under the contract, awarded following a tendering procedure, the UK-based company will be providing a 24-pax crew transfer vessel from March until November […]

  • 15 February 2023
    Contracts & Tenders, Infrastructure, Ports & Logistics

    DEME Group and the Port of Thyboron have signed a contract regarding the installation of foundations for Vattenfall’s Vesterhav Nord and Syd offshore wind farms in the Danish North Sea. The foundations that DEME will be installing include 41 monopiles and transition pieces (TPs). The 77-metre-long monopiles, each weighing around 622 tonnes will be produced […]

  • 16 May 2023
    Contracts & Tenders, Wind Farm Update

    FairWind has been awarded a turnkey pre-assembly contract for the Vesterhav Nord and Syd offshore wind farms at the Port of Esbjerg in Denmark. Under the contract, FairWind will be responsible for the pre-assembly erection of 41 Siemens Gamesa’s SG 8.0-167 DD wind turbines. Each direct drive (DD) wind turbine will have a power generating […]

  • 25 November 2021
    Contracts & Tenders, Wind Farm Update

    Vattenfall has awarded Bladt Industries with the contract to manufacture and deliver transition pieces for the Vesterhav Syd and Vesterhav Nord offshore wind farms in the Danish North Sea. Bladt Industries will fabricate a total of 41 transition pieces for the Vesterhav project, 21 units for Vesterhav Nord, and 20 units for Vesterhav Syd. The […]

  • 10 August 2015
    Authorities, R&D, Wind Farm Update

    The Danish Energy Agency (DEA) has extended the deadline for public hearing of EIA for Sæby nearshore wind farm. New deadline for comments is 24 August, 2015. The deadline is extended to give local MPs, in the newly elected parliament, and others a better opportunity to comment on the EIA. This year, the DEA launched a call for […]

  • 25 September 2017
    Contracts & Tenders, Wind Farm Update

    Vattenfall has invited tenders for the installation of foundations for three projects in Denmark: Danish Kriegers Flak in the Baltic Sea, and Vesterhav Nord and Vesterhav Syd in the North Sea.

  • 12 November 2018
    Environment

    Vattenfall and the Danish Armed Forces have uncovered and detonated two English mines in the area of the Danish North Sea where the Vesterhav Nord offshore wind farm is being built.

  • 21 October 2022
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Hellenic Cables has awarded Vos Prodect with a contract to deliver its sealed cable hang-off systems for the Vesterhav Nord and Syd offshore wind farms in the Danish North Sea. Vos Prodect said it will perform an extensive test program at the testing facility using the 66kV cross-linked polyethylene (XLPE) insulated inter-array cables. According to […]

  • 16 July 2015
    R&D, Wind Farm Update

    Danish transmission system operator Energinet.dk has announced that Environmental Impact Assessments (EIAs) for Smålandsfarvandet and Sejerø Bugt nearshore wind farms are now available, and will be in public consultation until 23 September, 2015. A public meeting regarding the EIAs will be held on 1 September for Smålandsfarvandet and for Sejerø Bugt the following day. The Danish Energy Agency […]

  • 6 July 2023
    Authorities, Wind Farm Update

    The Danish Energy Board of Appeal has revoked the Danish Energy Agency’s establishment permit for the Aflandshage offshore wind farm, which the project developer HOFOR received in the autumn of 2022. HOFOR said in a press release issued this morning (6 July) the Board notified the company that it was revoking the establishment permit granted to the Aflandshage offshore […]

  • 24 June 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    Northern Offshore Services (N-O-S) has won an EU tender to provide two crew transfer vessels (CTVs) to support operations and maintenance (O&M) activities at the Vesterhav Nord and Syd offshore wind farms in the Danish North Sea. The tender was carried out by Vattenfall Vindkraft A/S. The two CTVs will support yearly maintenance campaigns at […]

  • 14 December 2017
    Business & Finance

    Vattenfall’s three Danish offshore wind projects are progressing on schedule following the order of wind turbines from Siemens Gamesa Renewable Energy, Gunnar Groebler, Senior Vice President Business Area Wind at Vattenfall, said.

  • 22 September 2017
    Contracts & Tenders

    Vattenfall has invited foundation manufacturers to pre-qualify to be able to participate in the tender for the delivery of monopile foundations for three projects in Denmark: Kriegers Flak and Vesterhav Nord and Vesterhav Syd nearshore wind farms.

  • 16 December 2022
    Authorities, Wind Farm Update

    The Danish Environmental Protection Agency has started the second phase of public consultation for the new environmental impact assessment (EIA) of the onshore part of Vattenfall’s Vesterhav Syd offshore wind farm, which is being re-considered, together with that of its sibling project Vesterhav Nord. Namely, the two nearshore wind farms were grated environmental permits in […]

  • 6 May 2015
    Contracts & Tenders

    With the publication of the contract notice in February, the Danish Energy Agency (DEA) officially launched the tender of nearshore wind farms totaling 350 MW in up to six sites. The six sites are Vesterhav Nord, Vesterhav Syd, Sæby, Sejerø Bugt, Smålandsfarvandet and Bornholm. This is now followed by the preliminary tender documents, which are […]

  • 13 April 2016
    Authorities, Business & Finance, Environment, Grid Connection, Wind Farm Update

    Danish authorities have decided that the Sejerø Bugt site is off limits to nearshore wind developers and that the deadline for submitting final bids for other five sites is now pushed to 1 September, the Danish Wind Industry Association said. Sejerø Bugt was identified as one of six sites suitable for development of nearshore wind farms, and […]

  • 22 September 2017
    Contracts & Tenders, Wind Farm Update

    Along with its call for monopile maufacturers to pre-qualify for the tender for three Danish offshore wind projects, Vattenfall issued a pre-qualification call for the supply of transition pieces. 

  • 6 March 2015
    Authorities

    Danish Energy Agency (DEA) has issued a call for Expression of Interest (EoI) for the construction and operation of nearshore wind farms with a total capacity of up to 350 MW. Six areas will be offered for tender at the same time and projects within these sites will be competing against each other. The concession owner shall build and operate […]

  • 23 November 2021
    Business & Finance, Grid Connection, Wind Farm Update

    Vattenfall has awarded Asso.subsea with a contract for the transportation, installation, protection and commissioning of the 66 kV export and inter-array cables for the Vesterhav Nord and Syd offshore wind projects in Denmark.