Search results for: ostwind 2

111 results

A list of search results

  • 20 December 2023
    Cables, Fixed-Bottom, Foundations, Grid Connection, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Van Oord has completed the installation of all foundations and inter-array cables at Iberdrola’s Baltic Eagle offshore wind farm in the German sector of the Baltic Sea. The heavy-lift installation vessel Svanen installed the final monopile in September and the company has now put all the transition pieces (TPs) in place. The TPs were installed […]

  • 5 December 2023
    Project Updates, Wind Farm Update

    The Arcadis Ost 1 offshore wind farm is now supplying its full capacity to the German electricity transmission grid, according to the transmission system operator (TSO) 50Hertz. 50Hertz built the submarine and onshore cable connection to the Lubmin substation and worked with the wind farm operator Parkwind to construct the offshore platform. Parkwind’s 257 MW […]

  • 26 February 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Iberdrola Deutschland and O2 Telefónica have signed a long-term power purchase agreement to supply renewable power from the 476 MW Baltic Eagle offshore wind farm in the German Baltic Sea. Under the 15-year agreement, Iberdrola will supply 3,000 GWh of renewable energy to O2 Telefónica from the Baltic Eagle offshore wind project, starting in 2025. […]

  • 18 March 2024
    Business & Finance, Business development, Fixed-Bottom

    Abu Dhabi-based Masdar has achieved close on the financing of its 49 per cent shareholding in the 476 MW Baltic Eagle offshore wind farm in Germany. According to Masdar, the total lending package amounted to EUR 488 million, with participation from ABN AMRO, Credit Agricole CIB, ING, Santander, and Siemens Bank. The Baltic Eagle offshore wind […]

  • 6 October 2023
    Contracts & Tenders, Supply Chain

    Van Oord has contracted Jumbo Offshore to transport and install transition pieces (TPs) for Iberdrola’s Baltic Eagle offshore wind project in the German Baltic Sea. Operations on the project are to commence this month. Van Oord recently installed all monopiles and began inter-array cable installation activities at the Baltic Eagle site northeast of the Rügen […]

  • 9 January 2024
    Contracts & Tenders, Grid Connection, Supply Chain

    German offshore transmission system operator (TSO) 50Hertz Offshore GmbH has issued a contract notice for the engineering, procurement, construction, and installation (EPCI) of the 2 GW HVDC offshore platform and converter system for the Ostwind 4 grid connection project. The scope consists of the respective complete substructure and topside of the offshore platform and the […]

  • 4 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    Van Oord has commenced inter-array cable installation activities at Iberdrola Deutschland’s 476 MW Baltic Eagle offshore wind farm in Germany. After Van Oord’s heavy lift installation vessel Svanen completed the installation of all 50 monopiles for the Baltic Eagle offshore wind farm, Van Oord now continues installing transition pieces and starts cable installation. According to […]

  • 29 September 2023
    Business & Finance, Cables, Energy Islands, Grid Connection, Manufacturing, Onshore Infrastructure, Supply Chain

    German transmission system operator (TSO) 50Hertz has awarded several contracts to power cable manufacturers NKT and Prysmian. Valued at around EUR 4.6 billion in total, the contracts include offshore wind farm export cables, onshore energy connections, and interconnection for an energy island. NKT and Prysmian secured the orders following the tender procedure that 50Hertz launched […]

  • 26 July 2023
    Collaboration, Contracts & Tenders, Outlook & Strategy, Wind Farm Update

    Abu Dhabi-based Masdar has signed a strategic partnership with Iberdrola to co-invest in the 476 MW Baltic Eagle offshore wind farm in the German Baltic Sea. According to the terms of the deal, the Baltic Eagle wind farm is valued at approximately EUR 1.6 billion. Under the agreement, Iberdrola will control and manage the asset, […]

  • 20 June 2023
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Iberdrola Deutschland and SHS – Stahl Holding Saar, an operational management holding company that performs tasks for the two major steel companies in the German state of Saarland, Dillinger and Saarstahl, have signed a 15-year power purchase agreement (PPA) for the Baltic Eagle offshore wind farm. Under the PPA, SHS will cover 200 GWh of […]

  • 31 May 2023
    Grid Connection, Wind Farm Update

    50Hertz has completed the pull-in of two 220 kV subsea cable systems into Iberdrola’s Baltic Eagle platform. The two 220 kV subsea cable systems were previously laid on the seabed in a safe area next to the destination of the substation platform. In February of this year, the substation platform was installed at its intended […]

  • 19 November 2020
    Grid Connection

    50Hertz has begun onshore cable activities near the Lubmin substation of the Ostwind 2 grid connection project in Germany. According to 50Hertz, specialized companies started using the so-called cable train for the 3km long onshore connection between the landing site at Greifswalder Bodden and the Lubmin substation. The transmission system operator added that works on […]

  • 2 October 2019
    Grid Connection

    50Hertz and Parkwind have signed a Memorandum of Understanding (MoU) to collaborate on the technical aspects of the Ostwind 2 grid connection project in the German Baltic Sea. The essential aspects of the MoU include specific agreements for the development, procurement, construction and operation of the shared offshore platform, Ostwind 2, covering basic technical details and […]

  • 29 June 2021
    Grid Connection

    German transmission system operator for the Baltic Sea, 50Hertz, has pulled in the land cables for the Ostwind 2 offshore grid connection. The Ostwind 2 land cables have now been installed underground over a distance of three kilometres from the landing point, where the sea cables meet the mainland, to the Lubmin transformer station. Using […]

  • 21 July 2021
    Grid Connection

    50Hertz has reported that new transformers for the onshore substation for the Ostwind 2 offshore grid connection project have been delivered. The substation in Lubmin was first expanded in size and, with the new transformers, its transmission capacity is now being expanded. Preparatory work for connecting the transformers is currently taking place, including the installation […]

  • 4 June 2021
    Contracts & Tenders, Grid Connection

    German offshore transmission system operator (TSO) 50Hertz has issued a tender seeking a provider of the 220 kV submarine and onshore cable system for the Ostwind 3 grid connection. The selected party will be in charge of the design, engineering, construction, installation, handling and commissioning of the cable system that will connect the onshore substation […]

  • 12 March 2021
    Grid Connection

    The first cable section for the Ostwind 2 offshore grid connection was installed in the German part of the Baltic Sea in recent weeks, the transmission system operator 50Hertz said. In the coming months, further cables will be laid in individual sections along the 90-kilometre-long route. The work is being carried out by a consortium […]

  • 26 November 2018
    Contracts & Tenders, Grid Connection

    Boskalis and NKT have secured export cable contracts by 50Hertz for the Ostwind 2 offshore grid connection in Germany.

  • 10 December 2021
    Grid Connection, Wind Farm Update

    The second of the three 220 kV export cable systems for the Ostwind 2 project in the German Baltic Sea has been laid, 50Hertz Transmission GmbH said. This brings the connection of the Baltic Eagle offshore wind farm another step closer, the German transmission system operator said. The third and final cable is to be […]

  • 21 April 2021
    Grid Connection, Vessels

    NKT’s new cable barge NKT Agrippina has been loaded with a cable section for the offshore wind connection project Ostwind 2 in the German part of the Baltic Sea and will soon set out on its maiden trip after being christened on 20 April. The vessel has been specially designed to transport offshore power cables […]

  • 23 September 2020
    Environment, Grid Connection

    50Hertz has completed UXO clearance at the Ostwind 2 grid connection project in the German Baltic Sea.  The project comprised unexploded ordnance recovery at the subsea cable routes that will connect the Arcadis Ost 1 and Baltic Eagle offshore wind farms to the German high voltage grid. Activities were completed between the landfall near Lubmin and the […]

  • 14 April 2021
    Contracts & Tenders

    German offshore transmission system operator (TSO) in charge of the Baltic Sea infrastructure, 50Hertz, has opened a tender for unexploded ordnance (UXO) operations on the cable route of the Ostwind 3 project. The work scope encompasses provision and operation of all assets necessary for the UXO campaign works, including reporting and interfacing with the employer […]

  • 15 January 2019
    Contracts & Tenders, Grid Connection, Operations & Maintenance

    The Denmark-based Peter Madsen Rederi (PMR) has won a contract by 50Hertz to provide boulder clearance at the Ostwind 2 grid connection project in the German Baltic Sea.  The project comprises boulder clearance and extensive survey works at the three cable routes which will connect the Arcadis Ost 1 and Baltic Eagle offshore wind farms to the German […]

  • 9 November 2021
    Grid Connection, Wind Farm Update

    The final section of the second of the three 220 kV export cable systems for the Ostwind 2 project is being laid in the German Baltic Sea, 50Hertz Transmission GmbH said. Around 170 kilometres of export cables have been laid at sea and on land over the past months to connect two offshore wind farms […]

  • 20 July 2022
    Grid Connection, Wind Farm Update

    Transmission system operator 50Hertz has announced that the Arcadis Ost 1 offshore substation has been connected to the German extra-high voltage grid after the 220 kV submarine cable required for this was pulled into place on the platform over the past few days. Final assembly and commissioning works will now follow. “We are very proud […]

  • 23 February 2023
    Grid Connection, Wind Farm Update

    Heerema Marine Contractors has installed the offshore substation topside for Iberdrola’s Baltic Eagle offshore wind farm in Germany. The substation topside, which was completed last month, was installed by Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Thialf. The jacket foundation had been placed on the construction site in October 2022. The installation involved the heaviest lifting […]