241 results
A list of search results
-
All 47 Siemens Gamesa 8 MW wind turbines have been installed at the 376 MW Formosa 2 wind farm off the Miaoli coast in Taiwan. The last wind turbine was successfully installed on Tuesday, 31 January. The AIS data shows Fred. Olsen Windcarrier’s jack-ups Blue Tern and Bold Tern working on the wind farm at […]
-
Contracts & Tenders, Wind Farm Update
EDS HV Group (EDS), a subsidiary of James Fisher Renewables (JF Renewables), has been awarded a multi-million-pound contract to provide high voltage support services at the Formosa 2 wind farm offshore Taiwan. EDS will support the management of the high voltage network and the electrical safety during the construction and commissioning phase of the project, […]
-
Business & Finance, Contracts & Tenders, Wind Farm Update
TotalEnergies and Corio Generation have signed a joint venture partnership to develop the Formosa 3 offshore wind farms in Taiwan. Under this agreement, Corio will remain the majority shareholder and lead developer with 50 per cent plus ten shares overall in the project. The announcement comes after Taiwan’s Bureau of Energy confirmed in late December […]
-
All 47 wind turbine jacket foundations and all subsea cables are now in place at the Formosa 2 offshore wind farm in Taiwan. The wind farm also has more than half of its wind turbines installed so far. The final jacket foundation was installed on 26 August, with the subsea cable works reaching completion on […]
-
Authorities, Contracts & Tenders, Wind Farm Update
Taiwan’s Ministry of Economic Affairs (MOEA) has selected ten offshore wind projects in the first auction of the Round 3 Zonal Development Phase. The ten projects are proposed by: Copenhagen Infrastructure Partners (CIP); Corio Generation and JERA; Northland Power; Synera Renewable Energy (SRE; formerly known as Swancor Renewable Energy); Taiya Renewable Energy and EDF Renewables; and […]
-
Seaway 7 has completed the installation of the last of 188 pin piles on the Formosa 2 offshore wind farm in Taiwan. The installation was carried by the vessels Seaway Yudin and Siem Barracuda. The first batch of pin piles was manufactured and offloaded at the Port of Taichung in July 2020. Each of the […]
-
Business & Finance, Wind Farm Update
Ørsted expects to reach a final investment decision (FID) on its next offshore wind project in Taiwan, the 920 MW Greater Changhua 2b & 4, during this year, as planned. This will move the project into the construction phase and set it on the path towards commissioning in 2025. Ørsted was awarded rights to build […]
-
Business & Finance, Contracts & Tenders
Ørsted has decided not to submit a bid in the first auction of the Round 3 Zonal Development Phase in Taiwan, the developer announced on 30 September. “As the largest and most experienced offshore wind developer in Taiwan, we had to take stock of the limitations set by the current regulation, which in combination with […]
-
Authorities, Contracts & Tenders
Taiwan’s Ministry of Economic Affairs (MOEA) has narrowed down the list of offshore wind projects selected in the latest allocation round and has now awarded capacity to seven out of the initially chosen ten future offshore wind farms. On 14 December, MOEA announced that ten projects were selected in the first auction of the Round […]
-
Taiwan’s Formosa 2 offshore wind farm has passed two significant construction milestones, completing the installation of twelve turbines and transmitting power to the national grid. According to Formosa 2, the offshore wind farm has now completed more than half of the foundation installations and more than a quarter of the wind turbines have been installed […]
-
Contracts & Tenders, Wind Farm Update
Heerema Marine Contractors (HMC) has completed the final pin pile load-out for Ørsted’s Greater Changhua 1 & 2a offshore wind project in Taiwan. In July 2021, all of the 333 pin-piles that will support the wind farm’s three-legged jacket foundations were manufactured, according to Ørsted. The first units were made by Taiwanese suppliers Century Wind […]
-
Australian marine services provider MMA Offshore has completed the conversion of its anchor handling tug supply (AHTS) vessel MMA Crystal and reflagged it to support the offshore renewable energy market in Taiwan. The AHTS, which already worked on an offshore wind project in Taiwan, having supported a pre-installation noise mitigation survey at Formosa 2 last year, has been […]
-
Business & Finance, Vessels, Wind Farm Update
Saipem has reported that the company reached two important milestones in offshore wind this month following the installation of the offshore substation at the Saint-Brieuc wind farm site in France and the delivery of the final of its batch of jacket foundations for the Formosa 2 offshore wind farm in Taiwan. The transport and installation […]
-
Business & Finance, Contracts & Tenders, Wind Farm Update
Japanese utility JERA and Corio Generation, the new specialist offshore wind business of Macquarie’s Green Investment Group (GIG), announced on 30 June that they were ready to bid for the third phase of Taiwan’s offshore wind zonal development with their Formosa 3 project. JERA and Corio (GIG at the time) have already partnered in Taiwan […]
-
Business & Finance, Wind Farm Update
Subsea 7 has updated its Adjusted EBITDA guidance for the full year 2022 following reduced progress on two offshore wind projects and vessel reshuffle at its subsidiary Seaway 7. Seaway 7 announced provisions against the results of project execution of offshore windfarm installations due to increased costs relating to weather delays and mechanical breakdowns. This, […]
-
Authorities, Wind Farm Update
Formosa 4, an offshore wind project being developed by Swancor Renewable Energy (SRE) in Taiwan, has received the preliminary approval of its Environmental Impact Assessment (EIA). The project, also known as Miaoli 3, was the first of the nine projects for which Taiwan’s Environmental Protection Agency (EPA) started the review process in March this year. […]
-
Ports & Logistics, Vessels, Wind Farm Update
Wind farm installation vessel Seajacks Zaratan has left Akita Port in Japan loaded with the first sets of wind turbine components to be installed on the 140 MW Akita Noshiro offshore wind farm. Akita Noshiro comprises two sites off Akita Port and Noshiro Port. In total, the two wind farms will feature 33 MHI Vesta V117-4.2 MW wind […]
-
Taiwan’s Formosa 2 offshore wind farm has reached financial close, Macquarie’s Green Investment Group (GIG) said. Formosa 2 has been jointly developed by Macquarie Capital (75%) and Swancor Renewable Energy (25%). GIG will now play a role in delivering the project through its construction phase. The 376MW offshore wind project located off the coast of Miaoli […]
-
Specialist Marine Consultants (SMC) has secured a contract to provide marine coordination services for the Formosa 2 offshore wind farm in Taiwan. As for the Formosa 1 Phase 2 project, SMC will work with SeaPlanner and local communications company Mercury Data Systems to deliver a comprehensive marine coordination solution. This will comprise the design, communications […]
-
The European Commission has approved the acquisition of joint control by JERA, Macquarie and Swancor over the Formosa 2 offshore wind project in Taiwan. The 376MW Formosa 2 offshore wind project is currently owned by Macquarie and Swancor. The Commission concluded that the proposed acquisition would raise no competition concerns as Formosa 2 has no activity within the European Economic […]
-
MMA has completed a survey work scope at Formosa 2 offshore wind project located off the coast of Taiwan. MMA reports having carried out several potential unexploded ordnance target investigations as well as 168 km of magnetometer survey line from its support DP2 vessel MMA Prestige. The 376 MW Formosa 2 offshore wind farm is […]
-
Authorities, Business & Finance, Wind Farm Update
Swancor has signed a power purchase agreement (PPA) with Taipower for the Formosa 2 offshore wind farm.
-
Contracts & Tenders, Wind Farm Update
Singapore-based marine and offshore engineering group Sembcorp Marine has landed a contract with Jan De Nul to fabricate 15 jacket foundations for the Formosa 2 offshore wind farm in Taiwan. Located four kilometres offshore Miaoli County in the Taiwan Strait, the 376MW Formosa 2 will be Taiwan’s largest offshore wind farm once commissioned in late […]
-
The onshore construction of the Formosa 2 offshore wind project commenced today, 8 November, with a groundbreaking ceremony held in Taiwan. Formosa 2 will comprise 47 Siemens Gamesa 8.0 – 167 turbines mounted on jacket foundations which will be installed by Seaway 7 some 4km offshore Miaoli County in the Taiwan Strait. The 376MW project is expected […]
-
Jan De Nul has secured the engineering, procurement, construction and installation contract (EPCI) for foundations and subsea cables at the Formosa 2 offshore wind project in Taiwan. Jan De Nul Group is responsible for the design, fabrication and installation of the jacket foundations, as well as for the design, supply and installation of subsea cables […]
-
Contracts & Tenders, Wind Farm Update
Siemens Gamesa has received a firm order for the 376MW Formosa 2 offshore wind farm project in Taiwan from partners Macquarie’s Green Investment Group and Swancor Renewable Energy. The project, located in Miaoli county, will consist of 47 units of the SG 8.0-167 DD offshore wind turbine and construction is expected to begin in 2020. The wind […]