Search results for: formosa 2

222 results

A list of search results

  • 10 December 2020
    Contracts & Tenders, Wind Farm Update

    Siemens Gamesa has awarded FairWind with a contract to assist on pre-assembly work on offshore wind turbines for the Formosa 2 wind farm in Taiwan. FairWind will be responsible for the pre-assembly of the towers for 47 SGRE 8.0 MW wind turbines, scheduled to start in March 2021. “This is an important opportunity for FairWind […]

  • 10 November 2020
    Wind Farm Update

    Haizea Wind has so far sent off 20 out of the total 32 transition piece (TP) barrels for the Taiwanese Formosa 2 offshore wind farm from Spain to Indonesia. On 28 September, the company completed the delivery of the first batch of four TPs to Saipem by shipping them to the Karimun Yard in Indonesia. […]

  • 26 August 2020
    Vessels, Wind Farm Update

    JIFMAR Offshore Services’ shallow draft DP1 workboat JIF Breizh has completed operations at the Formosa 2 offshore wind farm in Taiwan, under a contract with Jan De Nul. The vessel, which was contracted and transported to Taiwan earlier this year, worked on export cable pull-in landfall Horizontal Direction Drilling (HDD) operations for three months. Within […]

  • 17 August 2020
    Contracts & Tenders, Grid Connection

    First Subsea has secured a contract by Jan De Nul to provide the cable protection system for the export and inter-array cables at the Formosa 2 offshore wind project in Taiwan. The order represents First Subsea’s second cable protection system award in Taiwan and follows last year’s cooperation with Jan De Nul at the Formosa 1 […]

  • 22 July 2020
    Ports & Logistics, Wind Farm Update

    The first batch of pin piles for the Formosa 2 jacket foundations have been offloaded at the Port of Taichung and are now waiting for installation, which is about to start soon.  Each of the pin piles – produced by EEW Korea, EEW KHPC and EEW Malaysia – is up to 78.9 metres long, has […]

  • 16 June 2020
    Wind Farm Update

    EEW Group is producing the steel pipe components for the 47 jacket foundations to be installed on the Formosa 2 wind farm offshore Taiwan. The production of the steel pipes for the jackets started in January at EEW Korea, EEW KHPC, and EEW Malaysia and is expected to be completed in October 2020. With a […]

  • 5 June 2020
    Wind Farm Update

    Jan De Nul has kicked off construction works in Taiwan for the 376 MW Formosa 2 offshore wind farm. Nearshore and onshore construction works have started at the landfall site in Miaoli County and Taichung port, Jan De Nul said. Offshore installation works will commence later this year. At the landfall site in Miaoli County, […]

  • 18 May 2020
    Wind Farm Update

    EEW’s manufacturing facilities in Asia have produced half of the total of 188 pin piles for Taiwan’s Formosa 2 offshore wind farm. Formosa 2 will comprise 47 jacket foundations, with each jacket secured to the seabed with four pin piles. Each pin pile is up to 78.9 metres long, has an outside diameter of 2.4 metres, […]

  • 11 May 2020
    Ports & Logistics, Wind Farm Update

    Jan De Nul will set up a logistics and operations hub for the 376 MW Formosa 2 offshore wind farm project in the Port of Taichung, Taiwan. Jan De Nul and a subsidiary of the Taiwan International Port Corporation (TIPC) signed a lease and operating agreement covering a total of around 15 hectares of land. […]

  • 5 March 2020
    Contracts & Tenders

    Specialist Marine Consultants (SMC) has secured a contract to provide marine coordination services for the Formosa 2 offshore wind farm in Taiwan. As for the Formosa 1 Phase 2 project, SMC will work with SeaPlanner and local communications company Mercury Data Systems to deliver a comprehensive marine coordination solution. This will comprise the design, communications […]

  • 28 November 2019
    Contracts & Tenders

    Italian offshore energy contractor Saipem will manufacture and deliver 32 wind turbine jacket foundations for the 376MW Formosa 2 offshore wind farm in Taiwan. As reported earlier, Jan De Nul, the EPCI contractor for the project’s foundations and subsea cables, selected Saipem and Sembcorp to deliver the pile jacket foundations for the wind farm. At […]

  • 8 November 2019
    Wind Farm Update

    The onshore construction of the Formosa 2 offshore wind project commenced today, 8 November, with a groundbreaking ceremony held in Taiwan. Formosa 2 will comprise 47 Siemens Gamesa 8.0 – 167 turbines mounted on jacket foundations which will be installed by Seaway 7 some 4km offshore Miaoli County in the Taiwan Strait. The 376MW project is expected […]

  • 5 November 2019
    Business & Finance

    UK Export Finance (UKEF) has provided an NT$ 9.2 billion (GBP 230 million) project finance guarantee to support the construction of the Formosa 2 offshore wind farm in Taiwan. As a result of the support, UK companies will be involved in the construction of the 376MW wind farm, helping unlock the export potential of the […]

  • 31 October 2019
    Contracts & Tenders, Wind Farm Update

    Jan De Nul has selected the suppliers of the jacket foundations and the accompanying pin piles for the 376MW Formosa 2 offshore wind farm in Taiwan. Jan De Nul is the EPCI contractor for the project’s foundations and subsea cables. Following the project financial close reached earlier this week, Jan De Nul awarded Saipem and Sembcorp […]

  • 31 October 2019
    Wind Farm Update

    Jan de Nul has contracted Seaway 7, the Renewables & Heavy Lifting business unit of Subsea 7, for foundation installation works on the Formosa 2 offshore wind farm in Taiwan. The contract includes transportation, pre-piling and installation of 47 jacket foundations. Seaway 7 will be working at the Taiwanese offshore wind farm site in 2020 and […]

  • 29 October 2019
    Wind Farm Update

    Taiwan’s Formosa 2 offshore wind farm has reached financial close, Macquarie’s Green Investment Group (GIG) said. Formosa 2 has been jointly developed by Macquarie Capital (75%) and Swancor Renewable Energy (25%). GIG will now play a role in delivering the project through its construction phase. The 376MW offshore wind project located off the coast of Miaoli […]

  • 29 October 2019
    Contracts & Tenders, Wind Farm Update

    Siemens Gamesa has received a firm order for the 376MW Formosa 2 offshore wind farm project in Taiwan from partners Macquarie’s Green Investment Group and Swancor Renewable Energy. The project, located in Miaoli county, will consist of 47 units of the SG 8.0-167 DD offshore wind turbine and construction is expected to begin in 2020. The wind […]

  • 9 October 2019
    Business & Finance, Wind Farm Update

    JERA is set to acquire a 49% equity interest in the Formosa 2 offshore wind farm in Taiwan, the Japanese utility revealed shortly after it had secured joint control over the project with Macquarie and Swancor. Macquarie will hold a 26% stake and Swancor will hold 25% of the 376MW wind project located offshore Miaoli County in the Taiwan Strait. The […]

  • 3 October 2019
    Business & Finance

    The European Commission has approved the acquisition of joint control by JERA, Macquarie and Swancor over the Formosa 2 offshore wind project in Taiwan. The 376MW Formosa 2 offshore wind project is currently owned by Macquarie and Swancor. The Commission concluded that the proposed acquisition would raise no competition concerns as Formosa 2 has no activity within the European Economic […]

  • 2 September 2019
    Contracts & Tenders, Wind Farm Update

    Singapore-based marine and offshore engineering group Sembcorp Marine has landed a contract with Jan De Nul to fabricate 15 jacket foundations for the Formosa 2 offshore wind farm in Taiwan. Located four kilometres offshore Miaoli County in the Taiwan Strait, the 376MW Formosa 2  will be Taiwan’s largest offshore wind farm once commissioned in late […]

  • 9 July 2019
    Contracts & Tenders, Vessels

    Seajacks International has conditionally been awarded a contract with Siemens Gamesa for the transport and installation of wind turbines at the Formosa 2 offshore wind farm in Taiwan. The 376MW Formosa 2, developed by Macquarie Capital and Swancor Renewable Energy, will consist of 47 SG 8.0 – 167 offshore wind turbines. Installation is scheduled for […]

  • 12 December 2018
    Authorities, Business & Finance, Wind Farm Update

    Swancor has signed a power purchase agreement (PPA) with Taipower for the Formosa 2 offshore wind farm.

  • 12 November 2019
    Wind Farm Update

    Ørsted and project partners have held an inauguration ceremony for the Formosa 1 Phase 2 offshore wind project in Taiwan. Formosa 1 Phase 2 is an extension of the existing two-turbine Formosa 1 Phase 1 project, which was officially commissioned in April 2017. The 120MW project comprises 20 Siemens Gamesa 6MW turbines installed approximately 2 […]

  • 29 October 2019
    Wind Farm Update

    Jan De Nul has completed the EPCI scope for foundations, power cables, and scour protection on the Formosa 1 (Phase 2) offshore wind farm in Taiwan. Jan De Nul engineered, procured, and installed twenty offshore wind turbine foundations consisting of a monopile and transition piece with a grouted connection. Around the monopile foundations, 56,000 tonnes […]

  • 15 October 2019
    Grid Connection

    Correll Services has completed the subsea and land cable termination and testing works at the Formosa 1 Phase 2 offshore wind farm in Taiwan. Correll Services was in charge of project documentation, export cable (HV & FO) jointing at the TJB and OSS, array cable terminations (HV & FO) on 22 assets, and post-installation testing from […]

  • 9 October 2019
    Wind Farm Update

    All 20 Siemens Gamesa 6MW turbines have been installed at the Formosa 1 Phase 2 offshore wind project in Taiwan. To remind, jack-up vessel Seajacks Zaratan installed the first turbine at the project site 6km off the west coast of the Miaoli district in the Taiwan Strait in July. Prior to commercial operation, each turbine goes through […]