  • 6 June 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Vessels, Wind Farm Update

    NKT, using its vessel NKT Victoria, is scheduled to start installing the export cable for the 1.4 GW East Anglia Three offshore wind farm in the UK this month. The vessel is expected to mobilise from the port of Karlskrona in Sweden on 14 June and work on the East Anglia Three site 24/7, conducting […]

  • 21 April 2025
    Contracts & Tenders, Supply Chain, Vessels

    Iberdrola’s ScottishPower Renewables has signed charter agreements with Caister-based NR Marine Services and Great Yarmouth-based OEG to provide vessels to support the construction of the 1.4 GW East Anglia Three offshore wind farm in the UK. The deals are worth more than GBP 16 million (approximately EUR 18.6 million), and all vessels will operate out […]

  • 17 March 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Seaway7, using the jack-up vessel Seaway Ventus, is scheduled to start installing wind turbine foundations at the East Anglia Three offshore wind farm site at the beginning of April. Seaway Ventus is expected to mobilise at BOW Terminal in the Netherlands on 27 March and commence offshore work within the East Anglia Three array site […]

  • 26 December 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    A pre-installation survey at the East Anglia Three offshore wind farm site is scheduled to begin in early January 2025, following subsea boulder clearance and scour protection work that was carried out in November 2024 and marked the start of offshore construction work. The survey, which will be performed by Seaway7 and Beam using the […]

  • 25 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Offshore construction has started at the East Anglia Three offshore wind farm site in the UK, with the first of 95 monopile foundations now installed by the jack-up vessel Seaway Ventus. Standing at 83.89 metres tall, 10.6 metres in diameter and weighing 1,800 tonnes, the monopile also represents a new offshore wind industry record – […]

  • 17 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted is conducting a confirmed unexploded ordnance (cUXO) removal campaign along the export cable route of the Hornsea Three offshore wind project in the UK and a potential UXO (pUXO) inspection campaign in the array area. As of 14 April, 24 confirmed UXOs within the Hornsea Three export cable route were removed, with the explosive […]

  • 12 December 2024
    Business & Finance, Foundations, Supply Chain

    Haizea Wind Group has become the sixth member of the Offshore Wind Foundations Alliance (OWFA), established by Bladt Industries, EEW Special Pipe Constructions, Sif Netherlands, Smulders Projects Belgium, and Steelwind Nordenham in 2021. In 2021, the five founding members said OWFA was formed with an aim to raise awareness about the key role offshore wind […]

  • 4 December 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Project Updates, Supply Chain, Wind Farm Update

    ScottishPower Renewables, part of the Iberdrola Group, has awarded an export cable contract for East Anglia Two (EA2), a 960 MW offshore wind farm in the UK, to Nexans. Under the contract, Nexans will supply and install approximately 100 kilometres of 275 kV high-voltage subsea export cables and 55 kilometres of onshore cables, which the […]

  • 16 January 2025
    Business & Finance, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    RWE has given the consortium of Aker Solutions and Siemens Energy the full notice to proceed on the offshore and onshore substations for the Norfolk Vanguard West and East offshore wind projects in the UK. Aker Solutions has provided work for the projects under a limited notice to proceed announced in November 2023, the company […]

  • 12 November 2024
    Business & Finance, Fixed-Bottom, Supply Chain, Wind Turbines

    ScottishPower has awarded Siemens Gamesa a turbine contract worth more than GBP 1 billion for its 960 MW East Anglia Two offshore wind farm in the UK. Under the contract, Siemens Gamesa will supply 64 of its flagship SG 14-236 DD wind turbines, which have a rotor diameter of 236 metres, for ScottishPower’s third offshore […]

  • 6 November 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Seaway7, part of the Subsea7 Group, has been awarded a contract by ScottishPower Renewables for the transport and installation of the inter-array cables for the 960 MW East Anglia Two offshore wind project in the UK. The deal is worth between USD 150 million and USD 300 million, as per Subsea7’s definition of a substantial contract. […]

  • 31 October 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Foundations, Manufacturing, Supply Chain

    ScottishPower Renewables has awarded Sif and Smulders a contract to supply 64 monopile foundation and transition pieces (TPs) for the 960 MW East Anglia Two offshore wind farm in the UK. ScottishPower Renewables, Iberdrola’s UK arm, signed the contracts with Sif Netherlands for supplying 64 monopiles and with a joint venture between Sif and Smulders […]

  • 29 November 2024
    Fixed-Bottom, Foundations, Manufacturing, Supply Chain

    The first of 54 monopiles for Equinor’s Empire Wind 1 offshore wind farm in the US has been manufactured at Sif’s Maasvlakte 2 site in Rotterdam, the Netherlands. On 28 November, the first monopile for Empire Wind was completed on the new production line of the expanded production facilities at Maasvlakte 2 Rotterdam. In February […]

  • 4 October 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Haizea Wind Group has manufactured the first monopile foundation for Iberdrola’s East Anglia Three offshore wind project at its facility in Bilbao, Spain. Haizea Bilbao will deliver 50 monopiles for the 1.4 GW East Anglia Three offshore wind farm under a contract with ScottishPower Renewables, Iberdrola’s UK arm, signed in March 2023. Under the contract, […]

  • 24 September 2024
    Business & Finance, Business development, Foundations, Industry, Infrastructure, Jobs & Recruitment, Outlook & Strategy, Supply Chain

    Windar Renovables has started preparatory work to construct a new monopile factory in Asturias, Spain. Windar Renovables acquired the construction site on the right bank of the Avilés estuary last March. This land, with a surface area of more than 400,000 square metres, includes several manufacturing warehouses with direct access to the Port of Avilés, […]

  • 3 September 2024
    Authorities, Planning & Permitting

    Offshore wind developers have been awarded contracts for approximately 5.3 GW of capacity in the UK’s latest Contract for Difference (CfD) Allocation Round 6 (AR6). Ørsted received the largest CfD for offshore wind, securing 2.4 GW for the Hornsea 4 offshore wind project. The offshore wind farms awarded CfDs are the 288 MW Inch Cape […]

  • 3 September 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Foundations, Supply Chain

    Sif is in exclusive negotiations for a 140-kilotonne monopile foundation project for an offshore wind farm that was awarded a Contract for Difference (CfD) in the UK’s Allocation Round 6 (AR6), the Dutch company informed following the announcement of the AR6 results. “It is expected that a final contract will be reached before the end […]

  • 26 September 2024
    Contracts & Tenders, Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    RWE has awarded two contracts to Lamprell Energy Limited for the future supply of transition pieces to its two east coast UK offshore wind projects currently under development, Norfolk Vanguard West and Norfolk Vanguard East. RWE and Lamprell marked the signing of the contract with a small event at the WindEnergy Hamburg 2024 conference. The […]

  • 6 August 2024
    Business & Finance, Jobs & Recruitment

    An industrial action of Siemens Gamesa’s employees in the company’s Hull offshore wind blade factory has been called off as the UK union Unite secured a pay rise worth 8.4 per cent. On 12 July, Unite said around 300 Siemens Gamesa wind turbine workers in Hull were being balloted for strike action over pay. “The […]

  • 27 June 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Navantia Seanergies has manufactured the first monopile foundation for Iberdrola’s UK offshore wind project East Anglia Three at Navantia-Windar’s monopile factory in Fene shipyard, in A Coruña, Spain. The Navantia-Windar consortium will deliver 45 monopiles for the 1.4 GW East Anglia Three offshore wind farm under a contract with ScottishPower Renewables, Iberdrola’s UK arm, signed […]

  • 1 August 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Windar Renovables has manufactured and loaded the final batch of transition pieces (TPs) for the 806 MW Vineyard Wind 1 offshore wind farm in the United States. In 2019, Windar Renovables won a contract to manufacture, certify, assemble, inspect, store, and deliver TPs for the offshore wind project, being developed by Vineyard Wind, a joint […]

  • 25 May 2016
    Authorities, Wind Farm Update

    A preliminary meeting of a panel forming the Examining Authority (ExA) for East Anglia Three’s Development Consent Order (DCO) application will be held on 28 June, to discuss the examination procedure. On 29 June, an Issue Specific Hearing will be held, relating to the definition of the project and draft Development Consent Order (DCO) matters. The application was […]

  • 11 January 2024
    Fixed-Bottom, Manufacturing, Supply Chain

    Spain-based Windar Renovables has transferred the first transition piece (TP) for the 1.4 GW East Anglia Three offshore wind project from its offshore facility to the Port of Avilés for completion. Under the contract signed with Iberdrola in May 2023, Windar Renovables is responsible for constructing 95 transition pieces for the East Anglia Three offshore […]

  • 2 July 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Hughes Subsea, a subsidiary of OEG Renewables, will start disposing of unexploded ordnance (UXO) at the UK 1.4 GW East Anglia Three (EA3) offshore wind farm site on 4 July, according to the latest Notice to Mariners issued by the EA3 project team. The UXO identification, investigation and clearance campaign started in March this year […]

  • 12 August 2022
    Grid Connection, Wind Farm Update

    ScottishPower Renewables has started onshore construction for its 1,400 MW East Anglia Three offshore wind farm in the UK. The initial focus of the East Anglia Three construction programme will be on the onshore converter station at Bramford in Suffolk – in partnership with Siemens Energy and Aker Solutions – and along the cable route, […]

  • 20 March 2024
    Business & Finance, Business development, Contracts & Tenders, Research & Development, Supply Chain

    OEG Renewables subsidiary, Hughes Subsea, has been awarded a contract to carry out an unexploded ordnance (UXO) identification and clearance campaign on the 1.4 GW East Anglia Three offshore wind farm site in the UK. The campaign is expected to last six months, commencing in mid-March and continuing until early October, utilising the 66.4-metre-long DP2 […]