108 results found for 'Vesterhav Nord'

108 results found for 'Vesterhav Nord'
Order results by

A list of search results

  • 20 February 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Vesterhav Nord (North) offshore wind farm, owned by Vattenfall, started producing power on 16 February, joining its sister park Vesterhav Syd, which began generating electricity in January 2024. Vesterhav Nord is part of Vattenfall’s 344 MW Vesterhav duo, whose 168 MW Vesterhav Syd (South) has been feeding power into the Danish grid since January. The […]

  • 12 March 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 21 wind turbines at Vattenfall’s Vesterhav Nord (North) offshore wind farm have delivered the first power and the 176 MW project is now connected to the Danish electricity grid. However, the blades on a single unit have been temporarily taken down for repairs after sustaining damage during the preparation of the offshore wind farm. […]

  • 13 March 2024
    Business & Finance, Fixed-Bottom, Industry, Project Updates, Wind Farm Update

    Thailand-based multinational conglomerate B. Grimm Power (BGRIM) has decided to expand its renewable energy business through investments in Nakwol Wind and Hanbit Wind, two offshore wind projects in South Korea that have a combined installed capacity of 740 MW. According to the CEO of BGRIM, Harald Link, B. Grimm Power Korea, a wholly-owned subsidiary of […]

  • 9 January 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Vattenfall has commissioned all wind turbines at the offshore wind farm Vesterhav Syd in Denmark, which is now fully operational and feeding power into the Danish grid. Vesterhav Syd (South) is part of Vattenfall’s 344 MW Vesterhav duo, whose Vesterhav Nord (North) wind farm the company expects to connect to the grid during the first […]

  • 13 November 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 170 MW Vesterhav Syd offshore wind farm, developed by Vattenfall in Denmark, has delivered its first green power. The installation of 20 8.4 Siemens Gamesa wind turbines took place from July to September this year, and Vattenfall’s initial plan was to connect the turbines to the grid immediately after the installation. However, the plan […]

  • 19 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 21st and final wind turbine was installed at the Vesterhav Nord wind farm in the Danish North Sea on Wednesday, 18 October, Vattenfall, the owner and developer of the project, said. The milestone completes the wind turbine installation scope at the Vesterhavn Nord, and the 20-turbine Vesterhavn Syd wind farm. Vattenfall expects to be […]

  • 8 February 2019
    Authorities, Business & Finance, Wind Farm Update

    The Danish Energy Agency has initiated a new environmental impact assessment (EIA) process for Vattenfall’s Vesterhav Syd offshore wind farm due to a cancelation of a part of its license for the project construction. According to the Danish Energy Agency, the Energy Board of Appeal canceled the part of the license after completing the processing of […]

  • 2 November 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    Mainprize Offshore has won a contract for the provision of crew transfer vessels (CTVs) during the construction phase of the Vesterhav Nord and Syd offshore wind farms in the Danish North Sea. Under the contract, awarded following a tendering procedure, the UK-based company will be providing a 24-pax crew transfer vessel from March until November […]

  • 13 September 2017
    Contracts & Tenders, Vessels

    Vattenfall has invited tenders for the provision of wind turbine installation vessels that will work on Kriegers Flak and the two nearshore projects, Vesterhav Nord and Vesterhav Syd.

  • 25 September 2017
    Contracts & Tenders, Wind Farm Update

    Vattenfall has invited tenders for the installation of foundations for three projects in Denmark: Danish Kriegers Flak in the Baltic Sea, and Vesterhav Nord and Vesterhav Syd in the North Sea.

  • 8 May 2015
    Authorities, Environment

    The Environmental Impact Assessments (EIAs) for Vesterhav Syd and Vesterhav Nord are now published, and will be out for public consultation until 30 June, 2015. Energinet.dk is preparing EIAs for all the six nearshore wind farm sites. Up until now EIAs for Bornholm, Vesterhav Syd and Vesterhav Nord have been published while EIAs for Sejerø […]

  • 12 November 2018
    Environment

    Vattenfall and the Danish Armed Forces have uncovered and detonated two English mines in the area of the Danish North Sea where the Vesterhav Nord offshore wind farm is being built.

  • 10 July 2020
    Contracts & Tenders

    EDS HV has secured two contracts with Vattenfall to provide high voltage network commissioning and safety management at the Kriegers Flak, Vesterhav Syd and Vesterhav Nord offshore wind projects in Denmark. In addition to the commissioning scope, EDS HV will be offering full high-voltage safety management. The company is also providing full management of all […]

  • 12 July 2018
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Vattenfall has awarded Per Aarsleff A/S with a contract to supply and install the onshore grid for the Vesterhav Nord and Vesterhav Syd nearshore wind projects in the Danish North Sea.

  • 22 May 2018
    Operations & Maintenance

    Vattenfall will begin investigating the seafloor of the Vesterhav Syd and Vesterhav Nord offshore wind project in the Danish North Sea and Kriegers Flak in the Baltic Sea in late summer, with an aim of finding old mines or bombs.

  • 29 August 2017
    Wind Farm Update

    Danish engineering consultancy LICengineering has won a contract to provide Vattenfall with design solutions for the Kriegers Flak offshore wind farm and the Vesterhav Nord and Vesterhav Syd nearshore wind farms in the Danish North Sea.

  • 14 April 2021
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Vattenfall has once again selected Denmark’s Port of Hvide Sande as an Operations & Maintenance base, this time for the Vesterhav Syd and the Vesterhav Nord offshore wind farms. Back in 2019, Vattenfall chose the Port of Hvide Sande as the O&M base for the 406.7 MW Horns Rev 3 offshore wind farm. Vattenfall plans […]

  • 29 March 2019
    Wind Farm Update

    Vattenfall has delayed the construction of the Vesterhav Syd and Vesterhav Nord offshore wind projects in Denmark by three years. According to turbine supplier Siemens Gamesa, the beginning of installation has been postponed to 2023, instead of 2020 as originally agreed. The Danish Energy Agency recently initiated new environmental impact assessment (EIA) processes for both Vesterhav Syd […]

  • 17 December 2021
    Contracts & Tenders, Wind Farm Update

    Vattenfall has chosen DEME Offshore to transport and install the monopile foundations at the Vesterhav Syd and Vesterhav Nord wind farms in the Danish North Sea. The Vesterhav offshore wind farms are located 10 kilometres off the West coast of Jutland near Thyborøn (Nord) and Søndervig (Syd) in water depths of approximately 20 metres. The […]

  • 14 December 2020
    Authorities, Business & Finance, Wind Farm Update

    The Danish Energy Agency (DEA) has granted permission for Vattenfall’s Vesterhav Nord and Vesterhav Syd offshore wind projects. The decisions come after the assessment of the supplementary environmental impact assessments (EIAs) for the two wind farms. The go-ahead allows Vattenfall to start the projects once the appeal period expires on 11 January 2021. Located nine […]

  • 22 December 2016
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    Vattenfall and the Danish minister for Energy, Utilities and Climate, Lars Chr. Lilleholt, have signed the concession agreements for the offshore wind farm Kriegers Flak and the near shore wind farms Vesterhav Nord and Vesterhav Syd. The signatures became possible after the Danish Parliament on 19 December unanimously adopted the legislation that determines the subsidies […]

  • 15 February 2023
    Contracts & Tenders, Infrastructure, Ports & Logistics

    DEME Group and the Port of Thyboron have signed a contract regarding the installation of foundations for Vattenfall’s Vesterhav Nord and Syd offshore wind farms in the Danish North Sea. The foundations that DEME will be installing include 41 monopiles and transition pieces (TPs). The 77-metre-long monopiles, each weighing around 622 tonnes will be produced […]

  • 13 September 2018
    Vessels, Wind Farm Update

    Vattenfall is preparing to deploy two vessels in search of naval mines and shipwrecks in the area of the Danish North Sea where the Vesterhav Syd and Vesterhav Nord offshore wind farms will be built.

  • 21 August 2017
    R&D, Vessels, Wind Farm Update

    Danish engineering consultancy Geo has started the final phase of the geophysical and geotechnical investigations on Vattenfall’s Vesterhav Nord and Vesterhav Syd nearshore wind farm zones off Denmark.

  • 22 September 2017
    Contracts & Tenders

    Vattenfall has invited foundation manufacturers to pre-qualify to be able to participate in the tender for the delivery of monopile foundations for three projects in Denmark: Kriegers Flak and Vesterhav Nord and Vesterhav Syd nearshore wind farms.

  • 25 April 2023
    Wind Farm Update

    Bladt Industries has sent off the last transition piece (TP) for the Vesterhav Nord offshore wind farm from its facility in Aalborg, Denmark. The company has thus delivered all TPs for Vattenfall’s Vesterhav Nord & Syd offshore wind project, 21 for Vesterhav Nord and 20 for Vesterhav Syd. Vattenfall awarded Bladt Industries a contract for […]