Search results for: Triton Knoll

270 results

A list of search results

  • 31 May 2022
    Contracts & Tenders, Wind Farm Update

    Vestas has selected Global Wind Service (GWS) to provide wind turbine pre-assembly services for the 27-turbine Arcadis Ost 1 offshore wind farm in Germany. The pre-assembly works will start soon at Rønne Havn on the Danish Bornholm Island in the Baltic Sea. In June last year, Parkwind ordered 27 Vestas V174-9.5 units which will be […]

  • 21 April 2022
    Business & Finance, Wind Farm Update

    New offshore wind capacity additions in Europe are poised to hit a record high of 4.2 GW this year, topping 4 GW for the first time and more than doubling additions seen in 2021, Rystad Energy research shows. The continent’s capacity additions in 2022 will top the previous annual record of 3.8 GW set in […]

  • 13 January 2022
    Wind Farm Update

    All 90 Vestas 9.5 MW wind turbines have been commissioned at the 857 MW Triton Knoll wind farm offshore Lincolnshire, UK, RWE said. The wind farm, constructed by RWE on behalf the project partners, has reached this milestone on time, overcoming the challenges posed by the global pandemic, the developer said. Standing at 164 metres […]

  • 30 November 2021
    Business & Finance, Wind Farm Update

    RWE has signed a fifteen-year power purchase agreement (PPA) with EDF who will purchase the renewable electricity from the 1.4 GW Sofia offshore wind farm which is set for full generation in 2026. In what represents RWE and EDF’s largest renewable energy agreement to date, EDF will offtake all the wind energy that Sofia will […]

  • 10 November 2021
    Contracts & Tenders, Grid Connection

    A consortium of the London-based Equitix Limited and Japan’s TEPCO Power Grid has been selected as the preferred bidder for the offshore electricity transmission link connecting the 857 MW Triton Knoll wind farm to the UK grid. Valued at approximately GBP 577 million (EUR 675 million), the new offshore electricity transmission asset is comprised of […]

  • 28 October 2021
    Contracts & Tenders

    RWE Renewables has awarded RINA with a contract for Cable Verification Services & OCP (Offshore Converter Platform) construction site quality assurance services for the 1.4 GW Sofia offshore wind farm in the UK. The offshore wind farm’s 220-kilometre export cable route will house ±320 kV high-voltage direct current (HVDC) subsea export cables, running from the […]

  • 8 October 2021
    Grid Connection, Wind Farm Update

    RWE has completed all the major onshore electrical system construction works for the 857 MW Triton Knoll offshore wind farm project in Lincolnshire, the UK. The works, which commenced in September 2018, involved laying 57 kilometres of 220 kV underground cable from the project’s landfall location near Anderby Creek to the newly constructed Triton Knoll […]

  • 17 September 2021
    Wind Farm Update

    The 90th and final wind turbine has been installed at the Triton Knoll offshore wind farm site, located 32 kilometres off the coast of Lincolnshire in the UK. Wind turbine installation works commenced in January 2021 after Cadeler’s wind farm installation vessel Wind Osprey arrived at the site loaded with the first sets of Vestas […]

  • 23 September 2021
    Operations & Maintenance, Vessels

    Esvagt has taken delivery of the third and final service operation vessel (SOV) ordered for Vestas and delivered by Havyard in Norway. Esvagt NHST 149, as the yet-to-be-named vessel is known, completes a series of three vessels delivered over the last nine months that Esvagt had ordered at Havyard Lervik to service Vestas on several […]

  • 23 September 2021
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Energy company RWE is to make a strategic commitment to the UK’s east coast with the creation of an operations hub for offshore wind farms at Grimsby’s Royal Dock. The new ‘Grimsby Hub’ facility will expand the existing Triton Knoll offshore wind farm base and will be the home for RWE’s specialist team for major […]

  • 6 January 2014
    Wind Farm Update

    RWE Innogy has revised plans for the proposed Triton Knoll Offshore Wind Farm project, which is being developed off the Lincolnshire Coast in the North Sea. Work on the site design has resulted in RWE Innogy deciding to progress the development with a reduced capacity which ranges between 600 and 900 megawatts, rather than the […]

  • 8 October 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Nexans has been awarded a contract worth over EUR 35 million by Triton Knoll’s onshore cable installation lead contractor J Murphy & Sons Ltd to supply the land export cable and accessories in order to connect the Triton Knoll wind farm to the UK grid.

  • 24 March 2017
    Environment, Grid Connection, Wind Farm Update

    Lincolnshire design consultancy Land Drainage Services Ltd (LDS) has been awarded a contract extension by Triton Knoll Offshore Wind Farm to provide a long-term liaison service between the project and its local landowners.

  • 31 October 2016
    Environment, Grid Connection, R&D, Wind Farm Update

    Triton Knoll is set to start survey works on the dunes and beach at Mogg’s Eye, Anderby, Lincolnshire, as the 900MW offshore wind project moves into the design phase after consent was granted for its Electrical System in September. Up to three days of survey works are scheduled to begin on Wednesday, 3 November, using […]

  • 17 October 2019
    Contracts & Tenders

    Partrac has secured a contract to supply, install and maintain navigation and metocean equipment at the Triton Knoll offshore wind project in the UK. The UK-based company will supply and install 12 buoys to demarcate the offshore construction site and act as navigation aids to mariners. It will also supply, install and maintain two metocean buoys that […]

  • 9 January 2020
    Wind Farm Update

    Seaway 7’s installation vessel Seaway Strashnov has arrived at the Triton Knoll offshore wind project site with the first turbine foundations. According to innogy, the vessel will begin installing the foundations as soon as weather conditions are favorable. Triton Knoll will comprise 90 MHI Vestas 9.5MW turbines mounted on monopile foundations some 32km off the Lincolnshire […]

  • 2 October 2017
    Business & Finance, Grid Connection, Wind Farm Update

    Triton Knoll Offshore Wind Farm has selected Siemens Transmission and Distribution as the preferred supplier to engineer, procure, and construct both the onshore and offshore substations.

  • 22 August 2019
    Contracts & Tenders, Wind Farm Update

    Seacat Services has won a contract to provide two offshore energy support vessels (OESVs) for the construction phase of the Triton Knoll offshore wind farm in the UK. The two OESVs will provide crew transfer and logistical support at the 857MW project and will be operating out of the new construction and operation base in the Port […]

  • 23 February 2015

    People in Lincolnshire living close to the proposed onshore infrastructure of the Triton Knoll Offshore Wind Farm have just a few days left to take part in a consultation on a major new community investment fund for their area. The consultation, to understand local priorities for the funding, the sorts of initiatives which could be supported […]

  • 18 September 2017
    Business & Finance, Wind Farm Update

    Triton Knoll has selected MHI Vestas Offshore Wind as its preferred turbine supplier and its plans to use 90 of its 9.5 MW turbines to generate power on the 860MW wind farm off Lincolnshire, England.

  • 19 September 2018
    Contracts & Tenders, Wind Farm Update

    UK-based marine consultancy Waves Group has been selected as Marine Warranty Surveyors for the Triton Knoll offshore wind farm development.

  • 8 August 2018
    Authorities, Grid Connection, Wind Farm Update

    UK’s Department for Business, Energy and Industrial Strategy (BEIS) has approved the changes proposed by Triton Knoll Offshore Wind Farm Limited for the Triton Knoll wind project offshore Lincolnshire.

  • 6 September 2016
    Grid Connection, Wind Farm Update

    The UK Secretary of State for Business, Energy and Industrial Strategy, Greg Clark, granted consent for Triton Knoll offshore wind farm’s electrical infrastructure today.  Triton Knoll Offshore Wind Farm, a project company comprising RWE and Statkraft, submitted an application for a Development Consent Order (DCO) for the Triton Knoll Electrical System in April 2015. As […]

  • 3 September 2018
    Business & Finance, Jobs & Recruitment, Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Triton Knoll has agreed a Memorandum of Understanding (MoU) with Associated British Ports (ABP) to use its Grimsby facility as the Triton Knoll wind farm’s long-term Operations and Maintenance (O&M) base.

  • 11 March 2021
    Contracts & Tenders, Grid Connection

    EDS HV, part of James Fisher and Sons, has secured a cable termination and testing contract for the Triton Knoll offshore wind project in the UK. The scope includes the installation and termination of high voltage cables between the foundations and the turbine switchgear, with pre-testing, mock-up trials and cable preparation already been undertaken in late […]

  • 12 July 2013

    ABP Marine Environmental Research ltd. (ABPmer) welcomes the announcement that planning consent has been granted by the Secretary of State, Edward Davey, for the construction of the offshore wind farm at Triton Knoll, off the Lincolnshire and Norfolk coast. Triton Knoll Offshore Wind Farm Limited has been granted permission to construct a 1,200MW wind farm […]