279 results found for 'Triton Knoll'

279 results found for 'Triton Knoll'
Order results by

A list of search results

  • 14 March 2024
    Business & Finance, Fixed-Bottom

    RWE has reported an adjusted EBITDA of nearly EUR 1.7 billion in its offshore wind segment for 2023, compared to EUR 1.4 billion for the previous fiscal year. The increase in earnings is due to the commissioning of new capacity and better wind conditions, according to the company. Electricity generation from renewable energy at RWE rose by […]

  • 15 December 2023
    Business & Finance, Contracts & Tenders, Supply Chain

    UK-headquartered James Fisher and Sons (James Fisher) has secured a multi-million-pound contract at the Triton Knoll offshore transmission (OFTO) project in Lincolnshire, with the offshore platform located 20 miles off the coast in the North Sea. Under the contract, James Fisher will provide complete end-to-end operations and maintenance (O&M) services to support informed decision-making for […]

  • 6 December 2023
    Business & Finance, Grid Connection, Project Updates

    Equitix and Tokyo-based TEPCO Power Grid (TEPCO PG) have reached financial close on the approx. GBP 600 million Triton Knoll Offshore Electricity Transmission (OFTO) project. The Triton Knoll OFTO Transmission Assets include two offshore substations, two 220 kV subsea export cable circuits (approximately 50km in length), which connect to two onshore cable circuits (of approximately […]

  • 17 October 2019
    Contracts & Tenders

    Partrac has secured a contract to supply, install and maintain navigation and metocean equipment at the Triton Knoll offshore wind project in the UK. The UK-based company will supply and install 12 buoys to demarcate the offshore construction site and act as navigation aids to mariners. It will also supply, install and maintain two metocean buoys that […]

  • 24 March 2017
    Environment, Grid Connection, Wind Farm Update

    Lincolnshire design consultancy Land Drainage Services Ltd (LDS) has been awarded a contract extension by Triton Knoll Offshore Wind Farm to provide a long-term liaison service between the project and its local landowners.

  • 6 January 2014
    Wind Farm Update

    RWE Innogy has revised plans for the proposed Triton Knoll Offshore Wind Farm project, which is being developed off the Lincolnshire Coast in the North Sea. Work on the site design has resulted in RWE Innogy deciding to progress the development with a reduced capacity which ranges between 600 and 900 megawatts, rather than the […]

  • 8 October 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Nexans has been awarded a contract worth over EUR 35 million by Triton Knoll’s onshore cable installation lead contractor J Murphy & Sons Ltd to supply the land export cable and accessories in order to connect the Triton Knoll wind farm to the UK grid.

  • 31 October 2016
    Environment, Grid Connection, R&D, Wind Farm Update

    Triton Knoll is set to start survey works on the dunes and beach at Mogg’s Eye, Anderby, Lincolnshire, as the 900MW offshore wind project moves into the design phase after consent was granted for its Electrical System in September. Up to three days of survey works are scheduled to begin on Wednesday, 3 November, using […]

  • 23 February 2015

    People in Lincolnshire living close to the proposed onshore infrastructure of the Triton Knoll Offshore Wind Farm have just a few days left to take part in a consultation on a major new community investment fund for their area. The consultation, to understand local priorities for the funding, the sorts of initiatives which could be supported […]

  • 22 August 2019
    Contracts & Tenders, Wind Farm Update

    Seacat Services has won a contract to provide two offshore energy support vessels (OESVs) for the construction phase of the Triton Knoll offshore wind farm in the UK. The two OESVs will provide crew transfer and logistical support at the 857MW project and will be operating out of the new construction and operation base in the Port […]

  • 19 September 2018
    Contracts & Tenders, Wind Farm Update

    UK-based marine consultancy Waves Group has been selected as Marine Warranty Surveyors for the Triton Knoll offshore wind farm development.

  • 3 September 2018
    Business & Finance, Jobs & Recruitment, Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Triton Knoll has agreed a Memorandum of Understanding (MoU) with Associated British Ports (ABP) to use its Grimsby facility as the Triton Knoll wind farm’s long-term Operations and Maintenance (O&M) base.

  • 8 August 2018
    Authorities, Grid Connection, Wind Farm Update

    UK’s Department for Business, Energy and Industrial Strategy (BEIS) has approved the changes proposed by Triton Knoll Offshore Wind Farm Limited for the Triton Knoll wind project offshore Lincolnshire.

  • 6 September 2016
    Grid Connection, Wind Farm Update

    The UK Secretary of State for Business, Energy and Industrial Strategy, Greg Clark, granted consent for Triton Knoll offshore wind farm’s electrical infrastructure today.  Triton Knoll Offshore Wind Farm, a project company comprising RWE and Statkraft, submitted an application for a Development Consent Order (DCO) for the Triton Knoll Electrical System in April 2015. As […]

  • 18 September 2017
    Business & Finance, Wind Farm Update

    Triton Knoll has selected MHI Vestas Offshore Wind as its preferred turbine supplier and its plans to use 90 of its 9.5 MW turbines to generate power on the 860MW wind farm off Lincolnshire, England.

  • 27 November 2019
    Ports & Logistics

    The Triton Knoll Offshore Construction Services (OCS) team has moved into their new facilities at Grimsby’s Royal Dock, establishing an HQ for offshore construction next year. The OCS base will manage offshore technicians, crews, and specialist vessels, including service operations vessels and crew transfer vessels which are together helping build the 857MW Triton Knoll offshore […]

  • 20 November 2014
    Authorities, Grid Connection, Wind Farm Update

    Monday, December 22, 2014, has been set as a due date for submitting a response to the consultation on Triton Knoll Offshore Wind Farm Electrical System.  However, this extension of the consultation period applies only to online questionnaire responses, as the deadline for the postal and Section 42 responses expired yesterday, November 19, as scheduled, the Skegness Standard news site writes. […]

  • 11 March 2021
    Contracts & Tenders, Grid Connection

    EDS HV, part of James Fisher and Sons, has secured a cable termination and testing contract for the Triton Knoll offshore wind project in the UK. The scope includes the installation and termination of high voltage cables between the foundations and the turbine switchgear, with pre-testing, mock-up trials and cable preparation already been undertaken in late […]

  • 12 July 2013

    ABP Marine Environmental Research ltd. (ABPmer) welcomes the announcement that planning consent has been granted by the Secretary of State, Edward Davey, for the construction of the offshore wind farm at Triton Knoll, off the Lincolnshire and Norfolk coast. Triton Knoll Offshore Wind Farm Limited has been granted permission to construct a 1,200MW wind farm […]

  • 18 July 2019
    Operations & Maintenance, Wind Farm Update

    Work to construct a new offshore construction and operations base for Triton Knoll has officially started at Grimsby’s Royal Dock as UK based contractor Tolent gets started on site. Having been awarded the contract last month, Tolent has now begun work to construct control room, office and warehouse facilities that will become the new operations […]

  • 13 January 2022
    Wind Farm Update

    All 90 Vestas 9.5 MW wind turbines have been commissioned at the 857 MW Triton Knoll wind farm offshore Lincolnshire, UK, RWE said. The wind farm, constructed by RWE on behalf the project partners, has reached this milestone on time, overcoming the challenges posed by the global pandemic, the developer said. Standing at 164 metres […]

  • 9 January 2020
    Wind Farm Update

    Seaway 7’s installation vessel Seaway Strashnov has arrived at the Triton Knoll offshore wind project site with the first turbine foundations. According to innogy, the vessel will begin installing the foundations as soon as weather conditions are favorable. Triton Knoll will comprise 90 MHI Vestas 9.5MW turbines mounted on monopile foundations some 32km off the Lincolnshire […]

  • 12 December 2017
    Wind Farm Update

    Fugro is set to start seabed and sub-seafloor investigations at the Triton Knoll site in the UK. Under a GBP 3 million contract, Fugro will operate three vessels out of the Humber, supported by technical teams from the company’s Wallingford headquarters.

  • 7 November 2017
    Contracts & Tenders, Technology, Wind Farm Update

    The Triton Knoll team, which won the UK’s Contract for Difference (CfD) for its 855MW offshore wind farm in September, plans to continue using Shoreline’s installation and O&M simulation tools as the project moves forward and into construction.

  • 7 March 2018
    Business & Finance, Jobs & Recruitment, Wind Farm Update

    Lincolnshire businesses have been given an insight into opportunities with Triton Knoll Offshore Wind Farm and its contractors, thanks to the project’s first ‘Meet The Buyer’ event.

  • 26 September 2019
    Grid Connection, Wind Farm Update

    Triton Knoll has given an update on the construction of the two offshore substations destined for the 860MW offshore wind project. According to Triton Knoll, a transition piece for the offshore substation has left the construction hall at Smulders’ Wallsend facility in the UK. The company has now commenced the offshore substation foundation work. Additionally, the […]