  • 28 June 2017
    Wind Farm Update

    The rotor for the 27th wind turbine was successfully installed last week at the Nordsee One construction site, marking the halfway point for turbine installation at the 332 MW wind farm.

  • 16 December 2015
    Wind Farm Update

    The first monopile foundation was installed at the Nordsee One offshore wind farm site on December 15 – ahead of schedule. GeoSea, which has been contracted to install the monopiles produced by Ambau, will continue the work through the remainder of 2015 and into 2016. The monopiles are being installed in water depths ranging between 25 and 29 meters. The 332MW Nordsee […]

  • 25 December 2017
    Business & Finance, Wind Farm Update

    Nordsee One GmbH, the owner and developer of the 332MW Nordsee One offshore wind farm, has closed the restructuring of its term loan facility, significantly improving pricing conditions, according to Green Giraffe.

  • 16 June 2015
    Vessels

    Nordsee One GmbH has invited tenders for the provision of guard vessel services, which include monitoring and safeguarding of its offshore wind farm construction area.  The services are to be provided continuously over the entire installation phase on a 24/7 basis. The vessel will observe the surrounding, but not project-related traffic, evaluate if any risk of collision […]

  • 7 March 2017
    Vessels, Wind Farm Update

    MPI Offshore’s wind turbine installation vessel MPI Enterprise has installed the first Senvion 6.2M-126 turbine at the 332MW Nordsee One offshore wind farm in the German North Sea.

  • 31 March 2017
    Grid Connection, Operations & Maintenance, Wind Farm Update

    The 332MW Nordsee One offshore wind farm has started delivering power to the German grid, Nordsee One GmbH, the owner and developer of the project, reports.

  • 16 November 2015
    Technology

    The SeaPlanner software has been selected as a marine coordination and management tool for the Nordsee One offshore wind farm. Nordsee One is the first project to utilize the recent upgrades to the SeaPlanner software, which includes a new mapping platform featuring an enhanced vessel guard zone alerting and analysis tool. This feature was developed to address the […]

  • 18 April 2016
    Vessels, Wind Farm Update

    Over the last weekend, Belgium’s GeoSea installed the final foundation at the 332MW Nordsee One offshore wind farm located approximately 40 kilometres north of the island of Juist in the German part of the North Sea. All 54 monopile foundations were also fitted with the associated transition pieces for the installation of the tower segments. This fully completes […]

  • 21 September 2016
    Business & Finance, Operations & Maintenance, Vessels, Wind Farm Update

    Nordsee One GmbH officially inaugurated a new operation and maintenance base for the 332MW Nordsee One offshore wind farm in Norddeich, Lower-Saxony, Germany, on Wednesday, 21 September. Nordsee One, which is currently being built approximately 40km north of the island of Juist, will be operated and serviced from the venue, which comprises offices, a control room, […]

  • 17 May 2017
    Wind Farm Update

    Twenty of the total 54 wind turbines have been installed at the Nordsee One offshore wind farm.

  • 6 November 2015
    Vessels

    EMS Maritime Offshore GmbH (EMO) has won a deal for a 332MW Nordsee One wind farm, located 32 kilometres north of the Island of Juist. The German company will be in charge of monitoring and safeguarding the wind farm construction area of 41.3 km² between the traffic separation area Terschelling-German Bight and German Bight western […]

  • 22 September 2017
    Wind Farm Update

    The 54th and final turbine was installed at the Nordsee One construction site today, 22 September. The 332MW offshore wind farm is scheduled to begin commercial operations by the end of this year.

  • 25 March 2015

    AMBAU GmbH has secured an order for the design and production of 54 monopiles and transition pieces for „Nordsee One“-project. Starting in June 2015, 54 monopiles and transition pieces for the “Nordsee One”-project will be produced in the AMBAU facilities in Bremen and Cuxhaven on behalf of Nordsee One GmbH. These 54 foundations consist of […]

  • 11 May 2017
    Business & Finance

    German wind turbine maker Senvion reported EUR 90.6 million revenue from the sale of offshore wind turbines in the first three months of 2017, a 217.9 jump compared to EUR 28.5 million revenue recorded in the first quarter of 2016.

  • 19 March 2015
    Wind Farm Update

    The €1.2 billion Nordsee One project has reached financial close announced Canadian-German duo today. Northland, who owns 85%, and RWE Innogy, who owns the remaining 15% of 332MW project, said the equity is contributed to the project and all debt required for the project is fully committed. Approximately 70% of the project’s required costs will be provided from […]

  • 7 November 2018
    Business & Finance

    Canada’s energy company Northland Power has reported CAD 93.3 million (EUR 62 million) net income for the third quarter of 2018, a 194% increase compared to CAD 31.7 million net income in the same period last year, attributed mostly to higher production at the Nordsee One offshore wind farm in Germany and higher production and wholesale market prices at the Gemini offshore wind farm in the Netherlands.

  • 4 September 2014

    Northland Power Inc., (“Northland”) Toronto, and RWE Innogy GmbH, Essen, have signed an agreement for Northland to acquire an 85% equity stake in three offshore wind projects, consisting of Nordsee One, a 332 megawatt (MW) project currently in advanced development, as well as Nordsee Two and Nordsee Three, which are in early stages of development. […]

  • 27 August 2015
    Vessels, Wind Farm Update

    Nordsee One GmbH has issued a call for tenders for a crew transfer vessel to serve its Nordsee One offshore wind farm. The contract will be awarded for the charter of one crew transfer vessel capable of daily transfers of staff and equipment from Norddeich or alternative harbours to the offshore wind farm site and between individual […]

  • 17 April 2015
    Business & Finance, Wind Farm Update

    ABS Group Ltd. was recently awarded a quality surveillance and inspection services contract for the Nordsee One offshore wind farm project, owned by Northland Power Inc. and RWE Innogy GmbH through the Nordsee One GmbH joint venture. The contract will involve quality surveillance and inspection services relating to the fabrication, manufacturing and installation of the Nordsee […]

  • 21 December 2017
    Business & Finance, Operations & Maintenance, R&D, Wind Farm Update

    The 332MW Nordsee One offshore wind farm located in the German North Sea started commercial operation on Thursday, 21 December.

  • 10 August 2017
    Wind Farm Update

    MPI Offshore’s wind turbine installation vessel MPI Enterprise has installed 44 out of 54 Senvion 6.2M126 wind turbines at the 332MW Nordsee One offshore wind farm in the German North Sea, Canada’s Northland Power reports.

  • 21 December 2018
    Wind Farm Update

    German 332MW offshore wind farm, Nordsee One, entered full commercial operation on 21 December 2017 and its owners – Northland Power (85%), innogy (13.5%) and Enova (1.5%) – are now celebrating the project’s first year of operation.

  • 7 July 2015
    Operations & Maintenance, Wind Farm Update

    Nordsee One GmbH has chosen Norddeich (Lower-Saxony) as the base port for the Nordsee One offshore wind farm, for which it signed a long-term rental agreement with Norddeicher Schiffswerft GmbH. The rental agreement will be valid for the next 26 years and covers more than 1,500 m² for offices and workshop/warehouse. A local architecture company Architektur- & Ingenieurbüro Torsten Janssen will design […]

  • 8 March 2017
    Vessels, Wind Farm Update

    innogy SE has shared several photos showing the installation of the first and the second Senvion 6.2M126 turbine at the 332ME Nordsee One offshore wind farm in the German North Sea.

  • 27 April 2017
    Vessels, Wind Farm Update

    Offshore service vessel Island Crown has just finished a month-long walk-to-work job for Bluestream at Nordsee One wind farm in the German North Sea, Island Offshore reports.

  • 9 August 2018
    Business & Finance

    Northland Power reported CAD 192.6 million in offshore wind sales in the second quarter of 2018, a CAD 31.9 million increase compared to the same period last year, mostly due to all turbines at the 332MW Nordsee One project producing power.