Construction Starts on Siemens Gamesa’s Hull Blade Factory Expansion

VolkerFitzpatrick has started with construction works on Siemens Gamesa Renewable Energy’s two blade manufacturing facilities, as well as on repurposing an existing factory, at the wind turbine supplier’s site in Hull.

VolkerFitzpatrick

The work, being carried out under an GBP 82 million (around EUR 96 million) design and build contract, began in August and are due for completion in May 2023, with the new facilities to be built in two phases.

An image rendering Siemens Gamesa's new blade manufacturing site in Hull, UK
Source: VolkerFitzpatrick

Phase one will include pre-cast piling, drainage and foundations, and steel frame structures. The steelwork has been specially designed to allow 40-metre clear spans, with a working height of 18 metres and significant load-bearing capability, to accommodate the various gantry and console cranes required during the wind turbine blade manufacturing process.

The buildings will cover a total footprint of 42,362 square metres and will be finished with aluminium faced insulated panels to the roof and walls, in continuity with the existing blade factory. The mechanical and electrical fit-out will include services for lighting, power, water, humidity control, ventilation and cooling.

Related Article

Phase two will involve modifications to the existing 34,217-square-metre blade factory, to repurpose it from a production facility to a finishing area. This will include internal reconfigurations, as well as upgrading and replacing mechanical services. The building’s envelope, steelwork and doors will also be altered to allow for larger blades to be maneuvered in and out.

VolkerFitzpatrick also built Siemens Gamesa’s existing blade factory at the same site in 2016.

Related Article

Once the new facilities are built and put into operation, they will enable the company to produce lager blades, with greater efficiency, Siemens Gamesa said.

According to the factory owner, VolkerFitzpatrick will support the local community throughout the construction and repurposing works by hiring trainees and a portion of its supply chain from the surrounding area, and will also re-use stone from the existing site, helping to minimise waste material.