Seajacks Scylla Loads First Deutsche Bucht Steel

Image source: Rhenus Offshore Logistics

The jack-up Seajacks Scylla has left Cuxhaven loaded with the first three monopiles and transition pieces to be installed on the 269MW Deutsche Bucht wind farm in the German North Sea.

The jack-up loaded the first three sets of foundation components at berth no. 4 at the Cuxport Terminal in Cuxhaven.

31 transition pieces for the wind farm have already been supplied to Cuxhaven from Spain on board the Happy Star heavy-lift vessel. The accompanying monopiles, each weighing around 1,100 tonnes, are being transported by barge from Rostock to Cuxhaven just in sequence and are being directly lifted from the barges to the installation vessel.

“By using the ship’s own cranes, it’s possible to complete the project without any shore crane. The fact that this new berth is being used for this project so soon after its completion shows how essential it is,” said Roland Schneider, Head of Business Development at Cuxport.

Cuxport is supporting the Balance of Plant contractor Van Oord at the new heavy-lift berth with a total capacity of 8.5 hectares of space. Rhenus Offshore Logistics takes on the function as port agent for the project, including the customs clearance and the crew changes.

The Deutsche Bucht wind farm is Canadian power producer Northland Power’s third North Sea offshore wind project. The wind farm is located about 95 kilometres northwest of the island of Borkum in the German Exclusive Economic Zone.

Van Oord is responsible for the design, engineering, procurement, construction and installation of the foundations, inter-array cables and offshore substation, and the transport of the wind turbines. MHI Vestas is handling the installation of the turbines. The offshore wind turbines will be connected to the BorWin beta offshore converter station, which is already operating.

The Deutsche Bucht wind farm will have a total of 33 wind turbines, 31 on monopiles and two on so-called Mono Bucket foundations. It is the first time this new type of foundation structure will be tested under commercial operating conditions. The 33 MHI Vestas offshore wind turbines can each generate up to 8.4MW of power.

Share this article

Follow Offshore Wind

Events>

<< Dec 2018 >>
MTWTFSS
26 27 28 29 30 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31 1 2 3 4 5 6

Energy Storage 2019

The conference will bring together senior representatives from European energy suppliers, developers…

read more >

5th Asia Offshore Wind Day 2019

The event will bring together senior executives active in the offshore wind industry in Asia…

read more >

11th Annual Wind Operations Dallas 2019 Conference & Exhibition

Wind Operations Dallas (O&M, Asset Management, Storage) will draw together 100 professional speakers…

read more >

Jobs>

Senior Contract Manager

Here at Scottish Power Renewables we’re committed to remaining a UK leader in renewable energy. As well as investing in our technologies, we are committed to investing in the future of extraordinary people like you...

apply

O&M Lead Contract Manager

Here at Scottish Power Renewables we’re committed to remaining a UK leader in renewable energy. As well as investing in our technologies, we are committed to investing in the future of extraordinary people like you...

apply

Senior Operations & Maintenance Engineer

The Senior O&M Engineer (Structural) sits within the Asset Integrity Management Department team of Offshore O&M, reporting to a Lead O&M Engineer...

apply

Vessels>