Kincardine Team Seeks Using Latest Wind Turbine Technology

Visualisation; Image source: Kincardine Offshore Windfarm Limited

On 15 May, the Scottish government approved the variation application submitted by Kincardine Offshore Windfarm Limited (KOWL) in November 2017 for the floating wind project to be built some 15 kilometres south-east of Aberdeen.

The variation request includes the reduction of the total number of turbines from eight to seven, with one 2MW turbine to be installed first, followed by six larger turbines with an output of up to 8.4MW. The project will retain its capacity limit of 50MW even with these changes, according to the consent decision letter.

Furthermore, KOWL is approved to change the maximum rotor diameter from 152 to 164 metres, turbine hub heights from 100 to 105 metres measured from Lowest Astronomical Tide (LAT), blade width from up to 4.5 to 5.4 metres, and to increase the maximum blade tip height from 176 to 191 metres above LAT.

Based on the turbine specifications KOWL listed in its variation application from November 2017, it looks like the project team has been considering using MHI Vestas 8MW platform with an increased power output.

The developer, a joint venture between Pilot Offshore Renewables and Atkins, is certainly seeking to use the latest wind turbine technology, given that KOWL filed another variation application on 9 May, seeking to remove the limit on the individual turbine capacity.

“The First Variation Application was submitted in November 2017 due to necessary technical changes, including an increase in the rated capacity for the largest turbines that were being considered at the time of writing the application.”

“Since our application in November 2017, there have been further improvements in wind turbine technology. The 8.4MW model noted in the First Variation Application documents may no longer be in production, and turbines are now available which have a higher rated capacity than those previously assessed, without changing the physical dimensions or operational parameters.”

Offshore WIND reached out to KOWL to confirm the wind turbines the developer is considering are those from MHI Vestas and to see if there were any updates regarding the second variation application. KOWL is yet to respond.


The Scottish government granted planning consent to the 50MW floating wind project, located approx. 15 kilometres off the Kincardineshire coast, in March 2017.

The Kincardine floating wind farm is a commercial demonstrator which will utilise floating semi-submersible technology to install seven large wind turbines in water depths of between 45 and 143 metres.

The project does not feature an offshore substation, as the wind turbines would be connected directly to the grid at Redmoss onshore substation via two transmission lines.

Offshore WIND Staff

Share this article

Follow Offshore Wind

Events>

<< Oct 2018 >>
MTWTFSS
1 2 3 4 5 6 7
8 9 10 11 12 13 14
15 16 17 18 19 20 21
22 23 24 25 26 27 28
29 30 31 1 2 3 4

ACI’s Operating Specialist Wind Vessels 2018

Already on its 5th edition, ACI’s Operating Specialist Wind Vessels 2018 will bring together senior executives and experts from ship owners

read more >

Offshore Energy Exhibition & Conference 2018

Offshore Energy Exhibition & Conference (OEEC) is Europe’s leading offshore energy event. It is unique in bringing together the oil & gas…

read more >

Offshore Wind Conference 2018

The 9th annual Offshore Wind Conference brings together the entire offshore wind value chain to discuss current…

read more >

Annual Asia Wind Energy Conference

Renewable energy such as wind energy is now increasingly being adopted by emerging economies …

read more >

Jobs>

Senior Operations & Maintenance Engineer

The Senior O&M Engineer (Structural) sits within the Asset Integrity Management Department team of Offshore O&M, reporting to a Lead O&M Engineer...

apply

Senior Contract Manager

Here at Scottish Power Renewables we’re committed to remaining a UK leader in renewable energy. As well as investing in our technologies, we are committed to investing in the future of extraordinary people like you...

apply

O&M Lead Contract Manager

Here at Scottish Power Renewables we’re committed to remaining a UK leader in renewable energy. As well as investing in our technologies, we are committed to investing in the future of extraordinary people like you...

apply

Vessels>