Race Bank Substation Jacket In Place (Gallery)

The jacket foundation for the Race Bank 01 offshore substation (OSS) was placed and fixed to the seabed at the offshore wind farm site on 15 March, with the 2,900t topside up next.


Engie Fabricom and Iemants, part of the Smulders group, sent off the substation from Hoboken in Belgium to the offshore construction site in the UK on 5 March.

The offshore works are carried out by Seaway Heavy Lifting (SHL), which also installed Race Bank 02, the first substation at the site, in August 2016.

Iemants and Engie Fabricom have been in charge of delivering both offshore substations for the 580MW offshore wind project, which is planned to be completed in 2018.

Turbine installation is set to start by the end of April, with A2SEA's Sea Installer already preparing for the work. At Race Bank, located off the North Norfolk coast, the vessel will erect 91 Siemens 6MW wind turbines.

Photos: DONG Energy

Related news

List of related news articles

Posted: 10 months ago

BorWin Gamma Unites with Its Jacket

The BorWin gamma topside has been installed onto its jacket foundation at the offshore site in the G...

Categories:
  • Grid Connection
Posted: 10 months ago
Posted: 10 months ago

BorWin Gamma Arrives Home

The BorWin gamma topside has completed its journey from Dubai to the installation site in the German...

Categories:
  • Grid Connection
Posted: 10 months ago
Posted: 10 months ago

BorWin Gamma Preps for Installation

The BorWin gamma topside is currently being prepared for installation onto its jacket foundation in ...

Categories:
  • Grid Connection
Posted: 10 months ago
Posted: 10 months ago

Virginia Affirms Offshore Wind Ambitions

Virginia's Governor Ralph Northam has released the 2018 Virginia Energy Plan which calls for the dev...

Categories:
  • Authorities
Posted: 10 months ago