New Round of Dialogue on Kriegers Flak OWF Project

New Round of Dialogue on Kriegers Flak OWF Project

In order to ensure that potential tenderers can offer their views on framework conditions and contribute to making the content of the conditions attractive and flexible for the market, the Danish Energy Agency (DEA) decided to conduct a technical dialogue in May 2013 covering two offshore wind projects, the Horns Rev 3 and Kriegers Flak. Today, the DEA issued a timetable for the new round of dialogue. 

While the tender for Horns Rev 3 has proceeded as planned, there have been important changes to the Kriegers Flak project following the first and successful market dialogue.

The changes have led to important amendments of the original timetable of the tender procedure as well as pushed back the time delay for commissioning the whole farm with two years from 2020 to 2022.

The new timetable

Considering the magnitude of the changes, the Danish Energy Agency has decided to renew the call for a technical dialogue concerning Kriegers Flak. The aim is still to make the tendering procedure and conditions as attractive and flexible as possible.

The form of the dialogue will be through the Danish Energy Agency asking the market specific questions on the basis of selected themes in this dialogue paper. Potential tenderers will be able to detail their written replies and views in bilateral meetings with the Danish Energy Agency. The replies will help drafting of the preliminary tender conditions.

[mappress mapid=”14578″]

Press release; Image: Energinet.dk