Japan: Experimental Offshore Floating Wind Farm Project

Japan Experimental Offshore Floating Wind Farm Project

A consortium made up of Marubeni (project integrator), the University of Tokyo (technical advisor), Mitsubishi, Mitsubishi Heavy Industries, Japan Marine United, Mitsui Engineering & Shipbuilding, Nippon Steel & Sumitomo Metal Corporation, Hitachi, Furukawa Electric, Shimizu, and Mizuho Information & Research have been participating in an experimental offshore floating wind farm project sponsored by the Ministry of Economy, Trade and Industry since March 2012.

At present, the laying of the extra-high voltage undersea cable and the dynamic cable at the testing area has been successfully completed.

1. Outline of construction works in the first term

  •  Setting one 2MW downwind-type floating wind turbine, the world’s first 66kV floating power sub-station and the cables.

2. Work progress to date <2MW downwind-type floating wind turbine and 66kV floating power sub-station>

  •  Mooring operation has been successfully completed.
  • Preparatory works for the operation are in process.

<Undersea cables>

  •  Connection of the extra-high voltage undersea cable and the dynamic cable has been successfully completed between onshore transmission line tower and 2MW downwind-type floating wind turbine through 66kV floating power sub-station.

3. Next Step

The following activities need to be completed to start operation of the power facilities.

Expected commencement of operation of the power facilities is November 2013, but the schedule will be changed depending on the meteorological and sea conditions.

 

Mid October

Depression of 66kV floating power sub-station

Pre-use inspection

Late October
Power receiving of 2MW floating wind turbine and 66kV floating power sub-station from Tohoku Electric Power Co., Inc
November
Commencement of operation

Press release, October 11, 2013; Image: hitachi

 

Share this article

Follow Offshore Wind

Leave a Reply

Events>

<< May 2015 >>
MTWTFSS
27 28 29 30 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 29 30 31

Energy Ocean 2015

Energy Ocean is your opportunity to meet with Energy Producers, Technology Developers, Policy Makers, Scientists, Engineering Firms, and…

read more >

Course of Marine Operations Simulation with SESAM MARINE organized by DNV-GL in collaboration with IHCantabria

The course introduces the participants to Sesam Marine for simulation of marine operations, heavy lifting, side-by-side mooring, floatover and floating wind turbines…

read more >

Young Professionals Green Energy Awards 2015

As an extension of the sell-out Scottish Green Energy Awards, this event will welcome Scottish Renewables members, guests and friends from…

read more >

UK Technical Seminar: Advanced Coastal, Lab and Turbulence Studies

Users are invited to contribute 15 minute presentations about their work and experiences on the following presentation themes…

read more >

Jobs>

Vacancy OIM

For one of our clients we are looking for a OIM on board of a Cable Lay vessel. Our client works in the Offshore industry. They are working worldwide in a 4 weeks on and off schedule...

apply

Lead Engineer

As the yard is specialized in the production of large Tugs and Fast Crew Suppliers the engineering team is mainly involved in the detail engineering and production support of these vessels. You are coordinating a project team and responsible for ...

apply

Superintendent Cable Lay and Cable Burial Offshore Wind Projects

The Superintendent Cable Lay and Cable Burial Offshore Wind Projects is responsible for and monitor our Cable Lay and Burial on board of our Cable Lay and Burial installation vessel the NEXUS...

apply

Vessels>