Search results for: Baltic 2

1718 results

A list of search results

  • 13 December 2013
    Wind Farm Update

    In just over two months Ballast Nedam Offshore has transported and installed 39 monopiles for the offshore wind farm Baltic 2. This was achieved despite the occurrence of two of the worst storms in a decade in October and November. Among the monopiles installed, were the largest monopiles used in offshore wind energy so far […]

  • 31 July 2023
    Authorities, Business development, Research & Development

    The US Bureau of Ocean Energy Management (BOEM) has announced three final wind energy areas (WEAs) offshore Delaware, Maryland, and Virginia, which, if fully developed, could support between 4 GW and 8 GW of offshore wind capacity. The three WEAs total approximately 356,550 acres. The first WEA (A-2) is 101,767 acres and is located 26 […]

  • 16 June 2015
    Vessels

    The ASV Pioneer, an accommodation barge managed by Dalby Offshore, is assisting in cable works on the Baltic 2 offshore wind farm for the summer and is supported by a spread of two tugs and a number of specialist personnel. The vessel mobilised from the UK in February and is expected to remain in the Baltic area […]

  • 8 July 2014
    Grid Connection, Wind Farm Update

    The jacket foundation for the Baltic 2 wind farm substation was loaded on a special pontoon Offshore BHV 1 in  Labradorhafen Bremerhavener yesterday. The 1,500-ton component will be shipped to Sassnitz, and from there it will sail to the construction site. The wind farm consisting of 80 Siemens 3.6MW wind turbines is located 32km north […]

  • 15 December 2016
    Contracts & Tenders, Grid Connection

    Nkt cables has appointed VBMS for the installation of approximately 50km of 150 kV AC high-voltage submarine cables for the Kriegers Flak Combined Grid Solution (CGS). The project, owned by Energinet.dk and 50Hertz, will connect the future Danish offshore wind farm Kriegers Flak and the German offshore wind farm Baltic 2, both located in the […]

  • 12 June 2015
    Wind Farm Update

    The EnBW Baltic 2 offshore wind farm has come to the finish line, as the eightieth and last wind turbine was installed yesterday at the construction site in the German Baltic Sea. On Tuesday, the fortieth turbine was put into operation and has been feeding power into the grid. In the meantime, two more were fully commissioned. The remaining wind turbines will […]

  • 24 November 2014

    On 26 August installation activities started at the 288MW EnBW Baltic 2 wind farm. The installation of the in total 80 Siemens SWT-3,6-120 turbines is being performed by the VIDAR. EnBW Baltic 2 is being constructed 32km north of the island Rügen, in the German Baltic Sea, in an area covering 27km2. The turbines are […]

  • 28 July 2016
    Business & Finance

    German energy company EnBW Energie Baden-Württemberg AG reported an adjusted EBIDTA (Earnings Before Interest, Taxes, Depreciation and Amortization) of EUR 153.1 million in its Renewable Energies segment, a 75% jump compared to the first half of 2015. Accordingly, the share of the EBITDA for the company accounted for by Renewable Energies increased from 6.9 percent to 15.8 percent. […]

  • 21 September 2015
    Wind Farm Update

    In the presence of the Minister President of Mecklenburg-Vorpommern, Erwin Sellering, and numerous guests from the worlds of business and politics, EnBW Energie Baden-Württemberg AG has officially put its second offshore wind farm in the Baltic Sea into operation. Following a construction period of around two years, EnBW Baltic 2 with its 80 wind turbines […]

  • 21 February 2012

    The investment offer for EnBW Baltic 2 offshore wind farm appears to be very popular: many municipal utilities, industrial companies and institutional investors from Baden-Württemberg and Germany are interested in participating in the second EnBW’s Baltic Sea wind farm. “We are delighted to be well received. In addition to partners who have already participated in […]

  • 2 February 2015
    Grid Connection

    JDR has extended its service support operations for the EnBW Baltic 2 offshore wind farm by Siem Offshore Contractors GmbH. Under a contract, JDR is providing pre-commissioning, test and termination services for the 80 turbine project in the Baltic Sea, off the coast of Rostock (Germany). JDR’s offshore wind test and termination team was commissioned to […]

  • 13 May 2016
    Business & Finance, Grid Connection

    German utility EnBW AG’s Grids and Renewable Energies division recorded a 159% increase in its operating result in the first quarter of 2016 compared to the same period in 2015, largely attributed to the 288 EnBW Baltic 2 offshore wind farm which was fully commissioned in September 2015. The division’s adjusted EBITDA was EUR 92.1 million in the […]

  • 8 January 2013

    ArGe Baltic 2 foundations, a Joint Venture between Hochtief and GeoSea, has awarded Ulstein Idea Equipment Solutions BV a contract for the Engineering, Procurement, Construction and Installation (EPCI) of a complete pile upend as well as lifting tool for the Baltic 2 wind farm installation project. By using basic laws of mechanical equilibrium, Ulstein Idea […]

  • 16 April 2013

    Ecosse Subsea Systems (ESS) has reported a successful start to a 10-week boulder clearing and trenching campaign on the Baltic 2 offshore wind farm project. Mobilised onboard the Siem Topaz anchor handling vessel, Ecosse Subsea’s SCAR subsea plough system is engaged on route clearing and pre-lay trenching operations on behalf of Siem Offshore Contractors. Soils […]

  • 31 May 2013

    EnBW is looking for a contractor for the lifting operations taking place in connection with loading of wind turbines onto the installation vessel as well as installation at an offshore windfarm EnBW Baltic 2 of 80 wind turbines. EnBW will need the assistance of lifting supervisors on board the wind turbine installation vessel surveying and […]

  • 26 August 2014

    On 19 August 2014 a new catamaran was christened at Knock Jetty in Emden. The ship’s godmother, Insa Stoidis-Connemann from Leer, gave the name “Windea Two” to the “Twin Axe Bow” type catamaran from Damen Shipyards and she wished: “Safe voyages for the crew and always a handbreadth of water under the keel for the […]

  • 5 May 2021
    Operations & Maintenance, Vessels, Wind Farm Update

    The service operations vessel Esvagt Dana has returned to the Baltic 2 offshore wind farm in the German Baltic Sea to support Siemens Gamesa during maintenance work. Esvagt and Siemens Gamesa entered into a 95-day agreement with an option of a further three months. The vessel provided support in Baltic 2 from November 2019 to […]

  • 13 March 2015
    Vessels

    FRS Windcat Offshore Logistics (FWOL) and EnBW Energie Baden-Württemberg AG have signed a five-year crew transfer contract for EnBW Baltic 2 wind farm in the German Baltic Sea. From 1 July 2015, the crew transfer vessel “Windcat 34” will sail daily from Rostock to the offshore wind farm EnBW Baltic 2 in the German Baltic Sea. EnBW […]

  • 15 April 2014
    Wind Farm Update

    All jacket pin piles have been installed at the Baltic 2 offshore wind farm, the project’s developer EnBW confirmed to Offshore WIND. Workers on the jack-up vessel Goliath have driven the jacket pin piles into the seabed. An important part of the work on the foundations is now complete, the company said. Baltic 2 consists […]

  • 29 October 2015
    Grid Connection

    Alstom has commissioned an AC offshore substation in the wind farm EnBW Baltic 2, Germany’s second offshore wind farm in the Baltic Sea. The wind farm hosts 80 wind turbines feeding up to 288 MW into the grid, providing power to 340,000 households. The offshore substation transmits the electrical energy from the wind turbines to […]

  • 13 November 2015
    Business & Finance, Operations & Maintenance, Wind Farm Update

    Since its official commissioning on September 21, the offshore wind farm EnBW Baltic 2 in Stralsund has helped the Karlsruhe-headquartered electric utilities company EnBW improve EBITDA in its renewable energies segment for the first nine months of 2015, and partly offset a 5.3% fall in revenue in the division. EBITDA rose to EUR 156.3 million in the first nine […]

  • 17 September 2014
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    A 4,400-ton substation for the EnBW Baltic 2 offshore wind farm has been prepared for transport at the shipyard of Abu Dhabi Mar Kiel. Since a very good weather for transportation and installation offshore is expected in the next few days, the platform should be moved directly to the construction field. Should the weather worsen, […]

  • 1 August 2014
    Business & Finance, Grid Connection

    In the first half of 2014, the EnBW Group achieved an operating result (adjusted EBITDA) of 1,271.5 million euros with 19,926 employees and almost unchanged revenue of around 10.4 billion euros. Earnings were 9.9 per cent below the figure for the first half of 2013. The operating result is thus developing in line with our […]

  • 4 November 2014
    Business & Finance, Wind Farm Update

    The order for AMBAU to manufacture 41 transition pieces (TPs) for Bladt Industries A/S to be used in the EnBW Baltic 2 wind farm came to an end on 16 October 2014 as the TPs were loaded for shipment. With a footprint of 13.5 metres, these TPs were the largest components ever to have left the facilities at AMBAU Bremen […]

  • 18 March 2015

    Seaway Heavy Lifting (SHL) has commissioned Skeye B.V. to film its new tool in action at the EnBW Baltic 2 offshore wind farm. The tool was specially developed by the company for placing tripod jacket foundations. Skeye was asked to film the performance of SHL’s new system and the installation of the tripods. Filming was done from the company’s heavy lift barge Stanislav Yudin. Aerial video footage […]

  • 4 July 2014
    Business & Finance, Operations & Maintenance, Wind Farm Update

    Specialist Marine Consultants Ltd (SMC) has begun another contract with Siemens Wind Power to provide marine coordination. The provision of services for the Baltic 2 offshore wind farm started at the beginning of July 2014 and sees SMC providing marine coordination on five offshore wind farm construction projects at once. Instructed by Siemens, SMC’s innovative […]