Search results for: hywind tampen

2643 results

A list of search results

  • 14 November 2022
    Wind Farm Update

    First power has been produced from the first turbine at Equinor’s Hywind Tampen floating offshore wind farm in the Norwegian part of the North Sea. The power from the first turbine, which was installed in June, was delivered to the Gullfaks A platform in the North Sea on 13 November. The Hywind Tampen floating offshore […]

  • 26 April 2019
    Contracts & Tenders, R&D, Wind Farm Update

    DEME Offshore has signed an agreement with Equinor to carry out a study examining potential floating concrete substructures for the planned Hywind Tampen floating wind farm in the Norwegian North Sea. The agreement was signed early December 2018 with a five-month duration, and the study is a part of the engineering works before the final investment […]

  • 16 October 2019
    Authorities, Wind Farm Update

    Equinor and the Snorre and Gullfaks partners have submitted updated development plans to the Norwegian government for the Hywind Tampen floating wind farm. The Hywind Tampen floating offshore wind farm will consist of 11 8MW wind turbines located some 140 kilometres from shore in 260-300 metres of water between the Snorre and Gullfaks oil and gas platforms. Equinor and […]

  • 31 October 2019
    Contracts & Tenders

    Following the award of a contract for the Hywind Tampen project, Kvaerner has joined forces with DOF Subsea to deliver marine operations for the floating wind farm in Norway. Kvaerner’s contract for the Hywind Tampen project is worth about NOK 1.5 billion (approx. EUR 146 million). In addition to engineering, procurement, and construction of the […]

  • 15 April 2022
    Ports & Logistics, Wind Farm Update

    The towing of 11 concrete SPAR-type floating foundations for the 88 MW Hywind Tampen offshore wind farm from Dommersnes to the assembly site in Gulen, Norway, has started. The concrete foundations will support the 11 Siemens Gamesa 8 MW wind turbines. The wind turbines will be fully assembled at the Wergeland Base in Gulen prior […]

  • 7 January 2021
    Contracts & Tenders

    Aker Solutions has awarded Granada Material Handling with a contract to supply eleven davit crane units for use at the Hywind Tampen floating offshore wind project in Norway. The company will design, supply, third party certify and commission 11 individual crane units. Granada said that each of its Python crane units has been specifically designed […]

  • 26 March 2020
    Contracts & Tenders, Wind Farm Update

    Equinor has awarded the offshore and engineering consultancy, Global Maritime, with a contract to provide Marine Warranty Survey services for the Hywind Tampen floating offshore wind project in the Norwegian North Sea. The project is still awaiting PUD approval but the intention is to start soon with the main offshore campaigns planned for 2022, Global […]

  • 19 February 2021
    Wind Farm Update

    Aker Solutions has begun the construction of concrete hulls that will carry the turbines at the Hywind Tampen floating offshore wind farm in Norway. Aker began the concrete slip-forming in Stord this week, of which there will be a total of almost 1.2 kilometers. Hywind Tampen will comprise 11 Siemens Gamesa 8 MW turbines installed […]

  • 28 August 2023
    Business & Finance, Business development, Contracts & Tenders, Equipment, Fixed-Bottom, Floating Wind, Foundations, Industry, Infrastructure, Innovation, Manufacturing, Market Outlooks, Outlook & Strategy, Ports & Logistics, R&D, Research & Development, Supply Chain, Technology, Vessels, Wind Turbines

    The following article is a guest post by Fred van Beers, CEO Sif Netherlands B.V., & Anne Vedel, SVP Product Solutions & Integration, Vestas. The looming climate crisis and an acute need for independence from Russian oil and gas have massively accelerated European appetite for offshore wind. Governments keep raising ambitions and underlining the importance […]

  • 21 January 2021
    Contracts & Tenders

    Kongsberg Maritime has secured a contract with Wood to supply positioning and monitoring equipment for the Hywind Tampen floating offshore wind farm. Kongsberg will supply its DPS position reference system and Motion Reference Unit (MRU) for what will be the world’s largest floating offshore wind farm. The DPS exploits all available GNSS infrastructure to deliver […]

  • 7 June 2022
    Wind Farm Update

    The first of the 11 Siemens Gamesa 8.6 MW wind turbines that will make up Equinor’s Hywind Tampen floating wind farm has been installed at the construction site some 140 kilometres offshore the Norwegian coast. The turbine had sailed away last week from the Wergeland’s base in Gulen in western Norway where it was assembled. […]

  • 29 April 2022
    Wind Farm Update

    After sending off the first tower sections for the Hywind Tampen wind turbines from its Bilbao factory at the beginning of March, Haizea Wind Group is nearing completion of its part of the project with eight towers manufactured so far. The 8-metre-diameter towers, the world’s largest in this respect, will support the eleven Siemens Gamesa 8 […]

  • 2 July 2019
    Business & Finance

    Equinor has met with the supplier industry in Norway to discuss cost-effective solutions for floating offshore wind farms on the Norwegian Continental Shelf. Equinor got together with Global Center of Expertise (GCE) NODE companies in Agder to talk about finding cost-optimal solutions related to designing floating foundations for turbines in the 10-15MW range. Additionally, the meetings were […]

  • 25 March 2022
    Ports & Logistics, Wind Farm Update

    Offshore construction on the 88 MW Hywind Tampen floating wind farm is set to start next week with the transport and installation of the suction anchors at the site located about 140 kilometres off the Norwegian coast, DOF Subsea said. The subsea AHTS vessel Skandi Skansen and the DOF Subsea team are currently preparing to […]

  • 22 July 2022
    Grid Connection, Wind Farm Update

    Subsea 7 has laid the first subsea cables in the water for the 94.6 MW Hywind Tampen floating wind farm offshore Norway. JDR Cable System is in charge of supplying the electric cables for the project from its factory in Hartlepool, the UK, while Subsea 7 is responsible for the installation of the cables and […]

  • 5 February 2019
    Contracts & Tenders, Ports & Logistics, Wind Farm Update

    Equinor has contracted the Gulen Industrial Harbour in Norway to provide a turbine assembly site for the Hywind Tampen floating wind project. The Gulen Industrial Harbour will provide onshore and inshore areas for storage, assembly and commissioning of all the components for the turbines, as well as necessary infrastructure and facilities in the project period. According to Equinor, […]

  • 3 June 2022
    Ports & Logistics, Wind Farm Update

    The first of the 11 Siemens Gamesa 8.6 MW floating wind turbines has started its journey from the Wergeland Base in Gulen towards the installation site some 140 kilometres offshore the Norwegian coast. The wind turbines are being assembled at the Wergeland Base in Gulen in western Norway prior to being towed to the installation […]

  • 14 November 2019
    Contracts & Tenders, Grid Connection

    JDR Cable Systems has secured a contract with Equinor to provide inter-array and export cables for the Hywind Tampen floating offshore wind project in Norway. JDR will design and manufacture eleven 66kV dynamic inter-array cables and two static export cables, each equipped with a JDR-designed breakaway system and a range of cable accessories for delivery […]

  • 31 October 2019
    Contracts & Tenders

    The Hywind Tampen developers have signed contracts with Kværner, Siemens Gamesa, Subsea 7 and JDR Cable Systems for the construction of the floating offshore wind farm that will power the Gullfaks and Snorre oil & gas platforms in Norway. Under the contracts worth NOK 3.3 billion (EUR 322.5 million), Kværner will construct the substructures, Siemens Gamesa will deliver eleven […]

  • 19 October 2020
    Ports & Logistics

    Wergeland Group and PSW Group have signed a Letter of Intent (LoI) with Huisman for the delivery of a Skyhook quayside crane at the Gulen Industrial Harbour, Norway. The Skyhook crane has a lifting capacity of 2,600mt in regular configuration as well as a high lift mode with a super flyjib, facilitating the assembly of […]

  • 7 April 2020
    Business & Finance

    EUR 6.1 billion was invested in four European offshore wind projects with a combined capacity of around 1.4 GW in 2019, marking the lowest amount invested and the capacity financed in a year since 2012, according to a report by WindEurope. The four wind farms that reached the Final Investment Decision (FID) in 2019 are […]

  • 1 April 2019
    Business & Finance, Wind Farm Update

    DNV GL is set to undertake a third-party verification study of Equinor’s Hywind Tampen floating wind farm in Norway, the world’s first expected to power oil platforms. The independent verification study will ensure that the wind turbines comply with the applicable codes and standards for floating offshore wind, DNV GL said. In addition, the study […]

  • 13 July 2022
    Wind Farm Update

    The 11-turbine Hywind Tampen, the world’s largest floating offshore wind farm under construction, will be completed in 2023 and not by the end of 2022 as initially planned, Equinor said. The first seven Siemens Gamesa 8.6 MW wind turbines will come on stream this year as planned. The final four will be installed next spring, […]

  • 7 July 2021
    Vessels, Wind Farm Update

    A few days after Simon Møkster Shipping announced its vessel Stril Server was chartered for the Hywind Tampen floating wind farm in Norway, Island Offshore and Vallourec revealed their contracts for the project. Island Offshore has been contracted for service operation vessel (SOV) services, with its walk-to-work vessel Island Diligence set to commence operations under the contract […]

  • 14 March 2023
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Equinor has awarded Ocean Installer a contract for the installation of dynamic inter-array cables on the Hywind Tampen floating offshore wind farm in Norway. The Norwegian company has been contracted to transport and install five 2.5-kilometre-long dynamic inter-array cables in water depths between 260 and 300 metres. These cables will connect existing turbines in the […]

  • 24 October 2019
    Business & Finance

    The last few months have been a game-changer for Equinor’s offshore wind business, the Norwegian energy company’s President and CEO Eldar Sætre said while commenting on the company’s results for the third quarter of 2019. ”Together with SSE, we were the winning bidder with three projects at Dogger Bank in the UK, making it the largest […]