281 results found for 'triton knoll'

281 results found for 'triton knoll'
Order results by

A list of search results

  • 14 March 2019
    Business & Finance, Grid Connection, Wind Farm Update

    The key works to connect the onshore and offshore electrical circuits of the Triton Knoll offshore wind project are set to start at the end of March, according to the project developer. The activities will take place at the project’s landfall location north of Anderby Creek, the UK, and will include Horizontal Directional Drilling (HDD) work expected […]

  • 1 May 2015
    Environment, Grid Connection

    Triton Knoll Offshore Wind Farm has submitted an application for a Development Consent Order (DCO) for the Triton Knoll Electrical System on 24 April 2015. “The application and associated documents will be reviewed by the Planning Inspectorate and we await confirmation that our application has been accepted,” said the company in a statement for Offshore […]

  • 10 November 2021
    Contracts & Tenders, Grid Connection

    A consortium of the London-based Equitix Limited and Japan’s TEPCO Power Grid has been selected as the preferred bidder for the offshore electricity transmission link connecting the 857 MW Triton Knoll wind farm to the UK grid. Valued at approximately GBP 577 million (EUR 675 million), the new offshore electricity transmission asset is comprised of […]

  • 21 March 2019
    Contracts & Tenders

    James Fisher Marine Services (JFMS) has secured a contract to carry out unexploded ordnance (UXO) removal and boulder clearance at the Triton Knoll offshore wind farm. JFMS is in charge of investigating and clearing locations at the 145km2 offshore site where earlier surveys have identified potential obstructions to construction. The works, set to begin in spring, […]

  • 10 June 2020
    Grid Connection

    Rotech Subsea has completed a three-phase work scope at the Borssele and Triton Knoll offshore wind farms for a dredging specialist. Rotech provided its TRS1 and TRS1LD Jet Trenching tools to carry out pit clearing and cable lowering at the Borssele project in the Dutch North Sea, as well as grout bag and cable de-burial […]

  • 19 June 2020
    Grid Connection, Wind Farm Update

    The consortium of Boskalis and NKT is set to work through the summer to install the offshore export cables at the Triton Knoll offshore wind farm in the UK. As reported, an initial 25km stretch of export cable has already been installed from the landfall north of Anderby Creek in Lincolnshire, establishing a connection between […]

  • 14 October 2019
    Grid Connection, Wind Farm Update

    The first transformer station has been delivered to the onshore substation of the Triton Knoll offshore wind farm in the UK. The transformer set sail from the manufacturing site in Austria towards the Sutton Bridge port in Lincolnshire, from where it was lifted onto a trailer and driven 20 miles to the Bicker Fen site. […]

  • 22 May 2015
    Grid Connection, Wind Farm Update

    The application for the electrical infrastructure for RWE’s Triton Knoll offshore wind farm has been accepted for examination, the UK Planning Inspectorate notified on its website.  RWE seeks an order granting development consent for its proposed electrical system, comprising onshore and offshore buried export cables, an intermediate electrical compound, and a substation located in the vicinity of the grid […]

  • 31 August 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    German-based offshore wind developer innogy has reached financial close for the 860MW Triton Knoll offshore wind farm in the UK, worth around GBP 2 billion, and moved the project towards construction that starts with the onshore electrical system in September.

  • 7 October 2014
    Grid Connection, R&D, Wind Farm Update

    The statutory consultation on the Triton Knoll Electrical System proposals will run from 15th October to 19th November 2014.  RWE has announced that it is now at a stage of the project where it can begin statutory consultation on the whole Triton Knoll Electrical System proposals ahead of submitting its application to the Planning Inspectorate in Spring 2015. The […]

  • 1 February 2021
    Contracts & Tenders, Vessels

    Solstad Offshore has signed a contract with MHI Vestas for the charter of its construction support vessel (CSV) Normand Fortress. The vessel will support MHI Vestas’ walk-to-work operations at the Triton Knoll offshore wind farm in the UK as of March. The contract has been signed for a firm period of 140 days with extension […]

  • 17 September 2021
    Wind Farm Update

    The 90th and final wind turbine has been installed at the Triton Knoll offshore wind farm site, located 32 kilometres off the coast of Lincolnshire in the UK. Wind turbine installation works commenced in January 2021 after Cadeler’s wind farm installation vessel Wind Osprey arrived at the site loaded with the first sets of Vestas […]

  • 8 April 2019
    Contracts & Tenders, Vessels

    Innogy has contracted Esvagt to provide its service operation vessel (SOV) Esvagt Froude for the construction of the Triton Knoll offshore wind farm in the UK. The contract will see Esvagt Froude support the construction of the project’s 90 MHI Vestas 9.5MW turbines, scheduled to be installed between the beginning of next year and the end […]

  • 31 May 2018

    Triton Knoll Offshore Wind Farm Ltd will hold a series of public information days in June to inform local residents in Lincolnshire, UK, about the wind farm’s onshore works before the initial activity begins in the coming weeks.

  • 13 June 2017
    Wind Farm Update

    Triton Knoll Offshore Wind Farm has awarded its largest onshore contract to date to Lincoln-based archaeologists Allen Archaeology.

  • 12 June 2017
    Environment, R&D, Wind Farm Update

    Triton Knoll Offshore Wind Farm will shortly begin an archaeological trial trenching programme along the full route of the 900MW wind farm’s onshore export cable corridor in Lincolnshire.

  • 13 August 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    German energy company Innogy has agreed to sell a 41% stake in its 860MW Triton Knoll offshore wind farm in the UK to Japan’s J-Power (25%) and Kansai Electric Power (16%).

  • 11 July 2013

    RenewableUK has welcomed news that Triton Knoll Offshore Wind Farm, to be built off the east coast of England, has been given final consent by the Secretary of State for Energy and Climate Change Edward Davey. This major project will include up to 288 turbines and is due to have an installed capacity of up […]

  • 21 February 2018
    Authorities, Business & Finance, Environment, Grid Connection, Wind Farm Update

    Triton Knoll Offshore Wind Farm Limited has filed an application to the UK’s Secretary of State for Business, Energy and Industrial Strategy (BEIS) seeking to make changes to the project’s Development Consent Order (DCO).

  • 8 October 2021
    Grid Connection, Wind Farm Update

    RWE has completed all the major onshore electrical system construction works for the 857 MW Triton Knoll offshore wind farm project in Lincolnshire, the UK. The works, which commenced in September 2018, involved laying 57 kilometres of 220 kV underground cable from the project’s landfall location near Anderby Creek to the newly constructed Triton Knoll […]

  • 4 April 2019
    Contracts & Tenders, Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Grimsby’s Royal Dock has been confirmed as the home for Triton Knoll’s offshore construction and operations and maintenance facility after the project signed a port lease with ABP in Grimsby. A new construction and longer-term Operations and Maintenance base will be constructed across nearly four acres. Tendering for a contractor to build the facility is […]

  • 15 April 2020
    Grid Connection, Wind Farm Update

    The first Triton Knoll offshore substation platform (OSP) is now standing at its designated location at the project site.

  • 31 July 2019
    Jobs & Recruitment, Operations & Maintenance, Wind Farm Update

    Innogy has kicked off a recruitment drive for up to 22 roles at its new Triton Knoll operations & maintenance (O&M) base in Grimsby, UK. Adverts for the new roles go live from Wednesday, 31 July, as the developer seeks to identify local talent for a range of jobs. The open positions being advertised are […]

  • 24 September 2017

    Offshore WIND’s most read news from 18 to 24 September 2017.

  • 9 December 2019
    Wind Farm Update

    Staffing and recruitment specialist Bureau UK has secured a framework agreement to provide resourcing to support the quality assurance, quality control, and surveillance activities across the Triton Knoll offshore wind project. Bureau UK is sourcing engineers to undertake work around Quality and Production Assurance Services for the project. The work carried out will cover the […]

  • 19 December 2017
    Business & Finance, Environment, Ports & Logistics, R&D

    Triton Knoll Offshore Wind Farm Ltd. is setting up two funds to support the local communities living close to the onshore infrastructure of the 860MW wind farm located some 32km offshore Lincolnshire, UK.