  • 15 April 2015
    Wind Farm Update

    Eneco Luchterduinen offshore wind farm has reached another milestone in its construction phase. Following a successful installation of the first turbine tower 23 kilometers off the coast of Noordwijk and Zandvoort, Van Oord had installed the first wind turbine last week. Van Oord’s new transport and installation vessel ‘Aeolus’ is used for the construction. It […]

  • 22 January 2013
    Business & Finance

    Eneco and Mitsubishi Corporation (MC) have concluded an agreement giving MC a 50% stake in the Eneco Luchterduinen offshore wind farm. The companies have also entered into a ‘Long-Term Partnership Agreement’, signalling their intention to work together on other offshore wind energy activities in Europe. This signals the start of a new phase of the […]

  • 4 June 2014
    Wind Farm Update

    On Tuesday May 20th, Verbrugge Terminals in the Port of Vlissingen successfully completed the first load-in for the Dutch offshore wind farm ‘Eneco Luchterduinen’. The monopiles are constructed by SIF Group and Smulders Group and are transported to Vlissingen for intermediate storage. In July 2014 the first monopiles will be shipped out and installed by […]

  • 30 May 2014
    Business & Finance

    The offshore wind farms Prinses Amaliawindpark, operational since 2008, and Eneco Luchterduinen, expected to enter operation next year, require inspection and maintenance of its balance of plant. This is defined as the wind turbine foundations and the OHVS foundation (below and above water and primary and secondary steel and cathodic protection), the outside steel structure […]

  • 20 June 2014
    Business & Finance

    Van Oord is holding a two-day event along the Rotterdam Wilhelminakade quay to mark the entry into service of Aeolus, its first transport and installation vessel for the construction of offshore wind farms. Today, business relations have the opportunity to inspect the vessel. On Saturday 21 June, Mrs K. Aboutaleb-Erahoutan, wife of the Mayor of […]

  • 12 May 2014
    Technology, Wind Farm Update

    In early July, Van Oord will commence the offshore installation of the 43 foundation piles for the Eneco Luchterduinen Wind Farm, the third Dutch offshore wind farm, which will be utilizing innovative new design elements with regard to its foundation piles.  While the tower and foundation components of offshore wind turbines have been connected by means of a […]

  • 25 May 2015
    Operations & Maintenance

    Last Friday saw a completion of the 240-hour test phase of the first of 43 wind turbines at offshore wind park Eneco Luchterduinen. This means that the wind park is now generating green energy for the Dutch grid. According to Van Oord, the installation of the wind turbines is progressing well with offshore installation vessel Aeolus […]

  • 10 September 2014
    Grid Connection, Wind Farm Update

    One of the Dutch offshore wind farms, Eneco Luchterduinen is taking shape, according to Eneco. Van Oord’s jack-up vessel Aeolus installed a total of 16 foundations by 8 September. Eneco added that they faced windy weather at the beginning of August, “but the last few weeks are very good. We had some minor starting problems […]

  • 4 September 2014
    Grid Connection

    The onshore preparations for the new 129 MW Eneco Luchterduinen, a partnership of Eneco and Mitsubishi Corporation, offshore wind farm have entered a new stage. Pre-fabricated sub-modules for the Offshore High Voltage Substation (OHVS) have now been transported to the yard of Fabricom in Antwerp, Belgium. In the coming six months, the final assembly and […]

  • 14 March 2015
    Grid Connection

    The high-voltage substation for the Eneco Luchterduinen offshore wind project has recently been installed in the Dutch North Sea. The substation was designed and built by Belgian firms Iemants, CG and Cofely Fabricon. Protective coatings from AkzoNobel’s International brand were used to protect the substation from the tough and corrosive environment of the North Sea. […]

  • 5 August 2016
    Business & Finance, Grid Connection

    Dutch energy company Eneco Group recorded EUR 139 million profit after income tax , slightly less than the EUR 144 million made by the company in the same period last year, as a result of lower prices for gas and, to a smaller extent, for electricity. The group’s grid operator, Stedin, and the energy company, Eneco, contributed more or […]

  • 26 August 2014

    Offshore Wind Services’ (OWS) latest Damen vessel – the Fast Crew Supplier 2008 ‘Offshore Waddenzee’ – was officially named at Damen Oranjewerf Amsterdam, on August 22. The FCS 2008 is the second vessel the Dutch company, which is a specialist in the provision of crew transfer vessels to the offshore wind industry, has ordered this […]

  • 26 October 2014

    TenneT Invites Tenders for BorWin4 TenneT-owned DC-Netz BorWin4 GmbH is inviting tenders for BorWin4 connection system located in the North Sea. Trianel Wind Farm Borkum Commissioning Pushed to 2015 The initial testing of the link between Trianel Wind Farm Borkum’s transformation platform and TenneT’s transformation platform “DolWin 1” failed. Seatower to Load Out Foundation from […]

  • 1 August 2014
    Wind Farm Update

    Van Oord kicked off the construction works on a 129MW wind farm located in the Dutch area of the North Sea. Yesterday, the wind turbine construction jack-up vessel  Aeolus commenced the foundation installation at Eneco Luchterduinen offshore wind farm. The wind energy project will comprise 43 Vestas V112 wind turbines installed 23 kilometers off the […]

  • 18 July 2014
    Technology

    Temporary Works Design (TWD) completed the design and assisted in the fabrication of a monopile gripper frame for Van Oord. The gripper is designed to keep the monopiles in the correct position and inclination, while counteracting the wave, wind, and current loads on the pile during wind turbine installations. The installation of the monopile gripper […]

  • 21 March 2016
    Vessels

    Seajacks Scylla, which made its maiden call to the Port of IJmuiden on 14 March, is readying for her first job at Veja Mate offshore wind farm in Germany.  At the port, the vessel was equipped with a monopile gripper, so it can install the 67 foundations for the German 402MW project. The Port of IJmuiden (Zeehaven […]

  • 9 August 2016
    Operations & Maintenance

    Dutch port of IJmuiden has installed two floating jetties at the recently renovated Trawlerkade quay, thus adding 46 metres of extra berthing space for crew transfer vessels used for offshore wind farm operations and maintenance, Amsterdam IJmuiden Offshore Port (AYOP) reports. The floating jetties will offer berths for six of Windcat Workboat’s CTVs. A wave protection barrier gives access to both pontoons […]

  • 30 September 2013
    Business & Finance

    On September 26th, Euskalforging received an order for 43 TP flanges for the Luchterduinen offshore wind farm. A record of 615 TP and MP flanges will be supplied by Euskalforging this year. Reported projects (TP and MP flanges) gained during 2013 by Euskalforging are: Dan Tysk, Amrumbank West, Humber Gateway, and Baltic 2. [mappress] Press […]

  • 21 February 2014

    Sif Group in the city of Roermond is working hard on the production of 43 steel foundation piles for the Eneco Luchterduinen Wind Farm. Ultimately, these piles will be installed 23 kilometres off the coast between Noordwijk and Zandvoort. What makes these foundation piles special is the fact that the wind turbines will be mounted […]

  • 27 January 2013

    Alstom Launches Construction of Its Plants in Saint-Nazaire, France Alstom CEO, Patrick Kron, and Alstom Renewable Power President, Jérôme Pécresse, accompanied Prime Minister, Jean-Marc Ayrault, in Saint-Nazaire, when he officially launched construction works of Alstom’s first two offshore wind turbine factories on Monday 21 January.   Spain: SUPRAPOWER Offshore Wind Turbine on Its Way SUPRAPOWER […]

  • 22 December 2014

    On a bright Sunday morning August 31st around 450 persons gathered in the Felison terminal of the DFDS Seaways in the port of IJmuiden where the Princess Seaways cruise liner was waiting to take them on a day trip to the Eneco Luchterduinen offshore wind farm, Dutch utility Eneco’s second offshore wind farm in Dutch […]

  • 31 January 2017
    Business & Finance

    Since 1 January 2017, the Technical University Delft and all Dutch office and manufacturing locations of the Unilever consumer goods group have been buying electricity generated by the Eneco Luchterduinen offshore wind farm.

  • 18 April 2016
    Grid Connection, Operations & Maintenance, Wind Farm Update

    Rotterdam-headquartered Primo Marine has finalized the Cable Emergency Response Manual for the subsea power cables of the 129MW Luchterduinen offshore wind farm. Primo Marine was commissioned to compile an operational Cable Emergency Response Manual, covering prevention, and preparedness & response in regard to cable emergencies and planned solutions. The main objective was to develop a handbook for […]

  • 5 May 2015

    DEME Joins MEG I Crew DEME Concessions has entered into a partnership with Nordsee Offshore MEG I GmbH to co-develop the MEG I offshore wind farm in the German North Sea last Thursday. Siem Offshore Contractors to Deliver Veja Mate’s Inner Array Grid Siem Offshore Contractors GmbH (SOC), a wholly owned subsidiary of Siem Offshore […]

  • 8 June 2012

    The development of Eneco Luchterduinen Wind Farm (former name: Q10), 23 kilometres off the coast of the municipalities of Noordwijk and Zandvoort, is entering a new phase after completion of the contractor selection process. Van Oord, a leading international contractor specialising in dredging, marine engineering and offshore wind projects, shall be responsible for the foundations […]

  • 3 November 2022
    Environment, R&D, Wind Farm Update

    Four oyster tables made of concrete and other material on which live oysters are placed have been installed at the Eneco Luchterduinen offshore wind farm as part of a mission to restore oyster reefs in the Dutch North Sea. The new oyster table design, which was developed under The Rich North Sea programme by the energy […]