47 results found for 'Les Alizés'

47 results found for 'Les Alizés'
Order results by

A list of search results

  • 30 March 2026
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first preparations ahead of offshore construction work at the OranjeWind project site in the Netherlands have begun, as Jan De Nul has started the filter layer installation campaign. In the coming weeks, the rock installation vessel Simon Stevin will install the first layer of erosion protection, which is essential to enable the subsequent installation […]

  • 11 November 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    All 72 wind turbine foundations at the Danish Thor offshore wind site, developed by RWE, are now equipped with secondary steel and ready for the wind turbine installation, which is expected to start in the spring of 2026. The installation of the secondary steel structures, including boat landings, main access platforms, and internal cassettes, was […]

  • 16 October 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first eight XXL monopile foundations for the 1.1 GW Inch Cape offshore wind farm in Scotland, produced by China’s CNOOD-Wenchong Heavy Industries (CWHI), have arrived in the Port of Leith ahead of the installation work, which will start before the end of the year. CWHI sent off the monopiles on 31 August aboard the […]

  • 25 September 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 72 monopile foundations have been installed at RWE’s Thor offshore wind farm in the Danish North Sea. The monopiles are around 100 metres in length and weigh up to 1,500 tonnes each. The units were shipped from the heavy-lift terminal in Eemshaven, in the Netherlands, to the Thor construction site in the Danish North […]

  • 9 September 2025
    Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has sent away the first batch of six monopiles that will be installed at the 1.1 GW Inch Cape offshore wind farm in Scotland. The first six monopiles have set sail from Dajin Heavy Industry’s Penglai facility, according to the latest social media post by the Chinese company. Dajin cut the first […]

  • 16 July 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Half of the monopile foundations are now in place at the Thor offshore wind farm site, as Jan De Nul’s heavy-lift vessel Les Alizés installed the 36th of the project’s total 72 monopiles on 15 July. “With Thor we are constructing Denmark’s largest offshore wind farm to date. Reaching halfway in the safe installation of […]

  • 4 December 2020
    Vessels

    Jan De Nul and China Merchant Heavy Industry (CMHI) have begun the construction of the 5,000-tonne floating installation crane vessel Les Alizés. Les Alizés is specifically designed for loading, transporting, lifting, and installing offshore wind turbine foundations. It will be capable of building the newest generation of offshore wind farms once delivered in April 2022, […]

  • 26 November 2019
    Vessels

    Jan De Nul has ordered a second mega offshore installation vessel, Les Alizés, from the CMHI Haimen shipyard in China. The new order comes six months after Jan De Nul ordered its first installation crane vessel targeting the largest wind turbines and foundations, the Voltaire. Together with the Voltaire, this new vessel will be capable […]

  • 9 September 2020
    Contracts & Tenders, Vessels

    Red Rock has received an order to supply three knuckle telescopic offshore cranes for Jan De Nul’s floating installation crane vessel Les Alizés. Les Alizés is specifically designed for loading, transporting, lifting, and installing offshore wind turbine foundations. Currently under construction at the CMHI Haimen shipyard in China, Les Alizés will be capable of building […]

  • 6 January 2022
    Vessels

    Jan De Nul has launched its next-generation floating offshore installation vessel Les Alizés at the CMHI Haimen shipyard in China. Les Alizés will be the largest heavy lift vessel in Jan De Nul’s fleet, able to install XXL offshore wind components in floating conditions and with ultra-low emissions, the company said. The launch started on […]

  • 15 September 2020
    Vessels

    Ingeteam has been selected as the electrical system integrator for Jan De Nul’s floating installation crane vessel Les Alizés. Ingeteam is in charge of the engineering, supply, commissioning and sea trials of the complete electrical power system, as well as the alarm monitoring and control system for the vessel. Les Alizés is specifically designed for […]

  • 13 October 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    Ørsted has contracted Jan De Nul for the transport and installation of 107 XXL monopiles and one offshore substation topside at Gode Wind 3 and Borkum Riffgrund 3 offshore wind farms in Germany. Under the final contract signed with Ørsted, Jan De Nul will deploy its new installation vessel Les Alizés for the work. Starting […]

  • 2 June 2023
    Infrastructure, Vessels

    Jan De Nul’s next-generation floating offshore installation vessel, Les Alizés, is getting ready for its first assignment which is to transport and install monopile foundations and an offshore substation topside at Ørsted’s offshore wind farms in Germany. The vessel’s delivery took place some two years after the construction started at the CMHI Haimen shipyard and […]

  • 7 October 2021
    Vessels

    Jan De Nul Group has selected Remazel for the delivery of a fully automated monopile installation system for its new floating installation vessel Les Alizés, which will handle and install XXL monopiles. The system is tailor-made for the new vessel and ideally suited to work in challenging weather conditions at sea, according to Jan De […]

  • 3 June 2022
    Technology, Vessels

    The Norway-based company OSC AS (previously known as Offshore Simulator Centre) will build a high-end simulator for Jan De Nul’s two next generation offshore wind installation vessels, Voltaire and Les Alizés. The crane simulator will be a digital twin, based on real physics and the actual vessel models, enabling Jan De Nul to train its […]

  • 17 April 2020
    Vessels

    German propulsion supplier SCHOTTEL will deliver a full propulsion package for Jan De Nul’s new offshore installation vessel Les Alizés.

  • 19 January 2023
    Vessels

    Jan De Nul’s next-generation floating offshore installation vessel, Les Alizés, sailed out of the China Merchants Heavy Industry’s (CMHI) Haimen shipyard in China on 19 January and is now on its way to Europe, where it will debut on Ørsted’s offshore wind farms in Germany. The CMHI shipyard delivered the vessel to Jan De Nul on […]

  • 4 May 2020
    Vessels

    China Merchant Heavy Industry (CMHI) has ordered 6 × MAN 12V32/44CR main engines for Jan De Nul’s 5,000-tonne floating installation crane vessel Les Alizés. Les Alizés will be built at CMHI’s shipyard in Jiangsu province, eastern China, and is scheduled for delivery in 2022. Lex Nijsen, Head of Four-Stroke Marine Sales – MAN Energy Solutions, […]

  • 27 February 2025
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Jan De Nul will deploy its heavy-lift vessel Les Alizés for the monopile installation at the Inch Cape offshore wind farm in Scotland. The company was announced as one of the project suppliers at the beginning of this year as ESB and Red Rock Renewables reached financial close on the 1,080 MW Inch Cape project. […]

  • 12 June 2023
    Contracts & Tenders, Infrastructure, Operations & Maintenance, Vessels, Wind Farm Update

    Jan De Nul Group has signed an agreement with RWE for the long-term chartering of two next-generation installation vessels for future offshore wind foundation and turbine construction. The charters are supported by a Service Agreement through which Jan De Nul will provide both in-house and market solutions and services, to support and perform installation campaigns […]

  • 31 January 2022
    Vessels

    Jan De Nul Group has launched the Voltaire, a next-generation offshore jack-up installation vessel for offshore renewables and decommissioning, at the COSCO Shipping Shipyard in Nantong, China. The Voltaire will be the second and the largest jack-up vessel in Jan De Nul’s fleet. The jack-up is due for delivery in the second half 2022, the […]

  • 7 August 2023
    Vessels, Wind Farm Update

    Jan De Nul Group’s newest crane vessel, Les Alizés, has kicked off its maiden assignment by installing the first of 107 monopile foundations at Ørsted’s Gode Wind 3 and Borkum Riffgrund 3 offshore wind farms in Germany. Delivered in early 2023, Les Alizés arrived in the Dutch Eemshaven at the end of June, where the […]

  • 12 June 2023
    Infrastructure, Vessels

    Jan De Nul Group has awarded Huisman a contract for the delivery of a 3,500mt Monopile Spreader Bar that will be equipped on Jan De Nul’s two next-generation installation vessels. The Spreader Bar will support and optimise the installation of offshore wind turbines since it is able to handle monopiles with the largest diameter and […]

  • 30 April 2021
    Vessels

    Jan De Nul and China Merchant Heavy Industry (CMHI) have laid the keel for floating installation crane vessel Les Alizés. The construction of the heavy-lift crane vessel began in December 2020 at the CMHI Haimen shipyard in China. Les Alizés is specifically designed for loading, transporting, lifting, and installing offshore wind turbine foundations. It will […]

  • 6 July 2021
    Contracts & Tenders, Technology, Vessels

    Jan De Nul has selected Imeca for the delivery of an electrical motion-compensated pile gripper for its new floating installation vessel – Les Alizés. The tailor-made gripper, with an integrated X-Laboratory guidance and survey system, will allow safe and efficient installation of next-generation monopiles with pin-point accuracy, JDN said. The delivery of the gripper delivery […]

  • 5 April 2022
    Jobs & Recruitment, Operations & Maintenance, Vessels

    Bart Gorsse tells about his role as Chief Engineer supervising the building process of the Les Alizés, Jan De Nul’s newest offshore installation vessel in the Navingo Career Podcast. The Les Alizéz is being constructed in China at the moment and is due for delivery in second half of 2022. Bart talks to Coco Kossmann, […]