Search results for: CrossWind

64 results

A list of search results

  • 14 July 2023
    Contracts & Tenders

    CrossWind has awarded Rosetti Marino an Engineering, Procurement, Construction, and Installation and Commissioning (EPCIC) contract for an offshore green hydrogen production and storage plant, located within CrossWind’s Hollandse Kust Noord offshore wind farm in the Netherlands. Rosetti Marino said that the pilot plant, called the Baseload Power Hub and fully integrated into an offshore wind […]

  • 20 October 2023
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The 69th and final Siemens Gamesa SG 11.0-200 DD wind turbine was installed at the 759 MW Hollandse Kust Noord wind farm in the Dutch North Sea on Thursday, 19 October, CrossWind, the owner and developer of the wind farm said. The final turbine’s three 97-metre long blades were lifted into position on Thursday evening, […]

  • 20 June 2023
    Wind Farm Update

    The 759 MW Hollandse Kust Noord offshore wind farm has produced its first green power and delivered it via TenneT’s offshore grid to the Dutch mainland. “We often talk about milestones along a project’s journey, and CrossWind has had a number to date, but to have the wind turbines generating green electricity safely and successfully […]

  • 3 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    66 out of 69 wind turbines have been installed at the 759 MW Hollandse Kust Noord (HKN) offshore wind farm in the Dutch North Sea. The Hollandse Kust Noord offshore wind farm will feature 69 Siemens Gamesa’s SG 11.0-200 DD wind turbines. The first unit was installed in April this year by the jack-up Seajacks Scylla. […]

  • 21 July 2023
    Grid Connection, Wind Farm Update

    Van Oord has completed installing and burying inter-array cables at CrossWind’s Hollandse Kust Noord offshore wind farm in the Dutch North Sea. Van Oord’s cable-laying vessel Nexus and trencher Dig-It, a remotely-operated vehicle operated from Subsea Viking, have installed a web of 69 inter-array cables measuring 140 kilometres in total. The offshore wind farm is […]

  • 9 June 2023
    Wind Farm Update

    Van Oord has equipped foundations at the Hollandse Kust Noord offshore wind farm with secondary steel and installed all inter-array cables, with cable burial and wind turbine installation underway at the 759 MW Dutch offshore wind farm. Offshore installation vessel MPI Resolution has installed all secondary steel and thus completed the wind turbine foundations. Cable-laying […]

  • 1 June 2023
    Grid Connection, Wind Farm Update

    The Hollandse Kust Noord platform has been taken over by the Dutch transmission system operator (TSO) TenneT. After a successful project engineering, procurement, construction, installation, and offshore hook-up, the Hollandse Kust Noord platform take-over is now official by signing off the Taking-Over certificate. In March 2020, TenneT awarded the joint venture Equans-Smulders the contract to […]

  • 14 July 2023
    Environment

    The Crown Estate and the Centre for Environment, Fisheries, and Aquaculture Science (Cefas) have released a report which aims to help stakeholders involved in offshore wind developments better assess the impacts of electromagnetic fields (EMFs) from subsea power cables on the marine environment. According to the Crown Estate, the report should improve the understanding of […]

  • 3 May 2023
    Business development, Environment, Research & Development, Technology

    Dutch geo-data specialist company Fugro has launched the BeWild project, aimed at measuring biodiversity at offshore wind farms. Fugro, together with project partners, will focus on developing methodologies and technologies for remotely collecting environmental DNA (eDNA) samples in the North Sea. The collected data will assess the impact of offshore wind farms on biodiversity and […]

  • 25 April 2023
    Business & Finance, Collaboration, Equipment, Infrastructure, Innovation, Market Outlooks, Outlook & Strategy, Technology, Transition

    Oceans of Energy has been awarded the contract for installing and operating offshore solar farm inside the Hollandse Kust Noord offshore wind park being developed by CrossWind, a joint venture between Shell and Eneco. This is set to be the first offshore solar farm in the world to be connected, installed, and operated within a […]

  • 17 April 2023
    Vessels, Wind Farm Update

    The first of 69 wind turbines has been installed at the 759 MW Hollandse Kust Noord offshore wind project in the Dutch North Sea. The offshore wind farm, located some 18.5 kilometres off the coast of Egmond aan Zee in the Netherlands, is developed by CrossWind, a joint venture between Shell and Eneco. The wind […]

  • 3 April 2023
    Grid Connection, Wind Farm Update

    The Dutch-German transmission system operator (TSO), TenneT, has announced that the grid connection for the 759 MW Hollandse Kust Noord offshore wind farm is ready for commissioning. Now the wind farm’s operator, CrossWind, can connect the 69 Siemens Gamesa’s SG 11.0-200 DD 11 MW wind turbines to the offshore substation located some 20 kilometres off the […]

  • 9 March 2023
    Contracts & Tenders

    Muehlhan Wind Service (MWS) has signed a contract with Siemens Gamesa for pre-assembly work for the Hollandse Kust Noord offshore wind farm, currently being built in the Netherlands by CrossWind, a joint venture of Shell and Eneco. Under the full-scope pre-assembly contract, MWS will be responsible for mechanical and electrical pre-assembly, crane/lifting operations, and the complete […]

  • 20 February 2023
    Technology, Wind Farm Update

    CrossWind, a joint venture between Shell and Eneco developing the 759 MW Hollandse Kust Noord wind farm off the Netherlands, has signed a contract with Elogen, a Gaztransport & Technigaz (GTT) group company, to design and manufacture a Proton Exchange Membrane (PEM) electrolyser with a power of 2.5 MW. The electrolyser will convert the green […]

  • 9 February 2023
    Wind Farm Update

    Van Oord has installed the final monopile for CrossWind’s Hollandse Kust Noord (HKN) offshore wind farm at the construction site some 18.5 kilometres off the coast of Egmond aan Zee in the Netherlands. Van Oord, as a Balance of Plant contractor for CrossWind, installed all 70 monopiles at the construction site with the first unit […]

  • 23 January 2023
    Contracts & Tenders, Technology, Wind Farm Update

    CrossWind, a joint venture between Shell and Eneco and the developer of the Hollandse Kust Noord (HKN) offshore wind project in the Netherlands, has ordered a fuel cell system from Canadian company Ballard Power Systems to integrate it into the offshore wind farm, which will use water electrolysis to convert wind power into green hydrogen […]

  • 30 January 2023
    Operations & Maintenance, Vessels, Wind Farm Update

    The first wind turbine parts for the 759 MW Hollandse Kust Noord (HKN) offshore wind project arrived in the Dutch port of Eemshaven last week. The tower sections were transported on the roll on/roll off (Ro-Ro) vessel Rotra Vente, operated by Deugro. The vessel arrived at the port under the agency of Amasus Agency Eemshaven, Delfzijl. […]

  • 27 December 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    SeaMar has been contracted by Van Oord to deploy guard vessels on the 759 MW Hollandse Kust Noord (HKN) offshore wind farm in the Netherlands. The guard vessels are present within the 125 km2 total surface area of the wind farm and are keeping close contact with the coast guard and project teams to secure […]

  • 4 March 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    CrossWind, a consortium of Shell and Eneco, has signed agreements with TenneT for the construction of the offshore grid connection for the Hollandse Kust (noord) wind farm. Located in the Dutch North Sea some some 18.5 kilometres off Egmond aan Zee, the 759 MW Hollandse Kust (noord) and its grid connection are scheduled to be […]

  • 19 April 2021
    Contracts & Tenders, Jobs & Recruitment

    CrossWind has awarded Quanta with a contract to supply personnel to the Hollandse Kust Noord offshore wind project in the Netherlands. Quanta will focus on delivering quality management and inspection professionals for the 759 MW wind farm. “We are delighted to be working with CrossWind on this exciting project and we are looking forward to supplying […]

  • 5 December 2022
    Contracts & Tenders, Environment, Grid Connection, Industry, R&D, Technology, Wind Farm Update

    Houston-headquartered engineering, construction, and services company, KBR, has been awarded a contract to provide engineering services for an offshore energy storage project for CrossWind, a joint venture between Shell and Dutch utility company, Eneco. KBR will perform a front-end engineering design of the baseload power hub (BLPH) for the Hollandse Kust noord wind farm located […]

  • 13 April 2021
    Contracts & Tenders

    The CrossWind consortium has selected ERSG to provide technical personnel for the Hollandse Kust Noord offshore wind project in the Netherlands. As part of the deal, ERSG will provide quality management and inspection manpower for the 759 MW subsidy-free offshore wind farm. “This is a great achievement for the ERSG team, who put together a […]

  • 30 July 2020
    Contracts & Tenders, Vessels, Wind Farm Update

    The CrossWind consortium of Shell and Eneco has selected Van Oord as the Balance of Plant contractor for the Hollandse Kust (noord) offshore wind project. As the Balance of Plant contractor, Van Oord’s activities encompass the engineering, procurement, construction, and installation of the foundations, the inter-array cables, and transportation and installation of the wind turbines. […]

  • 15 April 2021
    R&D, Technology

    Shell, Eneco, CrossWind, Siemens Gamesa, TU Delft, and GROW Foundation have started the work on the Dynamic Wind Farm Flow Control project. This project, focussed on reducing the wake effect by using real-time data, is one of CrossWind’s five innovations expected to contribute to a more constant electricity production at the 759 MW Hollandse Kust […]

  • 18 October 2022
    Contracts & Tenders, Wind Farm Update

    The construction of the 759 MW Hollandse Kust Noord (HKN) offshore wind farm has commenced with the first monopile installed at the site some 18.5 kilometres off the coast of Egmond aan Zee in the Netherlands. The HKN’s monopiles will be installed by Van Oord for which the company was awarded a contract in 2020. […]

  • 30 July 2020
    Wind Farm Update

    The CrossWind consortium has opted for Siemens Gamesa’s SG 11.0-200 DD wind turbines for the 759 MW Hollandse Kust (noord) wind farm in the Dutch North Sea. According to the winning bid submitted by the consortium of Shell and Eneco, the wind farm will feature 69 Siemens Gamesa wind turbines, the Dutch government said. Each […]