ECN (Energy research Centre of the Netherlands) has released results of a test campaign that took place in June 2014 in the Bremerhaven where IHC IQIP, together with other industrial parties, measured the behaviour of monopile foundations under different driving methods in onshore conditions.
Three piles were driven in the soil by hydraulic hammers of IHC IQIP. A novel approach of pile driving has been developed named ‘HiLo’. The principles are simple. Instead of aiming for a small number of blows with high impact energy, the HiLo approach is High frequency driving with Lower energy per blow. This reduces noise level and leads to a reduction of loads in the pile with a limited penalty on the installation time, according to IHC IQIP.
The Energy Research Center of the Netherlands (ECN) has conducted a study to investigate the development of fatigue damage in the pile during the driving operation. Correlations have been found between the measured structural response of the pile and the operational hammer parameters. The gathered insights of the loads during impact driving resulted to a better estimation of the consumed fatigue lifetime of an impact driven pile.
Three different driving strategies have been considered:
- Industry standard procedure: 25 blows / 25 cm penetration.
- IHC recommended driving strategy: 40 blows / 25 cm
- IHC’s new HiLo procedure: 80-120 blows / 25 cm.
The fatigue damage was determined for three tests, comparable to the generic procedures (respectively 22 blows / 25 cm, 40 blows / 25 cm and 95 blows / 25 cm). Compared to the industrial standard procedure, the HiLo installation shows a fatigue damage reduction of up to 89 percent. Compared to the IHC standard recommended driving strategy, the reduction still is 74 percent.
The fatigue damage due to the mean stresses in the pile was not very high in any of the experiments, according to Koen Hermans (ECN), researcher in the project. However, fatigue is much more of a concern when stress concentrations due to local defects, weld beads or other structural details are taken into account. This leads to an increase of up to 40 times the fatigue damage for a stress concentration factor of 3.3; in such a case, application of the HiLo strategy will limit fatigue damage considerably. This leads to a longer lifetime for the installed pile and potentially allows reduction of material used in the pile.
Source: ECN
Photo:
List of related news articles
-
Posted: 24 days ago
IHC IQIP Equipment for Akita-Noshiro OWF Construction
IHC IQIP will deliver equipment for the installation of the wind turbine foundations on the Akita-No...
Posted: 24 days ago -
Posted: 18 days ago
All Moray East Jacket Foundations Installed
The 103rd and final jacket foundation has been installed at the Moray East offshore wind farm site i...
Posted: 18 days ago -
Posted: 2 months ago
BLUE Piling Technology Enters New Testing Phase
IQIP and Delft University of Technology have started their joint work on the monopile drivability in...
Posted: 2 months ago -
Posted: 23 days ago
First Fécamp Gravity-Based Foundation Starts Taking Shape
The construction of the first concrete gravity-based foundation for the Fécamp offshore wind farm ha...
Posted: 23 days ago