Buckie Harbour Readies For Beatrice Export Cable Trenching Team

The Manu-Pekka dredger. Source: Boskalis

The two vessels contracted to carry out the trenching along the export cable route for the Beatrice offshore wind farm project are expected to arrive in the Buckie harbour in Scotland this weekend and start mobilising for the project.

The 160ft Manu-Pekka dredger barge is expected to berth on Sunday along with the 88ft BKM 103 multicat tug.

The Finnish-built barge has no propulsion and is towed between work locations by the tug.

The vessels will spend two to three weeks in Buckie while general maintenance work is carried out and new equipment is fitted before beginning work in the Moray Firth.

There they will spend around three months excavating a subsea trench which will carry transmission cabling from the site of the Beatrice wind farm situated 35 miles offshore from Buckie.

The power cables will make landfall to the west of Portgordon from where they will be connected to the new electricity substation currently under construction at Blackhillock, near Keith.

Nexans is supplying the cables under a turnkey contract, worth approximately EUR 245 million, which will see the company manufacture and deliver two complete 220 kV export cable circuits of 90 kilometres, with a total of 260 km of onshore and offshore cables. The offshore cables will be laid by the company’ cable laying ship, C/S Nexans Skagerrak, and trenched for seabed protection by the company’s Capjet system.

Buckie is the largest of Moray Council’s six harbours and is seen as having an important role as a support and maintenance base for the offshore renewables industry.

“The council continues to support offshore work by offering Buckie harbour as a strategic location for a range of services,” a council spokesman said.

“This latest opportunity is part of ongoing partnership working with the offshore sector and we will continue to expand and develop the services that we are able to offer.”

Offshore construction works in the Outer Moray Firth started in late March with the heavy lift vessel Stanislav Yudin installing the foundation piles at the site.

The 588MW wind farm will comprise 84 Siemens 7MW turbines.

Developed by a joint venture partnership between SSE (40%), Copenhagen Infrastructure Partners (35%) and SDIC Power (25%), the wind farm is expected to become fully operational in 2019.

Share this article

Follow Offshore Wind

Events>

<< Jul 2017 >>
MTWTFSS
26 27 28 29 30 1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31 1 2 3 4 5 6

CWP2017 Conference

CWP Conference includes the policy and market forums, the entrepreneur forums and the technology forums…

read more >

HUSUM Wind 2017

The new concept for HUSUM Wind 2015, with the focus specifically on the important German core market, has proven to be a complete success…

read more >

Digital Data Integration & Management

From SCADA to Asset Optimization Increasing turbine efficiency through sophisticated data management and control The conference Digital Data Integration and Management will take place in Bremen from 26 – 28 September, 2017. The topics to be covered include, but are not limited to, LiDAR and SCADA data, control systems, conditional monitoring and digital infrastructure. In […]

read more >

FwP Atlantic Forum 2017

The event is being held during the tenth edition of Sea Tech Week, an international week devoted to marine science and technology, organised…

read more >

Jobs>

Offshore wind jobs at Shell Netherlands BV

Commercial Lead New Energies, Offshore Wind Operations Lead and Wind Turbine Engineer.

apply

Network Support Engineer

As Network Support Engineer you will be responsible for the installation / configuration, operation and maintenance of the infrastructural network ...

apply

Commercial Manager - Liverpool based with some travel

As the Commercial Manager you can expect a variety of responsibilities. The principle focus will be the commercial management of the Bibby WaveMaster1 vessel...

apply

Vessels>