2774 results found for 'hywind tampen'

2774 results found for 'hywind tampen'
Order results by

A list of search results

  • 2 March 2022
    Wind Farm Update

    The first turbine nacelles for the 88 MW Hywind Tampen wind farm arrived at the Wergeland Base in Gulen in western Norway, Equinor, the developer of what will be the largest floating wind farm in operation, said. The wind farm’s 11 Siemens Gamesa 8 MW turbines will be assembled here and towed to the installation […]

  • 16 October 2020
    Contracts & Tenders, Wind Farm Update

    Norwegian engineering company Goodtech has won a contract with Wood for the delivery of a complete SCADA system for Equinor’s Hywind Tampen floating offshore wind farm. Goodtech will deliver a complete SCADA system to the offshore wind field, including the implementation of Equinor’s “Motion Control” system that ensures optimal production from the field through continuous […]

  • 14 October 2022
    Vessels, Wind Farm Update

    Equinor has extended a contract with Island Offshore Shipholding LP for Island Clipper, a combined platform supply vessel (PSV) and walk-to-work (W2W) vessel, which has supported the company’s Oseberg oil and gas field in Norway and is scheduled to also work on the Hywind Tampen floating offshore wind farm. The developer has extended the contract […]

  • 16 February 2021
    Contracts & Tenders

    Kværner has selected German engineering company Dominion for the design, supply, and supervision services for the slipform systems that will erect the concrete wind towers for the Hywind Tampen floating wind project. Dominion said its cylindrical and conical sets of slipform systems can be used multiple times and include hydraulic jacking system, formwork material, yokes […]

  • 17 April 2020
    Contracts & Tenders

    Kvaerner ASA has awarded Scana Offshore with a contract for the supply of mooring equipment for the Hywind Tampen floating offshore wind project in Norway. Scana Offshore will deliver 33 hull brackets, used to attach anchoring lines to the hulls on the project’s 11 turbines, and will provide ROV tools for possible replacement of the […]

  • 11 December 2019
    Wind Farm Update

    Wood has been awarded a new contract by Equinor to deliver modifications to two offshore installations in the Norwegian North Sea to connect electric power from the Hywind Tampen floating wind farm. Equinor’s project replaces energy generated by gas turbines with electricity from the 88MW  floating wind farm located between the Snorre and Gullfaks fields. […]

  • 31 October 2019
    Contracts & Tenders

    Following the award of a contract for the Hywind Tampen project, Kvaerner has joined forces with DOF Subsea to deliver marine operations for the floating wind farm in Norway. Kvaerner’s contract for the Hywind Tampen project is worth about NOK 1.5 billion (approx. EUR 146 million). In addition to engineering, procurement, and construction of the […]

  • 19 May 2023
    Operations & Maintenance, Wind Farm Update

    The final inter-array cable loadout has been completed for Equinor’s Hywind Tampen, the world’s largest floating offshore wind farm in operation. The remaining eleven kilometres of 630mm2 dynamic cabling including accessories were loaded onto the Normand Vision, a construction support vessel (CSV) from Ocean Installer, the company in charge of installing inter-array cables on the […]

  • 16 June 2023
    Wind Farm Update

    Dutch heavy lift and transportation specialist Mammoet has shared a video describing the company’s involvement in the construction of Equinor’s Hywind Tampen, the world’s largest floating offshore wind farm in operation. The 11-turbine Hywind Tampen is also the first wind farm in the world that is supplying electricity to oil and gas platforms. The 88 […]

  • 22 April 2021
    Wind Farm Update

    Aker Solutions has completed the first part of the construction of concrete foundations for the Hywind Tampen floating wind project at its yard in Stord, Norway. The 11 substructures are currently being towed to Vindafjord where the rest of the slip-forming and mechanical outfitting will be completed. Aker built the first 20 meters of the […]

  • 26 March 2020
    Contracts & Tenders, Wind Farm Update

    Equinor has awarded the offshore and engineering consultancy, Global Maritime, with a contract to provide Marine Warranty Survey services for the Hywind Tampen floating offshore wind project in the Norwegian North Sea. The project is still awaiting PUD approval but the intention is to start soon with the main offshore campaigns planned for 2022, Global […]

  • 16 October 2019
    Authorities, Wind Farm Update

    Equinor and the Snorre and Gullfaks partners have submitted updated development plans to the Norwegian government for the Hywind Tampen floating wind farm. The Hywind Tampen floating offshore wind farm will consist of 11 8MW wind turbines located some 140 kilometres from shore in 260-300 metres of water between the Snorre and Gullfaks oil and gas platforms. Equinor and […]

  • 7 June 2022
    Wind Farm Update

    The first of the 11 Siemens Gamesa 8.6 MW wind turbines that will make up Equinor’s Hywind Tampen floating wind farm has been installed at the construction site some 140 kilometres offshore the Norwegian coast. The turbine had sailed away last week from the Wergeland’s base in Gulen in western Norway where it was assembled. […]

  • 7 January 2021
    Contracts & Tenders

    Aker Solutions has awarded Granada Material Handling with a contract to supply eleven davit crane units for use at the Hywind Tampen floating offshore wind project in Norway. The company will design, supply, third party certify and commission 11 individual crane units. Granada said that each of its Python crane units has been specifically designed […]

  • 19 February 2021
    Wind Farm Update

    Aker Solutions has begun the construction of concrete hulls that will carry the turbines at the Hywind Tampen floating offshore wind farm in Norway. Aker began the concrete slip-forming in Stord this week, of which there will be a total of almost 1.2 kilometers. Hywind Tampen will comprise 11 Siemens Gamesa 8 MW turbines installed […]

  • 14 November 2022
    Wind Farm Update

    First power has been produced from the first turbine at Equinor’s Hywind Tampen floating offshore wind farm in the Norwegian part of the North Sea. The power from the first turbine, which was installed in June, was delivered to the Gullfaks A platform in the North Sea on 13 November. The Hywind Tampen floating offshore […]

  • 8 January 2021
    Contracts & Tenders

    VSL, a subsidiary of Bouygues Construction, will carry out post-tensioning works on the eleven floating concrete hulls for the Hywind Tampen floating wind turbines under a contract with Kværner, the EPCI contractor for the project. The company will perform the post-tensioning works of the semi-submersible concrete structures, which will require installation of vertical post-tensioning tendons […]

  • 26 April 2019
    Contracts & Tenders, R&D, Wind Farm Update

    DEME Offshore has signed an agreement with Equinor to carry out a study examining potential floating concrete substructures for the planned Hywind Tampen floating wind farm in the Norwegian North Sea. The agreement was signed early December 2018 with a five-month duration, and the study is a part of the engineering works before the final investment […]

  • 29 April 2022
    Wind Farm Update

    After sending off the first tower sections for the Hywind Tampen wind turbines from its Bilbao factory at the beginning of March, Haizea Wind Group is nearing completion of its part of the project with eight towers manufactured so far. The 8-metre-diameter towers, the world’s largest in this respect, will support the eleven Siemens Gamesa 8 […]

  • 15 April 2022
    Ports & Logistics, Wind Farm Update

    The towing of 11 concrete SPAR-type floating foundations for the 88 MW Hywind Tampen offshore wind farm from Dommersnes to the assembly site in Gulen, Norway, has started. The concrete foundations will support the 11 Siemens Gamesa 8 MW wind turbines. The wind turbines will be fully assembled at the Wergeland Base in Gulen prior […]

  • 21 April 2023
    Contracts & Tenders, Wind Farm Update

    The Dutch offshore access provider, Ampelmann, has revealed that the company will deploy a second E1000 gangway to assist with the construction of Equinor’s Hywind Tampen, the first commercial floating wind farm in Norway. An E1000 gangway was fitted to the offshore subsea construction vessel (OSCV) Siem Barracuda in early December and within the next […]

  • 21 January 2021
    Contracts & Tenders

    Kongsberg Maritime has secured a contract with Wood to supply positioning and monitoring equipment for the Hywind Tampen floating offshore wind farm. Kongsberg will supply its DPS position reference system and Motion Reference Unit (MRU) for what will be the world’s largest floating offshore wind farm. The DPS exploits all available GNSS infrastructure to deliver […]

  • 2 July 2019
    Business & Finance

    Equinor has met with the supplier industry in Norway to discuss cost-effective solutions for floating offshore wind farms on the Norwegian Continental Shelf. Equinor got together with Global Center of Expertise (GCE) NODE companies in Agder to talk about finding cost-optimal solutions related to designing floating foundations for turbines in the 10-15MW range. Additionally, the meetings were […]

  • 22 July 2022
    Grid Connection, Wind Farm Update

    Subsea 7 has laid the first subsea cables in the water for the 94.6 MW Hywind Tampen floating wind farm offshore Norway. JDR Cable System is in charge of supplying the electric cables for the project from its factory in Hartlepool, the UK, while Subsea 7 is responsible for the installation of the cables and […]

  • 25 March 2022
    Ports & Logistics, Wind Farm Update

    Offshore construction on the 88 MW Hywind Tampen floating wind farm is set to start next week with the transport and installation of the suction anchors at the site located about 140 kilometres off the Norwegian coast, DOF Subsea said. The subsea AHTS vessel Skandi Skansen and the DOF Subsea team are currently preparing to […]

  • 14 November 2019
    Contracts & Tenders, Grid Connection

    JDR Cable Systems has secured a contract with Equinor to provide inter-array and export cables for the Hywind Tampen floating offshore wind project in Norway. JDR will design and manufacture eleven 66kV dynamic inter-array cables and two static export cables, each equipped with a JDR-designed breakaway system and a range of cable accessories for delivery […]