181 results found for 'sofia'

181 results found for 'sofia'
Order results by

A list of search results

  • 25 June 2020
    Wind Farm Update

    Fugro has commenced the final phase of the pre-construction site investigation at innogy’s Sofia offshore wind project in the UK. Jack-up vessel Haven Seariser 2 will work in the nearshore area between Redcar and Marske-by-the-Sea from this week to conclude the six-month offshore site investigation. The 29-meter vessel will carry out borehole surveys for approximately a […]

  • 7 February 2020
    Wind Farm Update

    Site investigations have kicked off at innogy’s Sofia offshore wind project in the UK with export cable route surveys.

  • 22 June 2020
    Wind Farm Update

    Siemens Gamesa has signed a preferred supplier agreement with innogy to deliver 100 of its new SG 14-222 DD turbines for the Sofia offshore wind project in the UK. The Sofia project will, therefore, be the first European project to install the 14 MW model that will be market-ready by 2024, on time for installation at the […]

  • 16 June 2022
    Business & Finance, Contracts & Tenders

    Siemens Gamesa Renewable Energy, the supplier of wind turbines for the 1.4 GW Sofia offshore wind farm in the UK, and Cadeler, the company who will install them, will hold a supply chain event on 7 July to showcase contracting opportunities for the project. At the event, the companies will provide a high-level look at […]

  • 24 September 2021
    Grid Connection, Wind Farm Update

    Sembcorp Marine and RWE have marked the start of the fabrication of the offshore converter platform for the 1.4 GW Sofia offshore wind farm with an official steel-cutting ceremony at Sembcorp Marine’s yard in Batam, Indonesia. “The offshore converter station sitting at the heart of the wind farm will be one of the most powerful […]

  • 21 May 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Van Oord’s offshore installation vessel, Aeolus, has installed the first of 100 monopile foundations at the 1.4 GW Sofia project in the UK, RWE’s largest offshore wind farm to date. The Sofia offshore wind farm is located on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK. […]

  • 12 April 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Heerema Marine Contractors has secured a contract with Singapore’s Sembcorp Marine to transport and install the HVDC offshore converter platform for the Sofia offshore wind farm in the UK. The platform will be fabricated at Sembcorp Marine’s yard, while Heerema’s semi-submersible crane vessel Sleipnir is expected to carry out the offshore installation in 2024. Located at […]

  • 8 September 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Iv-Offshore & Energy b.v. has signed the main contract with Sembcorp Marine Integrated Yard Pte Ltd (SMIY) to supply engineering and procurement services for the high voltage direct current (HVDC) offshore converter platform of RWE’s Sofia offshore wind farm. Sofia offshore wind farm, located off the northeast coastline of the UK, will have a capacity […]

  • 10 April 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The installation of foundations is scheduled to kick off this month at the Sofia offshore wind farm site, located on Dogger Bank in the central North Sea, 195 kilometres from the nearest point on the UK’s northeast coast. Van Oord’s offshore wind installation vessel Aeolus and special service support vessel (SSSV) Baltic Explorer are expected […]

  • 4 October 2019
    R&D

    Geotechnics Ltd has carried out onshore cone penetration tests for innogy’s Sofia offshore wind farm in the UK. The work was carried out at Marske-by-the-Sea, Teeside, as part of site investigation works for the project’s onshore export cable route. Sofia, the largest project in innogy’s development portfolio, will comprise up to 200 turbines located 165km off the UK’s North […]

  • 28 June 2022
    Contracts & Tenders, Grid Connection

    France-headquartered electricity transmission consultancy and engineering company, RTE international, has been appointed as third-party consultant to conduct joint interaction studies between two HVDC projects in the UK: Sofia Offshore Wind Farm and Dogger Bank C. Under the contract, RTE international will carry out wide-ranging interaction studies to ensure the connection of both projects to the […]

  • 20 July 2020
    Business & Finance, Contracts & Tenders

    RWE has launched an online suppliers portal where companies can search for and find opportunities on the Sofia offshore wind project. The suppliers portal will display contract opportunities with the Sofia project and its key contractors as they become available. “We are keen to maximise the involvement of UK companies as the project progresses, particularly […]

  • 18 February 2022
    Contracts & Tenders

    UK-based engineering and construction company J. Murphy & Sons (Murphy) has been awarded a multi-million-pound contract for onshore civil works on the export cables for both the 1.4 GW Sofia offshore wind farm and 1.2 GW Dogger Bank C. Although the two large-scale offshore wind farms are being built by different developers, RWE (the owner of […]

  • 29 July 2020
    Wind Farm Update

    Fugro is set to deploy metocean equipment to support the planning of the export cable laying operations at the Sofia offshore wind project in August. Diving support vessel Curtis Marshall will be used for the work scheduled to begin on or around 3 August. The equipment will be deployed for a period of between six […]

  • 10 December 2020
    Contracts & Tenders, Wind Farm Update

    RWE has selected Van Oord as the preferred supplier for the engineering, procurement, construction and installation (EPCI) of monopile foundations and array cables for the 1.4 GW Sofia offshore wind project in the UK. Van Oord will deploy its offshore installation vessel Aeolus to install the 100 TP-less monopile foundations and the cable-laying vessel Nexus […]

  • 11 June 2021
    Wind Farm Update

    RWE has begun construction of its 1.4 GW Sofia offshore wind farm, the largest project currently in construction across the company’s entire renewables fleet. The official construction will start with onshore activities, which are also known as enabling works. UK firm Jones Bros Civil Engineering UK has been contracted to carry out the work. These […]

  • 27 May 2021
    Contracts & Tenders, Grid Connection

    RWE has selected France-based RTE International as the technical consultant for HVDC systems at the 1.4 GW Sofia offshore wind farm in the UK. RTE International will assure the technical quality of the HVDC components for the entire work site. The electricity generated by the offshore wind farm will be transported to the UK grid […]

  • 12 May 2020
    Wind Farm Update

    Four survey vessels are ready to commence site investigations at the Sofia offshore wind project site off the UK’s North East coast. The surveys are part of a six-month site investigation campaign for innogy’s 1.4 GW project that started in February. The multi-purpose vessel Despina and survey vessel Fugro Scout will carry out geotechnical surveys […]

  • 9 July 2020
    Grid Connection, Wind Farm Update

    RWE has selected a consortium of GE Renewable Energy’s Grid Solutions and Sembcorp Marine to provide the electrical transmission system for the 1.4 GW Sofia offshore wind project in the UK. As the consortium leader, GE Grid Solutions will be responsible for the engineering, procurement, construction and installation of two HVDC converter stations. The offshore […]

  • 18 December 2023
    Contracts & Tenders, Equipment, Supply Chain

    Norway-headquartered Glamox has won a contract from Dutch engineering company, Bakker Sliedrecht, to provide specialist marine LED lighting for the foundation platforms for 100 14 MW wind turbines for the Sofia offshore wind farm in the UK. For the Sofia offshore wind farm, Glamox will provide 800 marine-certified LED luminaires, which will illuminate the platforms […]

  • 14 March 2024
    Business & Finance, Fixed-Bottom

    RWE has reported an adjusted EBITDA of nearly EUR 1.7 billion in its offshore wind segment for 2023, compared to EUR 1.4 billion for the previous fiscal year. The increase in earnings is due to the commissioning of new capacity and better wind conditions, according to the company. Electricity generation from renewable energy at RWE rose by […]

  • 1 April 2021
    Contracts & Tenders, Wind Farm Update

    RWE has awarded Van Oord with a contract to carry out the engineering, procurement, construction, and installation (EPCI) of the monopile foundations and the inter-array cables for the 1.4 GW Sofia offshore wind farm. Sofia is sited on Dogger Bank in the central North Sea, 195 kilometres from the North East coast of the UK. […]

  • 19 August 2024
    Business & Finance, Fixed-Bottom, Foundations, Supply Chain

    Japan-based Sumitomo Corporation has acquired an equity stake in EEW Offshore Wind Holding, one of three new holding companies EEW Group founded to organise its business more efficiently, according to the German foundation manufacturer. According to EEW Group, Sumitomo’s stake has been in commercial effect since 1 July. The Group said on 19 August that, […]

  • 20 March 2020
    Wind Farm Update

    Fugro has completed the first tranche of offshore site investigations at innogy’s Sofia offshore wind project in the UK. The first tranche is complete with the multi-purpose vessel Fugro Pioneer having finished the geophysical survey of the wind farm’s export cable corridor. According to innogy, the vessel will be back to carry out more survey […]

  • 9 May 2023
    Contracts & Tenders

    Specialist Marine Consultants (SMC) has signed a contract to deliver Offshore Resources and Services for RWE’s 1.4 GW Sofia offshore wind farm during the project’s offshore construction which is scheduled to commence this year. SMC will deliver a turnkey package comprising a range of services, including above-water offshore balance of plant works which includes statutory […]

  • 18 January 2024
    Equipment, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    NOTE: The article was amended on 23 January to include the parts of Dogger Bank Wind Farm’s Supporting Statement filed to the Marine Management Organisation (MMO) that concern the reasons for the delay of the monopile installation on Dogger Bank B. The installation of foundations on two UK offshore wind projects, the 1.4 GW Sofia […]