Search results for: Amrumbank West

107 results

A list of search results

  • 27 June 2016

    Saft has supplied its Uptimax nickel battery systems for E.ON’s Amrumbank West offshore wind farm. Saft has provided a total of 80 Saft Uptimax battery systems – one for each turbine. In the event of an interruption to the main power supply, the batteries are designed to deliver peak power for essential safety systems for […]

  • 8 April 2014
    Wind Farm Update

    DBR Generatorsets has successfully completed commissioning and start-up of its custom-built auxiliary power package for E.ON’s Amrumbank West wind farm substation. DBR delivered and installed two 1,250kVA diesel generator sets and one 250kVA set. Cofely Fabricom is assembling the topsides at its Hoboken, Belgium yard before installation in the German Bight. “This was a challenging […]

  • 12 May 2014
    Grid Connection, Wind Farm Update

    Avantha Group Company CG installed its transformer substation at the Amrumbank West offshore wind farm. The renewable energy unit consists of 80 multi-megawatt wind turbines located 100 km off the German coast in the North Sea. The Amrumbank West offshore wind farm (which was completed along with CG’s consortium partners Fabricom GDF Suez, Iemants and […]

  • 25 November 2015

    Offshore Marine Management (OMM) has completed a contract with Aggreko to support temporary power supply during construction of Amrumbank West Offshore Wind Farm in Germany.  The contract saw OMM provide vessel management services as well as personnel and offshore logistical support, whereas Aggreko provided offshore modified hardware and offshore certified generator engineers. Thomas Schmerz, Sector […]

  • 29 March 2012
    Grid Connection

    Siem Offshore Contractors GmbH (“SOC”), a wholly owned subsidiary of Siem Offshore Inc., announced today that SOC has been awarded the contract for the installation of the inner array grid cables as well as associated services for the Amrumbank West Offshore Wind Farm (“OWF”) project by Amrumbank West GmbH (“AWG”), a subsidiary of E.ON Climate […]

  • 29 May 2013
    Wind Farm Update

    In April 2013 E.ON started preparations for constructing the Amrumbank West offshore wind farm. So-called scour protection is currently being installed north-west of Helgoland. This comprises two layers of special sand bags on the seabed to prevent the sea current from washing away the sand around the foundations of the wind turbines, thus ensuring turbine […]

  • 14 August 2013
    Business & Finance, Wind Farm Update

    E.ON has begun the construction phase of German Amrumbank West offshore wind farm, the company said in its report for the first half of 2013. Installation of foundations at the project’s site is scheduled for this fall (most likely in October). In April, the company started the preparatory work for constructing the offshore wind farm […]

  • 2 September 2013

    From mid-October 2013, E.ON Kraftwerke GmbH will start the construction of the Amrumbank West offshore wind farm via the offshore base port of Cuxhaven. The wind farm, located northwest of Helgoland, will comprise 80 Siemens’ 3.6 megawatt (MW) offshore wind turbines and will have a capacity of 288 MW. The main components of the foundation […]

  • 11 September 2014
    Business & Finance, Operations & Maintenance, Technology, Wind Farm Update

    Cuxport has been supporting the Dutch company Ballast Nedam Offshore in the use of an alternative technique to transport and install monopiles at the “Amrumbank West” wind park on behalf of E.ON since the middle of August. The foundation piles are no longer just transported to the offshore site on board the setup vessel, but […]

  • 30 September 2013
    Business & Finance

    On September 26th, Euskalforging received an order for 43 TP flanges for the Luchterduinen offshore wind farm. A record of 615 TP and MP flanges will be supplied by Euskalforging this year. Reported projects (TP and MP flanges) gained during 2013 by Euskalforging are: Dan Tysk, Amrumbank West, Humber Gateway, and Baltic 2. [mappress] Press […]

  • 5 December 2016

    CWind has completed inspections of monopiles, scour protection and cables at a number of locations at E.ON’s Amrumbank West offshore wind farm off the coast of Germany. To carry out the survey, CWind deployed a V8 Ocean Modules Inspection Class ROV from one of its vessels. The ROV was fitted with a super high definition […]

  • 19 November 2020
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Deutsche Bahn (German Rail) and RWE Supply & Trading have signed a 15-year power purchase agreement (PPA) for electricity produced at the Amrumbank West offshore wind farm. The PPA will begin in 2024 and run until 2039. The 288 MW Amrumbank West is located around 30 kilometres off the coast of Heligoland in the German […]

  • 27 April 2012
    Wind Farm Update

    E.ON has decided to base its operations and maintenance centre for its 288MW Amrumbank West offshore wind farm on the German island of Helgoland. E.ON’s Head of International Offshore business, Sven Utermöhlen, and Jörg Singer, the Mayor of Helgoland, met at the region’s economics ministry in Kiel to sign an agreement to use several plots […]

  • 16 December 2011

    Siemens Energy has received another large order to build an offshore wind power plant in Germany. For the Amrumbank West project in the North Sea, the company is supplying 80 wind turbines, each with an output of 3.6 megawatts (MW) and 120 meter diameter rotor. The customer is Amrumbank West GmbH, a subsidiary of E.ON […]

  • 25 November 2013

    Peter Madsen Rederi A/S has completed work on Amrumbank West Offshore Wind Farm in the North Sea. The Danish company has laid 45,000 sand bags around wind turbine foundations to prevent scour forming which would destabilise the foundation. The bags were filled with 60,000 tons of dredged sand, which were laid in a period of […]

  • 16 December 2011

    This calendar year, Siemens won six contracts for offshore wind farms with a total capacity of about 1.4 gigawatts (GW) – enough to supply clean electricity to more than 1.4 million homes. The latest success was the award of the Amrumbank West project in the North Sea, for Amrumbank West GmbH, a subsidiary of E.ON […]

  • 23 October 2016
    Authorities, Business & Finance, Environment, Grid Connection, Operations & Maintenance, R&D, Technology, Training & Education, Vessels, Wind Farm Update

    Elisa Floats Self-Installing Offshore Wind Turbine Researchers gathered around the EU-funded Elisa Project have developed an offshore wind turbine system that can be completely pre-assembled and pre-commissioned in controlled harbour conditions. The Big League Offering Lowest Offshore Wind Prices (Interview with Vattenfall) When you are talking with people working in real estate, there is a […]

  • 1 April 2014
    Wind Farm Update

    Siemens’ HelWin beta jacket was successfully loaded on the barge yesterday at Heerema’s Vlissingen yard. “The next milestone is the sail away to its final offshore destination,” Heerema Fabrication Gruop said. The jacket is part of the HelWin beta converter platform, which is one of the main components of the TenneT DC offshore grid connection […]

  • 30 May 2014

    Euskalforging is supplying the 150 Transition Piece Flange sets (150 TP Lower + 150 TP Top) and 150 Monopile Flanges for the 150 Joint Flange XL Monoplies. Euskalforging is the sole supplier selected for the Flange supply for the innovative Joint Flange XL Monopiles, achieving the demanding mechanical properties. Euskalforging exclusive flange manufacturing process fits […]

  • 27 July 2012
    Grid Connection

    Vattenfall, Swedish power company, will see its DanTysk offshore wind farm connected to the Germany’s power grid with a delay of up to five months, reports Bloomberg. Siemens spokesman Torsten Wolf stated that the link is scheduled for completion by the spring 2014, even though it was planned to be ready by the very start […]

  • 31 January 2014

    VIDEO: Anholt Offshore Wind Farm Construction DONG Energy has constructed the Anholt Offshore Wind Farm, which is one of the largest construction projects in Denmark. Under-Manning and Fatigue Threaten WFSV Safety As offshore wind farm developments move further out to sea and demands on the vessels and crews that service them increase, a rising number […]

  • 14 May 2014
    Business & Finance

    The E.ON Group’s businesses performed as anticipated in the first quarter of 2014. Owing to a continued difficult business and regulatory environment and in the wake of divestments, E.ON’s EBITDA declined by 12 percent year on year to €3.2 billion, its underlying net income by 13 percent to €1.2 billion. By contrast, operating cash flow […]

  • 15 January 2013
    Grid Connection

    Vos Prodect Innovations secures a new contract from Cofely Fabricom sa/nv, for the supply of sealed cable hang-off systems of E.ON’s Amrumbank OWF. The Amrumbank West offshore wind farm is located around 35 km north of the island of Helgoland. It will consist of 80 Siemens wind turbines with a rated output of 3.6 MW […]

  • 15 February 2012

    Mike Winkel, the head of the utility’s clean-energy unit, said that the investment into German offshore wind power could stop after 2015 due to delays in connecting the wind farms to the grid. “No one will be further investing if the network connection is uncertain, neither Eon nor someone else,“ Said Winkel. Tennet will connect […]

  • 11 June 2015
    Vessels, Wind Farm Update

    ITW has completed the last grouting operation at Amrumbank West Offshore Wind Farm in Germany with a high speed efficiency rate. Connections between transition pieces and monopiles have been grouted with ITW’s cementitious material Ducorit® and the installation of the product has been performed by the company’s teams. For the Amrumbank project, which has 80 connections, ITW […]

  • 11 February 2015
    Business & Finance, Vessels, Wind Farm Update

    MPI Adventure has installed the first of eighty Siemens 3.6MW turbines for E.On Renewables’ Amrumbank offshore wind farm, located 35 kilometers to the north of the island of Helgoland.  “We are confident that we will soon be able to feed electricity generated by the first turbines into the public grid as planned,” said Dominik Schwegmann, lead […]