Search results for: vineyard wind

409 results

A list of search results

  • 22 August 2023
    Wind Farm Update

    The first turbine nacelles for the Vineyard Wind 1 offshore wind farm have arrived at the New Bedford Marine Commerce Terminal in Massachusetts, USA. United Heavy Lift transported the first nacelles for Vineyard Wind 1 from France using its UHL Felicity vessel. The offshore wind farm will feature 62 GE Haliade-X 13 MW turbines to be […]

  • 26 May 2023
    Ports & Logistics, Wind Farm Update

    Vineyard Wind, a joint venture between Copenhagen Infrastructure Partners (CIP) and AVANGRID, has received the first shipment of turbine components for GE’s Haliade-X 13 MW turbine at the New Bedford Marine Commerce Terminal in Massachusetts, USA. The tower sections will be constructed at the terminal before being shipped out and installed later this summer, Vineyard […]

  • 13 September 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    The wind turbine installation campaign for the 806 MW Vineyard Wind 1 offshore wind project has begun some 15 miles (approximately 24 kilometres) off the coast of Massachusetts, the US. The installation campaign follows the successful transportation earlier this week of the first GE Haliade-X 13 MW wind turbine from the New Bedford Marine Commerce […]

  • 26 July 2023
    Wind Farm Update

    DEME’s specialised floating installation vessel Orion has installed the offshore substation for the 800 MW Vineyard Wind 1 wind farm, a first in the US, said the Belgium-based company. With a weight of more than 3,500 tonnes, this was the single heaviest lift of the entire construction campaign, according to Vineyard Wind, a joint venture between […]

  • 8 June 2023
    Wind Farm Update

    Offshore works have begun at the 800 MW Vineyard Wind 1 offshore wind farm in the US with the first of 62 foundations installed by DEME’s specialised floating installation vessel Orion. Vineyard Wind 1 is the first commercial-scale offshore wind farm in the country and the first of several US wind farm projects in DEME’s […]

  • 26 May 2023
    Grid Connection, Wind Farm Update

    The offshore substation topside and the jacket foundation for the Vineyard Wind 1 project have left the quay at Bladt Industries’ production site in Southern Denmark heading for its destination 35 miles from mainland Massachusetts, USA. The sail-away is on time according to the original schedule and is a major milestone for the project team […]

  • 7 June 2023
    Wind Farm Update

    The first GE Haliade-X blades for the 800 MW Vineyard Wind offshore wind farm have arrived at the New Bedford Marine Commerce Terminal in Massachusetts, USA. The 107-metre-long blades arrived on the Rolldock Sky heavy load vessel, which is currently docked in the Port of New Bedford, according to the latest AIS data. A couple […]

  • 12 May 2023
    Technology, Wind Farm Update

    Vineyard Wind, a joint venture between Copenhagen Infrastructure Partners (CIP) and Avangrid which is building the first large-scale offshore wind farm in the US, has signed an agreement with the US company ThayerMahan for a pilot programme to deploy and test a secondary bubble curtain during the installation of foundations. A bubble curtain mitigates noise […]

  • 30 May 2023
    Vessels

    Monopile installation work has started at the Vineyard Wind 1 site offshore Massachusetts, the first large-scale offshore wind farm in the US and the Americas. DEME’s installation vessel Orion which, according to AIS data available online, will reach the project site today (30 May), will install the first six monopiles and accompanying transition pieces (TPs) […]

  • 15 June 2023
    Wind Farm Update

    Two 220 kV high-voltage alternate current (HVAC) three-pole submarine cables have been installed for Vineyard Wind 1, America’s first large-scale offshore wind project. Prysmian Group, the supplier of the submarine cables, said that the operations proceed on time with the schedule and that their cable-laying vessel Ulisse is ready to perform submarine cable joints. Prysmian’s […]

  • 7 September 2023
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind, a joint venture between AVANGRID and Copenhagen Infrastructure Partners (CIP), has shipped the first GE Haliade-X 13 MW wind turbine from the New Bedford Marine Commerce Terminal to its location more than 30 miles (about 49 kilometres) off the coast of Cape Cod in the US. The GE Haliade-X 13 MW wind turbine […]

  • 10 August 2023
    Vessels, Wind Farm Update

    DEME’s jack-up installation vessel Sea Installer is on its way to the Vineyard Wind 1 offshore wind farm site, where the vessel will soon install what will be the first wind turbines offshore the US state of Massachusetts. The vessel, which first called the port of Halifax in Canada at the beginning of this month, […]

  • 10 April 2023
    Business & Finance, Grid Connection, Wind Farm Update

    Prysmian’s cable-laying barge Ulisse has resumed cable-laying operations at the first U.S. large-scale offshore wind project, located off the coast of Massachusetts. According to the project’s latest mariner update, cable laying operations of the mid-section cable for the Vineyard Wind 1 project were set to kick off on or about 9 April and continue through […]

  • 4 August 2023
    Wind Farm Update

    The installation of GE’s Haliade-X 13 MW wind turbines at the Vineyard Wind 1 offshore wind project site in Massachusetts is expected to start next week, according to WCVB Channel 5 Boston and other US media who reported on updates shared by Avangrid’s project team during a boat tour of the Vineyard Wind site earlier […]

  • 11 September 2023
    Cables, Fixed-Bottom, Grid Connection, Wind Farm Update

    Cable-laying operations for the inter-array cables are about to begin at the 800 MW Vineyard Wind 1 offshore wind farm in the US. The work, carried by Jan De Nul’s vessel Isaac Newton, will begin with array cable lines five and six. The vessel will remain on-site until early October, said Vineyard Wind, a joint […]

  • 23 June 2023
    Wind Farm Update

    The first monopile foundation has been installed at the South Fork Wind site offshore New York, the state’s first offshore wind farm. The foundation will support the project’s offshore substation, which will also be installed in the coming days. Boskalis’s offshore installation vessel Bokalift 2 is transporting and installing the foundations, including the one for […]

  • 29 March 2023
    Contracts & Tenders

    The Dutch offshore access provider Ampelmann has signed six new contracts in the US offshore wind market for 2023, 2024, and 2025. In the coming year, Ampelmann’s motion-compensated gangway will assist in the hook-up, cabling, and commissioning of turbines on Vineyard Wind and South Fork Wind offshore wind farms, two of the first commercial-scale wind […]

  • 3 April 2023
    Business & Finance, Business development, Equipment, Industry, Infrastructure, Technology

    GE and Siemens Gamesa have resolved their wind turbine technology patent disputes ”in their entirety”, GE said in a statement. ”GE and SGRE have reached an amicable settlement of all their wind turbine technology patent disputes in the United States and Europe on confidential terms and have granted each other and their respective subsidiaries worldwide […]

  • 27 June 2023
    Business & Finance, Operations & Maintenance

    Dublin-headquartered aircraft lessor LCI has started delivering helicopters that will be leased under long-term arrangements to HeliService USA and be used on offshore wind projects. These are the first dedicated offshore wind helicopters in the United States. The offshore helicopter transport provider based in Rhode Island, US, is leasing two AW169 helicopters, one of which […]

  • 27 June 2023
    Grid Connection

    Spain-based Iberdrola has announced that it will help deliver renewable offshore wind power from the Long Island grid to New York City and Westchester County. The company said it will add approximately 90 miles (about 150 kilometres) of new high-voltage transmission lines that will run the distance underground and underwater. The project will be developed […]

  • 16 August 2023
    Wind Farm Update

    Wind turbine components for the South Fork Wind Farm, New York’s first offshore wind farm, have started coming into New London ahead of the installation at the project site that is expected to start later this summer. Ørsted shared photos of the first shipment of wind turbine blades arriving on board United Heavy Lift’s cargo […]

  • 18 May 2023
    Contracts & Tenders, Wind Farm Update

    Iberdrola has signed an agreement with Windar Renovables for the construction of 95 transition pieces for the East Anglia Three offshore wind farm in UK waters. This is the largest order of this type of foundation to date for Windar Renovables and the production will be carried out mainly at the Asturian company’s facilities located […]

  • 18 September 2023
    Ports & Logistics

    Bladt Industries has started work on its new manufacturing facility in Denmark to cater offshore wind substation projects in the pipeline. The Danish company said that major excavation work is underway at its site in Aalborg, Denmark. Together with the Port of Aalborg, Bladt Industries is piloting the foundations that will eventually lay the foundation […]

  • 10 August 2023
    Wind Farm Update

    All 13 monopile foundations have been installed at the South Fork Wind Farm site offshore New York, the state’s first offshore wind farm. Boskalis’s offshore installation vessel Bokalift 2 was responsible for the transporting and installation of the foundations, as well as the one for the substation, the first American-built offshore wind substation. More than […]

  • 22 August 2023
    Floating Wind, Wind Farm Update

    Fred. Olsen Seawind and Vattenfall have revealed that the preliminary geophysical and environmental surveys have been completed for their Muir Mhòr floating offshore wind farm in Scotland. With marine survey services provider EGS International mobilising survey work on the EGS Ventus in April 2023, the four-month campaign was completed in early August. Utilising high-spec marine […]

  • 27 July 2023
    Wind Farm Update

    The first American-built offshore substation has been installed at the South Fork Wind site offshore New York, the state’s first offshore wind farm. The 1,500-tonne, 60-foot-tall offshore substation was built by Kiewit Offshore Services, the largest offshore fabricator in the US, at its Ingleside facility near Corpus Christi, Texas. The substation departed from the facility […]