373 results found for 'saint-nazaire'

373 results found for 'saint-nazaire'
Order results by

A list of search results

  • 19 January 2026
    Fixed-Bottom, Foundations, Grid Connection, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    Smulders has been awarded an engineering, procurement and construction (EPC) contract for the jacket foundation that will support the offshore substation of the 600 MW Dunkerque offshore wind farm in France. Final assembly and delivery of the jacket will take place at Smulders’s French yard in Fos‑sur‑Mer, the company said via social media. French transmission […]

  • 14 April 2026
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    RWE has completed the installation of two offshore substations at its Nordseecluster A wind farm site in the German North Sea. The platforms, each around 40 metres long and 22 metres high, were manufactured by Chantiers de l’Atlantique at its yard in Saint-Nazaire, France, and were placed onto their foundations by Scaldis using its floating […]

  • 8 April 2026
    Business development, Environment, Fixed-Bottom, Floating Wind, Foundations, Industry, Innovation, Offshore Platforms, Supply Chain, Technology

    Chantiers de l’Atlantique, EDF power solutions, Heerema Marine Contractors, Menck, RTE, Sealence and Smulders have formed the Searénité consortium to develop a dedicated solution designed to limit underwater noise generated during offshore construction, particularly for floating wind and substation foundations. While noise mitigation systems already exist, the Searénité consortium says it aims to introduce advanced […]

  • 10 February 2026
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Chantiers de l’Atlantique has completed the construction and integration of two offshore electrical substations for the 660 MW Nordseecluster A offshore wind farm, currently under construction off the German coast. Each of the topsides is approximately 40 metres long and 22 metres high, with one weighing about 1,800 tonnes, while the other one comes in […]

  • 31 May 2021
    Ports & Logistics, Vessels, Wind Farm Update

    The first shipment of wind turbine blades for the Saint-Nazaire offshore wind farm has arrived in France. United Wind Logistics’ module deck carrier Vestvind arrived at the Nantes Saint-Nazaire Port loaded with six sets (18 units) of wind turbine blades. The 480 MW Saint-Nazaire offshore wind farm, also known as Parc du Banc de Guérande, […]

  • 8 June 2021
    Ports & Logistics, Wind Farm Update

    The first turbine nacelles for the Saint-Nazaire offshore wind farm have arrived by sea at the Nantes-Saint-Nazaire Port. The first GE Haliade 150-6MW nacelles made a short trip from GE Renewable Energy’s nacelle assembly plant in Montoir-de-​Bretagne to the Nantes-Saint-Nazaire Port earlier this week. Some of the nacelles for the project reached the wind turbine […]

  • 7 April 2022
    Ports & Logistics, Vessels, Wind Farm Update

    Jan De Nul’s jack-up Vole au vent has left the Nantes-Saint Nazaire Port loaded with the first set of GE Haliade wind turbine components to be installed on the 480 MW Saint-Nazaire – France’s first commercial-scale offshore wind farm. Vole au vent is transporting the first four sets to the installation site between 12 and […]

  • 13 August 2021

    The jacket foundation and the topside of the Saint-Nazaire offshore substation are scheduled to depart from the Nantes Saint-Nazaire Port to the installation site in the coming several days. The jacket foundation will leave the Nantes Saint-Nazaire Port on Saturday, 14 August. The topside will follow soon and set off in the evening hours of […]

  • 3 June 2025
    Business & Finance, Project Updates, Wind Farm Update

    The French government and three offshore wind farms have signed amendments to their power purchase agreements (PPAs), allowing them to halt production during periods of negative electricity prices. The three wind farms that signed PPAs are the 500 MW Fécamp, the 480 MW Saint-Nazaire, and the 496 MW Saint-Brieuc. According to the Ministry of Economics, […]

  • 12 March 2020
    Contracts & Tenders, Wind Farm Update

    Tekmar Energy Limited has won a contract from French cable installation specialist Louis Dreyfus TravOcean to supply TekLink® cable protection systems (CPS) for the Saint-Nazaire offshore wind farm in France. Saint-Nazaire is a 480MW offshore wind farm set for construction off France’s Atlantic Coast and owned by EDF Renewables and Enbridge. It will be the […]

  • 16 February 2021
    Wind Farm Update

    The first nacelle for a GE Haliade 6 MW wind turbine for the French Saint-Nazaire offshore wind farm has arrived at the project’s pre-assembly site in the Port of Saint-Nazaire. The nacelles are being produced in GE Renewable Energy’s factory in Montoir-de-Bretagne, from where the next units will be sent off to the wind turbine pre-assembly […]

  • 20 April 2022
    Contracts & Tenders, Wind Farm Update

    GE Renewable Energy (GE) has selected Denmark-based Global Wind Service (GWS) for 50 per cent of the service and maintenance scope at the Saint-Nazaire wind farm offshore France. Under the agreement, GWS will perform planned maintenance, including brake-in and annual maintenance along with corrective maintenance tasks such as troubleshooting and unplanned service. The service and […]

  • 17 July 2018
    Operations & Maintenance, Wind Farm Update

    EDF Energies Nouvelles (EN) has completed the layout of the operations and maintenance (O&M) base for its Saint-Nazaire offshore wind farm in France, and has hired a local architectural firm to design the O&M building to be built in La Turballe, with a focus on landscape and environment.

  • 2 February 2021
    Contracts & Tenders, Vessels

    BOA OCV has secured a contract with DEME Offshore to deploy its subsea construction vessel BOA Sub C at the Saint-Nazaire offshore wind project in France. BOA Sub C will begin working at Saint-Nazaire in the second quarter of the year for a period of 220 days firm plus options. The two companies previously worked […]

  • 22 September 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    GE Renewable Energy and Acta Marine have signed a charter contract for the Acta Auriga Service Operations Vessel (SOV), which will support the commissioning of 80 Haliade 6 MW turbines at the Saint-Nazaire offshore wind farm in France. Operating out of the Port of Saint-Nazaire, the vessel will assist in the mechanical completion and commissioning […]

  • 12 October 2020
    Contracts & Tenders, Wind Farm Update

    ProCon Wind Energy has won a contract to provide the electrical outfitting of the transition pieces for the Saint-Nazaire offshore wind project in France. Under the deal with Eiffage Métal, ProCon is providing the installation and commissioning of the electrical scope for the transition pieces. The company already began the work and is expected to complete […]

  • 21 April 2021
    Wind Farm Update

    The first 40 Haliade 150-6MW nacelles for the Saint-Nazaire offshore wind farm have exited GE Renewable Energy’s factory in Saint-Nazaire, France. GE dispatched the first nacelle for the project from its factory in Montoir-de-Bretagne in February, when it was transported to the wind turbine pre-assembly site in the Port of Saint-Nazaire. The company rolled out the first […]

  • 14 February 2019
    Business & Finance, Wind Farm Update

    EDF Energies Nouvelles and Enbridge have applied for funding with the European Investment Bank (EIB) for the Saint-Nazaire and Fécamp offshore wind projects in France. EIB has not disclosed the total cost and the approximate amount of the proposed finance that the companies applied for. Saint-Nazaire is being developed by Eolien Maritime France (EMF), a joint venture of EDF EN […]

  • 1 May 2015

    Groupement solidaire Artelia has been awarded project management contract at Saint-Nazaire by Grand Port Maritime (GPM) de Nantes. The Saint-Nazaire Port Authority’s contract is aiming to ensure the design and undertaking of work regarding an industrial project creating a platform for a future home for the logistics hub at Saint-Nazaire for storage, assembly and boarding […]

  • 27 April 2016
    Authorities, Business & Finance, Wind Farm Update

    France’s Loire-Atlantique prefecture has granted approval for the construction of the 480MW Saint-Nazaire offshore wind farm. The approval allows for the official start of the construction phase, and establishes the conditions for the installation and operation of the offshore wind farm which is being jointly developed by EDF-EN, Dong Energy, the Lorient-based Nass & Wind Offshore, and GE. The wind farm will […]

  • 11 May 2018
    Vessels, Wind Farm Update

    Fugro has started a geotechnical survey campaign on the 480MW Saint-Nazaire offshore wind farm in France.

  • 6 November 2017
    Vessels, Wind Farm Update

    BigLift’s heavy load carrier Big Sky has arrived in the Port of Eemshaven in the Netherlands loaded with the first six of the sixty-six GE Haliade nacelles to be installed on the 396MW Merkur offshore wind farm in the German North Sea.

  • 11 May 2015
    Business & Finance, Wind Farm Update

    Eolien Maritime France, a consortium made of EDF EN France, Dong Energy Power Holding and WPD Offshore GmbH, has issued an invitation to tender for wind turbine installation on three French offshore wind sites. A contract for each of the three lots will last for six years (72 months) from the date of award. Deadline for submission of tenders or […]

  • 2 July 2025
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore substation (OSS) of the 496 MW Dieppe Le Tréport offshore wind farm has been installed at its designated location 15 kilometres off the city of Le Tréport and 17 kilometres off the city of Dieppe in France. The substation, which was designed and built by Atlantique Offshore Energy, the Chantiers de l’Atlantique division […]

  • 22 September 2022
    Technology, Wind Farm Update

    French waters offshore Saint-Nazaire are buzzing with inaugural activity today (22 September) as the country’s first offshore wind farm was officially put into operation and, in a separate event, the world’s first offshore green hydrogen production platform was launched. As reported earlier today, French President Emmanuel Macron arrived at the Saint-Nazaire project site this morning […]

  • 31 August 2020
    Vessels, Wind Farm Update

    DEME’s vessels Neptune, D’Artagnan, and Bonny River have been deployed on the Saint-Nazaire offshore wind project, with some of the work now underway at the site located some 12 kilometres off the coast of the Guérande peninsula in France. The company’s cutter suction dredger D’Artagnan and trailing suction hopper dredger Bonny River are currently on […]