202 results found for 'Vineyard Wind 1'

202 results found for 'Vineyard Wind 1'
Order results by

A list of search results

  • 4 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    On 27 February, a turbine at the Vineyard Wind offshore wind project was struck by lightning. The GE Vernova Haliade-X 13 MW turbine had previously experienced a blade failure in July 2024. In July 2024, a blade from one of the GE Vernova’s Haliade-X turbines detached, which resulted in debris washing up on beaches on […]

  • 21 January 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The US Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) have completed the review and approved the revised Construction and Operations Plan (COP) for the Vineyard Wind 1 offshore wind farm. Last week, the federal government lifted the suspension on Vineyard Wind’s installation of the remaining GE Vernova […]

  • 14 July 2025
    Authorities, Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update, Wind Turbines

    The Town and County of Nantucket in Massachusetts and GE Vernova have reached a settlement agreement worth USD 10.5 million (approximately EUR 9 million), which the wind turbine OEM will pay to compensate the Town and local businesses for losses resulting from the failure of a turbine blade on the Vineyard Wind 1 offshore wind […]

  • 11 April 2025
    Fixed-Bottom, Foundations, Innovation, Project Updates, Supply Chain, Technology, Wind Farm Update

    RWE, in collaboration with Hydrotechnik Offshore, a Germany-based bubble curtain developer, has deployed the underwater noise abatement technology during monopile installation at the Sofia offshore wind farm, marking the first time the technology has been used in the UK. Currently under construction on Dogger Bank, 195 kilometres off the UK coast, the 1.4 GW Sofia […]

  • 2 April 2025
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting

    The signing of contracts with the selected winners in Massachusetts’ fourth offshore wind solicitation has been delayed once more, now expected to take place on or before 30 June. In September 2024, Massachusetts selected 1,087 MW of the multi-state 1,287 MW SouthCoast Wind project, with Rhode Island Energy awarding the remaining 200 MW. Massachusetts also selected Avangrid’s 791 MW […]

  • 2 April 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The town and county of Nantucket, Massachusetts, have filed an appeal in the US District Court for the District of Columbia against the US Bureau of Ocean Energy Management (BOEM) over its approval of the 2.4 GW SouthCoast Wind offshore wind project. Nantucket alleges that BOEM violated the National Historic Preservation Act (NHPA) and the […]

  • 20 January 2025
    Authorities, Planning & Permitting

    The signing of contracts with projects selected in Massachusetts’ fourth offshore wind solicitation has been delayed once more, with the new expected date being on or before 31 March. The execution of contracts, which had already been delayed to 15 January, is further postponed as the Electric Distribution Companies have filed a letter with the […]

  • 1 January 2025
    Business development, Equipment, Fixed-Bottom, Floating Wind, Operations & Maintenance, Project Updates, Supply Chain, Technology, Vessels, Wind Farm Update, Wind Turbines

    New wind turbine models, vessels and equipment, and project updates were the most read topics on offshoreWIND.biz in 2024. In this overview, we are bringing the ten most popular news in 2024. In January 2024, Siemens Gamesa received a EUR 30 million grant from the EU for a project called Highly Innovative Prototype of the […]

  • 15 January 2025
    Authorities, Fixed-Bottom, Floating Wind, Planning & Permitting

    NOTE: This article was updated on 15 January at 21:50 CET following information offshoreWIND.biz received, attributing the drafting of the executive order halting offshore wind activities on the US East Coast to Congressman Jefferson Van Drew instead of the US President-elect Donald Trump himself. The article was further amended to state that lease, rather than […]

  • 18 January 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US Bureau of Ocean Energy Management (BOEM) has approved the Construction and Operations Plan (COP) for the SouthCoast Wind offshore wind project. This is the final approval needed for the project from BOEM following the Record of Decision (ROD) from the Department of the Interior (DOI) in December 2024, the federal agency said on […]

  • 28 October 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner update. Prior to installation, the POLARIS and HOS RUGER […]

  • 24 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Following a July blade failure incident, GE Vernova plans to remove some blades and strengthen others at the Vineyard Wind 1 offshore wind farm in the US. The companies are implementing the incident and response action plan, which was announced in August. The plan outlined steps to safely remove the remainder of the damaged blade […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 9 September 2024
    Authorities, Planning & Permitting

    Massachusetts and Rhode Island have published the results of their first multi-state offshore wind solicitation, selecting nearly 2.9 GW of offshore wind power. As a part of the procurement, Massachusetts selected 2,678 MW in total from three projects and Rhode Island awarded 200 MW to one project. Massachusetts selected 1,087 MW of the multi-state 1,287 […]

  • 1 August 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Windar Renovables has manufactured and loaded the final batch of transition pieces (TPs) for the 806 MW Vineyard Wind 1 offshore wind farm in the United States. In 2019, Windar Renovables won a contract to manufacture, certify, assemble, inspect, store, and deliver TPs for the offshore wind project, being developed by Vineyard Wind, a joint […]

  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The blade failure event at the Dogger Bank A offshore wind farm last month was not caused by an installation or manufacturing issue but happened during the commissioning process, according to an analysis conducted by GE Vernova. The blade failure occurred on the morning of 22 August and, according to an update from the Dogger […]

  • 13 August 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine installation and operations. The blade incident […]

  • 22 August 2023
    Wind Farm Update

    The first turbine nacelles for the Vineyard Wind 1 offshore wind farm have arrived at the New Bedford Marine Commerce Terminal in Massachusetts, USA. United Heavy Lift transported the first nacelles for Vineyard Wind 1 from France using its UHL Felicity vessel. The offshore wind farm will feature 62 GE Haliade-X 13 MW turbines to be […]

  • 26 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Vineyard Wind 1 project is now delivering more than 136 MW to the electric grid in Massachusetts, making it the largest operating offshore wind project in the US. Vineyard Wind 1, the first large-scale offshore wind project in the US, now has ten turbines in operation totalling approximately 136 MW, enough to power 64,000 […]

  • 4 August 2022
    Operations & Maintenance, Wind Farm Update

    Avangrid has finalized an agreement to assume responsibility as the operations and management services provider for Vineyard Wind 1, the first commercial-scale offshore wind project in the United States. The 800 MW Vineyard Wind 1, a 50-50 joint venture between Avangrid and Copenhagen Infrastructure Partners (CIP) funds CI II and CI III, is currently under […]

  • 13 April 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Vineyard Wind has selected the US-based Southwire to design, manufacture, and install the onshore cables for Vineyard Wind 1, the first commercial-scale wind farm in the United States. Southwire’s facility in Huntersville, North Carolina, will manufacture the high voltage cable for the onshore portion of Vineyard Wind 1. ”We’re proud to partner with Southwire, a […]

  • 28 December 2023
    Business & Finance, Fixed-Bottom, Jobs & Recruitment

    Vineyard Wind 1, the 806 MW offshore wind farm that Copenhagen Infrastructure Partners (CIP) and Avangrid are building off Massachusetts, has created 937 union jobs during the two years of the project’s construction. With more jobs coming in 2024, Vineyard Wind 1 will have created more than 1,000 union jobs by the time the construction […]

  • 2 June 2022
    Contracts & Tenders, Wind Farm Update

    Norway-based DeepOcean has been awarded a contract to provide subsea services to Vineyard Wind 1, the first utility-scale offshore wind project in the US. Under the contract, DeepOcean will provide a range of subsea services including project management, engineering, ROV, tooling, and survey activities. The company will lead the project out of its office in […]

  • 25 July 2024
    Business & Finance, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The breakage of the blade on one of GE Vernova’s Haliade-X wind turbines at the Vineyard Wind 1 offshore wind farm in the US was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call on 24 July. Strazik also pointed out that a blade event that happened on a […]

  • 14 August 2024
    Authorities, Fixed-Bottom, Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has allowed Vineyard Wind to resume certain limited additional activities at the Vineyard Wind 1 offshore wind farm site. These include the installation of towers and nacelles but not (yet) the installation of the wind turbine blades. BSEE issued an update to the Suspension Order the […]

  • 30 August 2021
    Authorities, Operations & Maintenance

    The developer of the 800 MW Vineyard Wind 1 offshore wind farm is considering Tisbury Marine Terminal as a base for its operations and maintenance (O&M) activities, according to the latest documents available on the Martha’s Vineyard Commission’s website. Namely, the Commission is currently reviewing plans submitted by Tisbury Marine Terminal LLC (TMT), which is […]