190 results found for 'Vineyard Wind 1'

190 results found for 'Vineyard Wind 1'
Order results by

A list of search results

  • 26 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Vineyard Wind 1 project is now delivering more than 136 MW to the electric grid in Massachusetts, making it the largest operating offshore wind project in the US. Vineyard Wind 1, the first large-scale offshore wind project in the US, now has ten turbines in operation totalling approximately 136 MW, enough to power 64,000 […]

  • 1 August 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Windar Renovables has manufactured and loaded the final batch of transition pieces (TPs) for the 806 MW Vineyard Wind 1 offshore wind farm in the United States. In 2019, Windar Renovables won a contract to manufacture, certify, assemble, inspect, store, and deliver TPs for the offshore wind project, being developed by Vineyard Wind, a joint […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 25 July 2024
    Business & Finance, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The breakage of the blade on one of GE Vernova’s Haliade-X wind turbines at the Vineyard Wind 1 offshore wind farm in the US was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call on 24 July. Strazik also pointed out that a blade event that happened on a […]

  • 30 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The installation of transition pieces (TPs) is about to commence at Vineyard Wind 1, America’s first large-scale offshore wind farm. Beginning next month, DEME Group’s jack-up vessel Sea Challenger will begin placing TPs at 17 monopile locations in lease area OCS-A 0501. The campaign will continue through June 2024. The units are being manufactured by […]

  • 16 July 2024
    Project Updates, Wind Farm Update

    NOTE: The article was updated on 19 July with more information about the GE Vernova turbine blade incident at the Vineyard Wind project.  A turbine blade at the Vineyard Wind 1 offshore wind farm in the US has been damaged, leading to an investigation by the blade’s manufacturer, GE Vernova. Vineyard Wind, a joint venture […]

  • 18 July 2024
    Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has issued an order instructing Vineyard Wind to halt electricity production from all wind turbines following a blade failure incident on 13 July. The 800 MW Vineyard Wind offshore wind farm is planned to feature 62 GE Vernova’s Haliade-X 13 MW wind turbines, each with a […]

  • 13 August 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine installation and operations. The blade incident […]

  • 14 August 2024
    Authorities, Fixed-Bottom, Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has allowed Vineyard Wind to resume certain limited additional activities at the Vineyard Wind 1 offshore wind farm site. These include the installation of towers and nacelles but not (yet) the installation of the wind turbine blades. BSEE issued an update to the Suspension Order the […]

  • 18 July 2024
    Business & Finance, Business development, Collaboration, Outlook & Strategy, Research & Development

    EDF Renewables and Repsol have signed an exclusivity agreement to collaborate on future offshore wind tenders in Spain and Portugal. According to the press release, this collaboration combines Repsol’s commitment to multi-energy growth and its knowledge of the Spanish and Portuguese markets with EDF Renewables’ technological experience. Repsol said that it expects to have 9,000 […]

  • 17 July 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Following a blade damage incident that took place on 13 July at its 800 MW offshore wind project in Massachusetts, Vineyard Wind has revealed that it is mobilising debris recovery teams on Nantucket. Vineyard Wind, a joint venture between Iberdrola’s US subsidiary Avangrid and Denmark’s Copenhagen Infrastructure Partners (CIP), announced on 16 July that it […]

  • 26 June 2024
    Business & Finance, Contracts & Tenders, Floating Wind, Supply Chain, Wind Turbines

    Denmark’s Floating Power Plant has purchased a wind turbine from Siemens Gamesa Renewable Energy for its flagship demonstrator project located off the coast of Gran Canaria. According to the company, the selected wind turbine, a 4.3 MW SWT-DD-120 from Siemens Gamesa, fits Floating Power Plant’s requirements for a well-established technology. The wind turbine generator will […]

  • 26 July 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    More than a quarter of wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 27 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will comprise are in place, according to information in Equinor’s results for the […]

  • 18 July 2024
    Business & Finance, Business development, Ports & Logistics, Research & Development

    NIRAS has been selected by the Asian Development Bank (ADB) to prepare pre-feasibility studies to assess the expansion of several ports for use as offshore wind ports. The Denmark-headquartered consultancy company has been commissioned by ADB on behalf of the Philippine government. Under the contract, NIRAS will prepare the pre-feasibility studies for the expansion of […]

  • 2 July 2024
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Avangrid, a US renewable energy company majority-owned by Spanish Iberdrola, has received the authorisation to build and operate its New England Wind offshore wind farms from the Bureau of Ocean Energy Management (BOEM). This is the final approval needed from BOEM for the two projects offshore Massachusetts totalling 2.6 GW, following the federal agency’s Record […]

  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The blade failure event at the Dogger Bank A offshore wind farm last month was not caused by an installation or manufacturing issue but happened during the commissioning process, according to an analysis conducted by GE Vernova. The blade failure occurred on the morning of 22 August and, according to an update from the Dogger […]

  • 19 July 2024
    Contracts & Tenders, Grid Connection, Offshore Platforms, Onshore Infrastructure, Supply Chain

    The transmission system operator (TSO) 50Hertz has awarded the consortium comprising Dragados Offshore, a subsidiary of Cobra IS, and Siemens Energy a EUR 2.9 billion contract to design, build, and install two electrical conversion stations. The consortium’s scope of work consists of supplying an offshore converter for the LanWin3 grid connection project in the North […]

  • 19 August 2024
    Business & Finance, Fixed-Bottom, Foundations, Supply Chain

    Japan-based Sumitomo Corporation has acquired an equity stake in EEW Offshore Wind Holding, one of three new holding companies EEW Group founded to organise its business more efficiently, according to the German foundation manufacturer. According to EEW Group, Sumitomo’s stake has been in commercial effect since 1 July. The Group said on 19 August that, […]

  • 9 September 2024
    Authorities, Planning & Permitting

    Massachusetts and Rhode Island have published the results of their first multi-state offshore wind solicitation, selecting nearly 2.9 GW of offshore wind power. As a part of the procurement, Massachusetts selected 2,678 MW in total from three projects and Rhode Island awarded 200 MW to one project. Massachusetts selected 1,087 MW of the multi-state 1,287 […]

  • 26 July 2024
    Authorities, Business & Finance, Business development, Floating Wind, Planning & Permitting, R&D, Research & Development

    The US Department of Energy’s (DOE’s) Wind Energy Technologies Office (WETO) has launched the Offshore Wind National and Regional Research and Development Funding Opportunity, allocating USD 48.6 million to projects designed to address several key needs in offshore wind development. The areas include accelerating research and development of floating offshore wind platforms; exploring innovations for […]

  • 1 August 2024
    Business & Finance, Business development, Contribution, Industry, Jobs & Recruitment, Supply Chain

    This is an op-ed piece by Sam Salustro, Vice President of Strategic Communication at Oceantic Network, the US offshore renewable energy industry organisation.  Six months occupied with questions about the upcoming election have muddied the waters, shifting the conversation about offshore wind energy away from the real groundwork being laid and progress already underway in […]

  • 9 July 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Iberdrola, through its US subsidiary Avangrid, and Virginia Electric and Power Company, a wholly-owned subsidiary of Dominion Energy, have signed an agreement under which Dominion will acquire the Kitty Hawk North Wind offshore wind lease area. The site, located some 40 kilometres north of the under-construction Coastal Virginia Offshore Wind (CVOW) project, would be renamed CVOW-South, […]

  • 15 April 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Read the latest news on CVOW here: 2.6 GW US Project Receives Final Federal Permit, Monopile Installation to Start in May The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, has sailed out of Invergordon in Scotland and is now en route to the United States, where it will […]

  • 22 April 2024
    Authorities, Planning & Permitting, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The New York State Energy Research and Development Authority (NYSERDA) has cancelled three offshore wind projects with a combined capacity of over 4 GW due to ”technical and commercial complexities between provisional awardees and their partners”. In October 2023, NYSERDA provisionally awarded three offshore wind projects, subject to the successful conclusion of contract negotiations. These […]

  • 14 August 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    RWE plans to participate in one of the upcoming offshore wind solicitations in New York with its 1,314 MW Community Offshore Wind project, one of the three cancelled earlier this year as GE Vernova dropped plans for the 18 MW Haliade-X wind turbine which was planned to be used in the projects. Community Offshore Wind […]

  • 16 August 2024
    Fixed-Bottom, Floating Wind, Ports & Logistics

    Construction work on converting a former oil- and coal-fired power plant site in Salem, Massachusetts, into a terminal serving the offshore wind industry has started. On 15 August, Crowley Wind Services, the company managing the redevelopment and the new terminal’s operator, held a groundbreaking ceremony at the site that will become the Salem Offshore Wind […]