201 results found for 'Vineyard Wind 1'

201 results found for 'Vineyard Wind 1'
Order results by

A list of search results

  • 4 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    On 27 February, a turbine at the Vineyard Wind offshore wind project was struck by lightning. The GE Vernova Haliade-X 13 MW turbine had previously experienced a blade failure in July 2024. In July 2024, a blade from one of the GE Vernova’s Haliade-X turbines detached, which resulted in debris washing up on beaches on […]

  • 21 January 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The US Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) have completed the review and approved the revised Construction and Operations Plan (COP) for the Vineyard Wind 1 offshore wind farm. Last week, the federal government lifted the suspension on Vineyard Wind’s installation of the remaining GE Vernova […]

  • 11 April 2025
    Fixed-Bottom, Foundations, Innovation, Project Updates, Supply Chain, Technology, Wind Farm Update

    RWE, in collaboration with Hydrotechnik Offshore, a Germany-based bubble curtain developer, has deployed the underwater noise abatement technology during monopile installation at the Sofia offshore wind farm, marking the first time the technology has been used in the UK. Currently under construction on Dogger Bank, 195 kilometres off the UK coast, the 1.4 GW Sofia […]

  • 1 January 2025
    Business development, Equipment, Fixed-Bottom, Floating Wind, Operations & Maintenance, Project Updates, Supply Chain, Technology, Vessels, Wind Farm Update, Wind Turbines

    New wind turbine models, vessels and equipment, and project updates were the most read topics on offshoreWIND.biz in 2024. In this overview, we are bringing the ten most popular news in 2024. In January 2024, Siemens Gamesa received a EUR 30 million grant from the EU for a project called Highly Innovative Prototype of the […]

  • 28 October 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner update. Prior to installation, the POLARIS and HOS RUGER […]

  • 2 April 2025
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting

    The signing of contracts with the selected winners in Massachusetts’ fourth offshore wind solicitation has been delayed once more, now expected to take place on or before 30 June. In September 2024, Massachusetts selected 1,087 MW of the multi-state 1,287 MW SouthCoast Wind project, with Rhode Island Energy awarding the remaining 200 MW. Massachusetts also selected Avangrid’s 791 MW […]

  • 24 October 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    Following a July blade failure incident, GE Vernova plans to remove some blades and strengthen others at the Vineyard Wind 1 offshore wind farm in the US. The companies are implementing the incident and response action plan, which was announced in August. The plan outlined steps to safely remove the remainder of the damaged blade […]

  • 2 April 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The town and county of Nantucket, Massachusetts, have filed an appeal in the US District Court for the District of Columbia against the US Bureau of Ocean Energy Management (BOEM) over its approval of the 2.4 GW SouthCoast Wind offshore wind project. Nantucket alleges that BOEM violated the National Historic Preservation Act (NHPA) and the […]

  • 20 January 2025
    Authorities, Planning & Permitting

    The signing of contracts with projects selected in Massachusetts’ fourth offshore wind solicitation has been delayed once more, with the new expected date being on or before 31 March. The execution of contracts, which had already been delayed to 15 January, is further postponed as the Electric Distribution Companies have filed a letter with the […]

  • 15 January 2025
    Authorities, Fixed-Bottom, Floating Wind, Planning & Permitting

    NOTE: This article was updated on 15 January at 21:50 CET following information offshoreWIND.biz received, attributing the drafting of the executive order halting offshore wind activities on the US East Coast to Congressman Jefferson Van Drew instead of the US President-elect Donald Trump himself. The article was further amended to state that lease, rather than […]

  • 18 January 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US Bureau of Ocean Energy Management (BOEM) has approved the Construction and Operations Plan (COP) for the SouthCoast Wind offshore wind project. This is the final approval needed for the project from BOEM following the Record of Decision (ROD) from the Department of the Interior (DOI) in December 2024, the federal agency said on […]

  • 9 September 2024
    Authorities, Planning & Permitting

    Massachusetts and Rhode Island have published the results of their first multi-state offshore wind solicitation, selecting nearly 2.9 GW of offshore wind power. As a part of the procurement, Massachusetts selected 2,678 MW in total from three projects and Rhode Island awarded 200 MW to one project. Massachusetts selected 1,087 MW of the multi-state 1,287 […]

  • 23 August 2024
    Fixed-Bottom, Manufacturing, Supply Chain, Wind Farm Update, Wind Turbines

    This article was updated at 15:05 CET on 23 August 2024 with a statement from GE Vernova. One of the already installed wind turbine blades at Dogger Bank A offshore wind farm, currently under construction in the UK, has sustained damage and failed. The blade failure occurred on the morning of 22 August and, according […]

  • 2 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The blade failure event at the Dogger Bank A offshore wind farm last month was not caused by an installation or manufacturing issue but happened during the commissioning process, according to an analysis conducted by GE Vernova. The blade failure occurred on the morning of 22 August and, according to an update from the Dogger […]

  • 13 August 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Vineyard Wind and GE Vernova have set out an action plan covering several main tasks following the blade incident at Vineyard Wind 1 offshore wind farm. The plan includes removing the remainder of the damaged blade on the turbine AW-38, continuing the collection of any debris, and resuming turbine installation and operations. The blade incident […]

  • 14 August 2024
    Authorities, Fixed-Bottom, Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has allowed Vineyard Wind to resume certain limited additional activities at the Vineyard Wind 1 offshore wind farm site. These include the installation of towers and nacelles but not (yet) the installation of the wind turbine blades. BSEE issued an update to the Suspension Order the […]

  • 19 August 2024
    Business & Finance, Fixed-Bottom, Foundations, Supply Chain

    Japan-based Sumitomo Corporation has acquired an equity stake in EEW Offshore Wind Holding, one of three new holding companies EEW Group founded to organise its business more efficiently, according to the German foundation manufacturer. According to EEW Group, Sumitomo’s stake has been in commercial effect since 1 July. The Group said on 19 August that, […]

  • 1 August 2024
    Fixed-Bottom, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Windar Renovables has manufactured and loaded the final batch of transition pieces (TPs) for the 806 MW Vineyard Wind 1 offshore wind farm in the United States. In 2019, Windar Renovables won a contract to manufacture, certify, assemble, inspect, store, and deliver TPs for the offshore wind project, being developed by Vineyard Wind, a joint […]

  • 25 July 2024
    Business & Finance, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The breakage of the blade on one of GE Vernova’s Haliade-X wind turbines at the Vineyard Wind 1 offshore wind farm in the US was caused by a manufacturing deviation, the company’s CEO Scott Strazik revealed during an earnings call on 24 July. Strazik also pointed out that a blade event that happened on a […]

  • 18 July 2024
    Project Updates, Wind Farm Update

    The US Bureau of Safety and Environmental Enforcement (BSEE) has issued an order instructing Vineyard Wind to halt electricity production from all wind turbines following a blade failure incident on 13 July. The 800 MW Vineyard Wind offshore wind farm is planned to feature 62 GE Vernova’s Haliade-X 13 MW wind turbines, each with a […]

  • 16 July 2024
    Project Updates, Wind Farm Update

    NOTE: The article was updated on 19 July with more information about the GE Vernova turbine blade incident at the Vineyard Wind project.  A turbine blade at the Vineyard Wind 1 offshore wind farm in the US has been damaged, leading to an investigation by the blade’s manufacturer, GE Vernova. Vineyard Wind, a joint venture […]

  • 26 July 2024
    Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    More than a quarter of wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 27 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will comprise are in place, according to information in Equinor’s results for the […]

  • 18 July 2024
    Business & Finance, Business development, Collaboration, Outlook & Strategy, Research & Development

    EDF Renewables and Repsol have signed an exclusivity agreement to collaborate on future offshore wind tenders in Spain and Portugal. According to the press release, this collaboration combines Repsol’s commitment to multi-energy growth and its knowledge of the Spanish and Portuguese markets with EDF Renewables’ technological experience. Repsol said that it expects to have 9,000 […]

  • 26 July 2024
    Authorities, Business & Finance, Business development, Floating Wind, Planning & Permitting, R&D, Research & Development

    The US Department of Energy’s (DOE’s) Wind Energy Technologies Office (WETO) has launched the Offshore Wind National and Regional Research and Development Funding Opportunity, allocating USD 48.6 million to projects designed to address several key needs in offshore wind development. The areas include accelerating research and development of floating offshore wind platforms; exploring innovations for […]

  • 26 June 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Vineyard Wind 1 project is now delivering more than 136 MW to the electric grid in Massachusetts, making it the largest operating offshore wind project in the US. Vineyard Wind 1, the first large-scale offshore wind project in the US, now has ten turbines in operation totalling approximately 136 MW, enough to power 64,000 […]

  • 17 July 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Following a blade damage incident that took place on 13 July at its 800 MW offshore wind project in Massachusetts, Vineyard Wind has revealed that it is mobilising debris recovery teams on Nantucket. Vineyard Wind, a joint venture between Iberdrola’s US subsidiary Avangrid and Denmark’s Copenhagen Infrastructure Partners (CIP), announced on 16 July that it […]